Monthly State Let Maintenance Report For Dallas District As Of Nov 10, 2024 Page 4 Of 5

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCOLLIN
HighwayUS0075
FromSH 190/PGBT
ToTHROCKMORTON
CSJ6450-97-001
Proj IDRMC - 645097001
Work TypeREPAIR/REPLACE CONCRETE BARRIER
 
0.010377800.0042064.5011.1
Work Order02-27-24
Work Began03-05-24
Work Completed
Time Computed03-05-24
Contract Working Days365
Addl Days Granted0
Working Days Charged235
Percent Time Used64
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6450-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234209
Totals377800.000.0042064.5011.1

CountyCOLLIN
HighwayFM0455
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6451-09-001
Proj IDRMC - 645109001
Work TypeCULVERT EXTENSION & CROSS DRAINAGE
 
0.010397771.50400702.95100.0
Work Order04-16-24
Work Began05-06-24
Work Completed10-22-24
Time Computed04-23-24
Contract Working Days44
Addl Days Granted0
Working Days Charged41
Percent Time Used93
Contractor(s)
AAD CONTRACTING INC.
SUBCONTRACTOR(S) FOR CCSJ: 6451-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244209
Totals397771.500.00400702.95100.0

CountyDALLAS
HighwayIH0030
FromVARIOUS ROADWAYS IN THE EAST DALLAS
ToCOUNTY MAINTENANCE SECTION
CSJ6452-25-001
Proj IDRMC - 645225001
Work TypeBUNDLED BID
 
0.01024325136.005664000.3023.2
Work Order05-13-24
Work Began04-26-24
Work Completed
Time Computed04-26-24
Contract Working Days730
Addl Days Granted0
Working Days Charged183
Percent Time Used25
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6452-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244212
Totals24325136.001285760.205664000.3023.2

CountyDALLAS
HighwayIH0030
FromVARIOUS ROADWAYS IN THE WEST DALLAS
ToCOUNTY MAINTENANCE SECTION
CSJ6452-27-001
Proj IDRMC - 645227001
Work TypeBUNDLED BID
 
0.01026852805.563594725.9413.3
Work Order05-16-24
Work Began05-26-24
Work Completed
Time Computed05-26-24
Contract Working Days730
Addl Days Granted0
Working Days Charged153
Percent Time Used20
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6452-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03244204
Totals26852805.561035949.603594725.9413.3

CountyKAUFMAN
HighwayFM0740
FromVARIOUS ROADWAYS IN THE KAUFMAN -
ToROCKWALL MAINTENANCE SECTION
CSJ6453-05-001
Proj IDRMC - 645305001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.0101990800.001363299.7968.4
Work Order02-01-24
Work Began02-01-24
Work Completed
Time Computed02-08-24
Contract Working Days365
Addl Days Granted365
Working Days Charged268
Percent Time Used36
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6453-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234025
Totals1990800.00288719.551363299.7968.4

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6456-15-001
Proj IDRMC - 645615001
Work TypeRAISED PAVEMENT MARKERS
 
0.010388191.00368178.36100.0
Work Order02-27-24
Work Began04-01-24
Work Completed09-18-24
Time Computed03-05-24
Contract Working Days84
Addl Days Granted0
Working Days Charged54
Percent Time Used64
Contractor(s)
FC TRAFFIC CONTROL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6456-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244015
Totals388191.000.00368178.36100.0

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6456-95-001
Proj IDRMC - 645695001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010428320.00202513.0047.2
Work Order03-26-24
Work Began03-27-24
Work Completed
Time Computed03-27-24
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
SUPERIOR TRAFFIC CONTROL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6456-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244014
Totals428320.0011250.00202513.0047.2

CountyDENTON
HighwayFM1171
FromVARIOUS ROADWAYS
ToDENTON COUNTY MAINTENANCE SECTION
CSJ6457-03-001
Proj IDRMC - 645703001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.0101030771.00961918.3793.3
Work Order03-19-24
Work Began04-22-24
Work Completed
Time Computed04-01-24
Contract Working Days38
Addl Days Granted0
Working Days Charged38
Percent Time Used100
Contractor(s)
SILVER CREEK CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6457-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244012
Totals1030771.000.00961918.3793.3

CountyNAVARRO
HighwayIH0045
FromVARIOUS ROADWAYS IN
ToNAVARRO COUNTY
CSJ6457-67-001
Proj IDRMC - 645767001
Work TypeHERBICIDE/INSECTICIDE
 
0.010383162.16157221.0041.0
Work Order02-20-24
Work Began02-28-24
Work Completed
Time Computed02-28-24
Contract Working Days365
Addl Days Granted0
Working Days Charged241
Percent Time Used66
Contractor(s)
OPTERRA SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6457-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234026
Totals383162.160.00157221.0041.0

CountyNAVARRO
HighwayIH0045
FromVARIOUS ROADWAYS
ToNAVARRO COUNTY MAINTENANCE SECTION
CSJ6457-71-001
Proj IDRMC - 645771001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.0101229508.00947928.5677.0
Work Order04-04-24
Work Began04-12-24
Work Completed
Time Computed04-12-24
Contract Working Days365
Addl Days Granted0
Working Days Charged197
Percent Time Used53
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6457-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244016
Totals1229508.0099289.40947928.5677.0

