Monthly State Let Construction Report For Odessa District As Of Nov 10, 2024 Page 3 Of 4

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-239
Proj IDC 906-00-239
Work TypeTRAFFIC CONTROL DEVICES
 
705606.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days21
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MIJELUM, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-239
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243217
Totals705606.100.000.000.0

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-257
Proj IDC 906-00-257
Work TypeTRAFFIC CONTROL DEVICES
 
850900.00831173.1997.6
Work Order05-10-23
Work Began08-21-23
Work Completed
Time Computed09-08-23
Contract Working Days106
Addl Days Granted70
Working Days Charged76
Percent Time Used43
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-257
FC TRAFFIC CONTROL, INC. (0.24)
MICA CORPORATION (2.71)
Contract #04233035
Totals850900.0031921.00831173.1997.6

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-267
Proj IDC 906-00-267
Work TypeTRAFFIC CONTROL DEVICES
 
1139465.001220314.5199.9
Work Order05-17-23
Work Began09-11-23
Work Completed
Time Computed09-11-23
Contract Working Days79
Addl Days Granted7
Working Days Charged99
Percent Time Used115
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-267
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04233224
Totals1139465.000.001220314.5199.9

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-268
Proj IDC 906-00-268
Work TypeTRAFFIC CONTROL DEVICES
 
5500864.552695992.7249.0
Work Order01-04-24
Work Began08-13-24
Work Completed
Time Computed07-03-24
Contract Working Days180
Addl Days Granted0
Working Days Charged78
Percent Time Used43
Contractor(s)
MICA CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-268
WILLIS ELECTRIC CO., LP (10.96)
APOLLO CONSTRUCTORS, INC. (9.18)
COPPELL CONSTRUCTION CO., INC. (3.71)
HJC FARMS, INC. (2.09)
Contract #12233210
Totals5500864.55953224.372695992.7249.0

CountyECTOR
HighwayVA
FromIH 10 - 2.2 MI W OF PECOS COUNTY LINE
ToIH 10 - 4.2 MI W OF FM 1776
CSJ0906-00-271
Proj IDF 2024(381)
Work TypeTRAFFIC CONTROL DEVICES
 
831393.820.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-24-24
Work Began10-23-24
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LIGHT IT UP ELECTRIC
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-271
APOLLO CONSTRUCTORS, INC. (28.78)
BARRICADES UNLIMITED (4.81)
Contract #06243053
Totals831393.820.000.000.0

CountyECTOR
HighwayVA
FromDISTRICTWIDE
To.
CSJ0906-00-282
Proj IDBR 2024(781)
Work TypeBRIDGE MAINTENANCE
 
2165724.000.000.0
Work Order05-03-24
Work Began00-00-00
Work Completed
Time Computed08-02-24
Contract Working Days330
Addl Days Granted0
Working Days Charged35
Percent Time Used10
Contractor(s)
AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-282
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243215
Totals2165724.000.000.000.0

CountyMIDLAND
HighwayCS
FromAT SCHARBAUER DRAW
To.
CSJ0906-32-050
Proj IDBR 2B23(292)
Work TypeBRIDGE REPLACEMENT
 
1625626.50444600.8427.3
CountyMIDLAND
HighwayCS
FromAT MIDLAND DRAW
To.
CSJ0906-32-058
Proj IDBR 2B23(292)
Work TypeBRIDGE REPLACEMENT
 
910623.5063182.506.9
CountyMIDLAND
HighwayCS
FromAT MIDLAND DRAW
To.
CSJ0906-32-061
Proj IDBR 2B23(292)
Work TypeBRIDGE REPLACEMENT
 
1360388.50124542.509.1
Work Order04-18-24
Work Began09-09-24
Work Completed
Time Computed07-18-24
Contract Working Days174
Addl Days Granted0
Working Days Charged36
Percent Time Used20
Contractor(s)
DELGADO'S CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0906-32-050
BARRICADES UNLIMITED (0.33)
TRP CONSTRUCTION GROUP, LLC (0.71)
J. R. (JOE) RAMON & SONS, INC. (3.01)
Z-TEK CONSTRUCTION, LLC (13.17)
Contract #01243024
Totals3896638.5014820.00632325.8416.2

