Monthly State Let Construction Report For Lufkin District As Of Apr 7, 2016 Page 5 Of 5

Last Update: Thursday, April 7, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyNACOGDOCHES
Highway SL 224
From SH 7
To FM 2259
CSJ 2560-01-076
Proj ID STP 2016(425)
Work Type RESURFACE WITH THIN OVERLAY MIXTURE
 
5.189 789787.24 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-09-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 15
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2560-01-076
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163033
Totals 789787.24 0.00 0.00 0.0

CountyANGELINA
Highway FM 706
From US 69
To SH 103
CSJ 2959-01-009
Proj ID STP 1502(185)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
4.914 638068.30 7163.00 647314.39 99.9
Work Order 06-30-15
Work Began 08-19-15
Work Completed  
Time Computed 07-31-15
Contract Working Days 110
Addl Days Granted 0
Working Days Charged 107
Percent Time Used 97
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2959-01-009
PANOLA SIGN & BARRICADE, INC.(1.29%)
FREDONIA CONSTRUCTION SERVICES (0.00%)
J.P. ABNER STUMP GRINDING & TREE SERVICE (0.19%)
Contract # 05153011
Totals 638068.30 7163.00 647314.39 99.9

CountySHELBY
Highway LP 500
From US 96 (N)
To SH 7 EAST OF CENTER
CSJ 3315-01-016
Proj ID STP 2012(648)
Work Type GR, STR, BASE & SURF
 
3.338 11879175.22 50435.36 12771931.84 99.9
Work Order 09-24-12
Work Began 11-01-12
Work Completed  
Time Computed 11-01-12
Contract Working Days 462
Addl Days Granted 224
Working Days Charged 690
Percent Time Used 100
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 3315-01-016
HIGHWAY INTELLIGENT TRAFFIC SYSTEMS, CORP. (0.89%)
MOORE BROTHERS CONSTRUCTION COMPANY( 21.73%)
NORTH TEXAS REBAR, LLC (0.62%)
RICE ENVIRONMENTAL SERVICES(0.31%)
S & S PAINTING (0.11%)
TEX OP CONSTRUCTION, LP(0.02%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.46%)
W. W. FOUNDATION DRILLING, LTD.(1.07%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.32%)
HIGHWAY TECHNOLOGIES, INC. (0.00%)
FBL & ASSOCIATES (0.79%)
S & R DOZER, INC.(0.73%)
SILVA CONTRACTING COMPANY, INC.(2.02%)
MCL CONTRACTING, LLC (0.68%)
L. S. EQUIPMENT CO., INC.(0.19%)
HOUSTON SAWING & DRILLING(0.07%)
DUSTROL, INC.(0.04%)
Contract # 07123206
Totals 11879175.22 50435.36 12771931.84 99.9

CountyNACOGDOCHES
Highway FM 3314
From 0.9 MI W OF US 59
To US 59 RAMP
CSJ 3490-01-003
Proj ID STP 2015(619)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
0.874 548619.07 0.00 499603.50 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-23-15
Work Began 04-21-15
Work Completed 09-16-15
Time Computed 04-08-15
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 100
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 3490-01-003
AMERICAN REMEDIATION OPTIONS, INC. (5.18%)
A R BROTHERS CONSTRUCTION SERVICES, INC. (6.06%)
MOORE BROTHERS CONSTRUCTION COMPANY( 34.92%)
PANOLA SIGN & BARRICADE, INC.(0.73%)
SANDHILL FOUNDATION, LLC (0.91%)
STRIPING TECHNOLOGY, L.P.(3.90%)
Contract # 02153013
Totals 548619.07 0.00 499603.50 100.0

page 1 | page 2 | page 3 | page 4 | page 5