CountyDALLAS
HighwayIH0020
FromVARIOUS LOCATIONS IN WEST
ToDALLAS COUNTY MAINTENANCE SECTIONS
CSJ6457-75-001
Proj IDRMC - 645775001
Work TypeVEGETATION MANAGEMENT
 
0.010775762.00319867.0041.2
Work Order03-11-24
Work Began03-11-24
Work Completed
Time Computed03-18-24
Contract Working Days365
Addl Days Granted0
Working Days Charged229
Percent Time Used62
Contractor(s)
OPTERRA SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6457-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234210
Totals775762.000.00319867.0041.2

CountyDALLAS
HighwayIH0020
FromVARIOUS LOCATIONS IN WEST
ToDALLAS COUNTY MAINTENANCE SECTIONS
CSJ6457-77-001
Proj IDRMC - 645777001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010638620.00285925.0044.7
Work Order03-04-24
Work Began03-11-24
Work Completed
Time Computed03-11-24
Contract Working Days365
Addl Days Granted0
Working Days Charged229
Percent Time Used62
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6457-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234027
Totals638620.000.00285925.0044.7

CountyELLIS
HighwayUS0067
FromVARIOUS ROADWAYS IN
ToELLIS COUNTY MAINTENANCE SECTION
CSJ6459-25-001
Proj IDRMC - 645925001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.0102418807.702361423.1297.6
Work Order04-03-24
Work Began05-06-24
Work Completed
Time Computed05-06-24
Contract Working Days115
Addl Days Granted15
Working Days Charged60
Percent Time Used46
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6459-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244019
Totals2418807.700.002361423.1297.6

CountyDALLAS
HighwaySS0408
FromVARIOUS ROADWAYS IN THE SOUTHWEST
ToDALLAS COUNTY MAINTENANCE SECTIONS
CSJ6460-70-001
Proj IDBPM - 646070001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.010260661.00219479.5084.2
Work Order05-23-24
Work Began06-04-24
Work Completed
Time Computed05-28-24
Contract Working Days67
Addl Days Granted0
Working Days Charged23
Percent Time Used34
Contractor(s)
ICOS MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6460-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03244010
Totals260661.000.00219479.5084.2

CountyDALLAS
HighwaySH0310
FromON SH 310 IN
ToSOUTHEAST DALLAS COUNTY MAINTENANCE
CSJ6460-89-001
Proj IDRMC - 646089001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.0101011656.00811889.5480.2
Work Order07-02-24
Work Began07-12-24
Work Completed
Time Computed07-12-24
Contract Working Days58
Addl Days Granted0
Working Days Charged58
Percent Time Used100
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6460-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03244205
Totals1011656.000.00811889.5480.2

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6460-92-001
Proj IDRMC - 646092001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.010650985.00559922.9886.0
Work Order08-02-24
Work Began09-16-24
Work Completed
Time Computed08-09-24
Contract Working Days70
Addl Days Granted0
Working Days Charged34
Percent Time Used48
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6460-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06244211
Totals650985.00402529.98559922.9886.0

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE EAST DALLAS
ToCOUNTY MAINTENANCE SECTIONS
CSJ6461-81-001
Proj IDRMC - 646181001
Work TypeREFLECTORIZED PAVEMENT MARKINGS & MARKE
 
0.0101498435.32332485.4022.1
Work Order06-19-24
Work Began06-26-24
Work Completed
Time Computed06-26-24
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
TRAFFIC HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6461-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244209
Totals1498435.3289929.81332485.4022.1

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE WEST DALLAS
ToCOUNTY MAINTENANCE SECTIONS
CSJ6461-82-001
Proj IDRMC - 646182001
Work TypeREFLECTORIZED PAVEMENT MARKINGS & MARKE
 
0.0101416294.00177385.7112.5
Work Order06-25-24
Work Began07-02-24
Work Completed
Time Computed07-02-24
Contract Working Days365
Addl Days Granted0
Working Days Charged116
Percent Time Used31
Contractor(s)
STRIPE-A-ZONE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6461-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244009
Totals1416294.00164529.71177385.7112.5

CountyNAVARRO
HighwayIH0045
FromNAVARRO
ToNAVARRO COUNTY MAINTENANCE SECTION
CSJ6461-84-001
Proj IDRMC - 646184001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010635909.0077645.5012.2
Work Order07-03-24
Work Began07-11-24
Work Completed
Time Computed07-11-24
Contract Working Days365
Addl Days Granted0
Working Days Charged107
Percent Time Used29
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6461-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05244009
Totals635909.0025032.0077645.5012.2

CountyDALLAS
HighwayUS0067
FromVARIOUS ROADWAYS IN
ToWEST DALLAS COUNTY MAINTENANCE
CSJ6462-23-001
Proj IDRMC - 646223001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010979868.50855799.8787.3
Work Order06-19-24
Work Began10-13-24
Work Completed
Time Computed09-01-24
Contract Working Days26
Addl Days Granted0
Working Days Charged6
Percent Time Used23
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6462-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244013
Totals979868.50855799.87855799.8787.3

page 1 | page 2 | page 3 | page 4 | page 5