CountyMIDLAND
HighwayCS
FromAT SCHARBAUER DRAW
To.
CSJ0906-32-052
Proj IDBR 2025(147)
Work TypeBRIDGE REPLACEMENT
 
1912116.950.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days84
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0906-32-052
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10243226
Totals1912116.950.000.000.0

CountyMIDLAND
HighwayCS
FromBELMONT ST
To.
CSJ0906-32-060
Proj IDSTP 2B23(013)HESG
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
496352.87493320.0099.3
Work Order09-13-23
Work Began06-10-24
Work Completed
Time Computed12-13-23
Contract Working Days91
Addl Days Granted0
Working Days Charged71
Percent Time Used78
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0906-32-060
BARRICADES UNLIMITED (1.05)
KING & GEORGE, LLC (1.84)
Contract #08233263
Totals496352.8714032.43493320.0099.3

CountyMARTIN
HighwayFM 846
FromSH 137
ToHOWARD COUNTY LINE
CSJ1155-01-017
Proj IDC 1155-1-17
Work TypeREHABILITATION OF EXISTING ROAD
 
26967769.445103.000.0
Work Order07-17-24
Work Began00-00-00
Work Completed
Time Computed10-16-24
Contract Working Days534
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1155-01-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06243207
Totals26967769.445103.005103.000.0

CountyMIDLAND
HighwaySL 250
FromAT NORTH A STREET
To.
CSJ1188-02-118
Proj IDC 1188-2-118
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1609466.841544862.7195.9
Work Order02-02-24
Work Began05-28-24
Work Completed
Time Computed05-03-24
Contract Working Days64
Addl Days Granted3
Working Days Charged60
Percent Time Used89
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1188-02-118
WILLIS ELECTRIC CO., LP (0.52)
BARRICADES UNLIMITED (0.89)
DK CONTRACTING, LLC (0.92)
TRP CONSTRUCTION GROUP, LLC (2.91)
K. L. DURHAM CONSTRUCTION, L.L.C. (0.59)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.52)
D & E LOGISTICS, LLC (0.92)
Contract #01243231
Totals1609466.840.001544862.7195.9

CountyWINKLER
HighwayFM 1232
FromSH 302
ToSH 115
CSJ1371-01-023
Proj IDF 2023(150)
Work TypeREHABILITATION OF EXISTING ROAD
 
19548504.643395662.2817.3
Work Order11-16-23
Work Began07-15-24
Work Completed
Time Computed02-15-24
Contract Working Days390
Addl Days Granted0
Working Days Charged70
Percent Time Used17
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1371-01-023
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.01)
CONTRACTORS SERVICE, LTD. (0.80)
DK CONTRACTING, LLC (0.40)
HJC FARMS, INC. (2.38)
R.E.B.D. TRUCKING LLC (1.65)
TEXOP CONSTRUCTION (0.71)
WILLIS ELECTRIC CO., LP (0.86)
W. S. CONSTRUCTION COMPANY (8.53)
DOUBLE A CONTRACTING, L.P. (2.08)
Contract #10233203
Totals19548504.64349300.003395662.2817.3

CountyREEVES
HighwayFM 1450
From8 MILES EAST OF US285
ToPECOS COUNTY LINE
CSJ1639-01-016
Proj IDF 2023(524)
Work TypeREHABILITATION OF EXISTING ROAD
 
17.56181336501.6451821641.4663.7
Work Order04-13-23
Work Began09-05-23
Work Completed
Time Computed07-13-23
Contract Working Days420
Addl Days Granted139
Working Days Charged276
Percent Time Used49
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1639-01-016
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.17)
WILLIS ELECTRIC CO., LP (0.47)
DOUBLE A CONTRACTING, L.P. (0.76)
FC TRAFFIC CONTROL, INC. (0.16)
MARCOM"S MOWING SERVICE, LLC (0.17)
A.L. CONSTRUCTION LLC (1.00)
WILD WEST TRUCKING, LLC (1.61)
A BROTHERS MILLING, LLC (0.18)
Contract #03233002
Totals81336501.643680499.6251821641.4663.7

CountyMIDLAND
HighwaySH 349
FromAT SH 191
To.
CSJ1718-07-045
Proj IDF 2023(297)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
10681716.814156196.7838.9
Work Order11-16-23
Work Began06-04-24
Work Completed
Time Computed02-15-24
Contract Working Days175
Addl Days Granted0
Working Days Charged94
Percent Time Used53
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1718-07-045
CONTRACTORS SERVICE, LTD. (0.71)
DK CONTRACTING, LLC (0.76)
DOUBLE A CONTRACTING, L.P. (1.71)
O. TREVINO CONSTRUCTION, LLC (32.40)
TEXOP CONSTRUCTION (2.62)
R.E.B.D. TRUCKING LLC (0.00)
WILLIS ELECTRIC CO., LP (0.19)
Contract #10233205
Totals10681716.81753586.574156196.7838.9

CountyECTOR
HighwayFM 1882
FromBI 20
ToUS 385 S
CSJ2005-02-017
Proj IDF 2023(304)
Work TypeREHABILITATION OF EXISTING ROAD
 
10165599.4310558359.7299.9
Work Order10-12-23
Work Began01-29-24
Work Completed
Time Computed01-11-24
Contract Working Days210
Addl Days Granted20
Working Days Charged144
Percent Time Used62
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2005-02-017
O. TREVINO CONSTRUCTION, LLC (2.53)
CONTRACTORS SERVICE, LTD. (0.71)
TEX OP CONSTRUCTION, LP (2.80)
DESERT PAVING, INC. (0.03)
DK CONTRACTING, LLC (0.75)
HJC FARMS, INC. (0.82)
TRP CONSTRUCTION GROUP, LLC (1.43)
WILLIS ELECTRIC CO., LP (0.16)
R.E.B.D. TRUCKING LLC (0.00)
FC TRAFFIC CONTROL, INC. (0.03)
SCR CIVIL CONSTRUCTION, LLC (0.73)
Contract #09233038
Totals10165599.4358452.0010558359.7299.9

CountyECTOR
HighwaySL 338
FromUS 385N
ToSH 191
CSJ2224-01-118
Proj IDF 2022(586)
Work TypeREHABILITATION OF EXISTING ROAD
 
18181464.7019674444.9899.9
Work Order01-04-23
Work Began05-08-23
Work Completed
Time Computed04-04-23
Contract Working Days255
Addl Days Granted0
Working Days Charged243
Percent Time Used95
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2224-01-118
A BROTHERS MILLING, LLC (0.28)
CONTRACTORS SERVICE, LTD. (0.50)
DK CONTRACTING, LLC (1.31)
DOUBLE A CONTRACTING, L.P. (1.18)
HJC FARMS, INC. (1.30)
W. S. CONSTRUCTION COMPANY (1.11)
R.E.B.D. TRUCKING LLC (0.01)
HERNANDEZ OILFIELD TRANSPORTATION LLC (0.09)
WILLIS ELECTRIC CO., LP (0.31)
MICA CORPORATION (0.25)
TEXOP CONSTRUCTION (0.16)
Contract #12223006
Totals18181464.7064640.9019674444.9899.9

CountyECTOR
HighwaySL 338
FromSOUTH OF W YUKON ROAD
ToWEST OF US 385 N
CSJ2224-01-119
Proj IDC 2224-1-119
Work TypeREHABILITATION OF EXISTING ROAD
 
7949949.697982038.7999.9
Work Order01-04-24
Work Began05-30-24
Work Completed
Time Computed04-04-24
Contract Working Days155
Addl Days Granted0
Working Days Charged102
Percent Time Used65
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2224-01-119
CONTRACTORS SERVICE, LTD. (0.97)
DESERT PAVING, INC. (1.60)
DK CONTRACTING, LLC (0.69)
DOUBLE A CONTRACTING, L.P. (1.94)
R.E.B.D. TRUCKING LLC (0.00)
TEX OP CONSTRUCTION, LP (2.33)
AIMS COMPANIES (0.12)
Contract #12233018
Totals7949949.69289145.067982038.7999.9

CountyMIDLAND
HighwaySH 191
FromAT YUKON RD
To.
CSJ2296-02-026
Proj IDC 2296-2-26
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
2.45527535249.6921527849.9878.1
Work Order02-23-22
Work Began06-06-22
Work Completed
Time Computed05-24-22
Contract Working Days580
Addl Days Granted0
Working Days Charged443
Percent Time Used76
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2296-02-026
BARRICADES UNLIMITED (1.61)
WILLIS ELECTRIC CO., LP (3.39)
FUSION COMMUNICATIONS, LLC (0.17)
DOUBLE A CONTRACTING, L.P. (0.02)
K. L. DURHAM CONSTRUCTION, L.L.C. (0.01)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.09)
S & S BRIDGE PAINTING, INC. (0.22)
GARY A. CRAIN, INC. (0.01)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.15)
HJC FARMS, INC. (0.98)
DK CONTRACTING, LLC (0.99)
RPV CONSTRUCTION, LLC (0.69)
J. H. ODEN CONTRACTING COMPANY (0.35)
JB PINNACLE GROUP, LLC (1.27)
COUGHLIN COMPANY I, INC. (1.23)
RUBIO"S PAVING (0.06)
TRP CONSTRUCTION GROUP, LLC (1.03)
TORO BRAVO CONSTRUCTION, LLC (0.06)
FIBERTEX, LLC (0.17)
LENZO COMMERCIAL CONCRETE, INC. (0.14)
Contract #01223202
Totals27535249.69726943.5221527849.9878.1

CountyUPTON
HighwayRM 2594
FromRM 2401
ToRM 1555
CSJ2568-01-009
Proj IDC 2568-1-9
Work TypeREHABILITATION OF EXISTING ROAD
 
17171717.5911962152.4169.6
Work Order06-14-23
Work Began12-04-23
Work Completed
Time Computed10-13-23
Contract Working Days362
Addl Days Granted0
Working Days Charged237
Percent Time Used65
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2568-01-009
CONTRACTORS SERVICE, LTD. (1.07)
DK CONTRACTING, LLC (0.43)
DOUBLE A CONTRACTING, L.P. (1.88)
R.E.B.D. TRUCKING LLC (0.00)
WILLIS ELECTRIC CO., LP (1.65)
W. S. CONSTRUCTION COMPANY (1.60)
TITAN MILLING INC. (0.59)
Contract #05233208
Totals17171717.591330249.2711962152.4169.6

CountyMIDLAND
HighwayRM 1492
FromFM 1787
ToUPTON COUNTY LINE
CSJ2906-01-006
Proj IDC 2906-1-6
Work TypeREHABILITATION OF EXISTING ROAD
 
2324435.402416801.6299.9
CountyUPTON
HighwayRM 1492
FromMIDLAND COUNTY LINE
ToSH 329
CSJ2906-02-007
Proj IDC 2906-2-7
Work TypeREHABILITATION OF EXISTING ROAD
 
13927408.8713267545.5495.2
Work Order12-07-22
Work Began03-14-23
Work Completed
Time Computed03-07-23
Contract Working Days402
Addl Days Granted0
Working Days Charged359
Percent Time Used89
Contractor(s)
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2906-01-006
DK CONTRACTING, LLC (0.21)
CONTRACTORS SERVICE, LTD. (0.47)
BOLER EQUIPMENT SERVICE, INC (4.21)
DOUBLE A CONTRACTING, L.P. (1.46)
WILLIS ELECTRIC CO., LP (0.15)
MAKIN" IT MOVE TRANSPORT,LLC (0.00)
R.E.B.D. TRUCKING LLC (0.00)
HERNANDEZ OILFIELD TRANSPORTATION LLC (0.00)
TITAN MILLING INC. (0.31)
DUSTROL, INC. (0.35)
Contract #11223003
Totals16251844.275317878.7215684347.1696.5

page 1 | page 2 | page 3 | page 4