Monthly State Let Construction Report For Pharr District As Of Nov 10, 2024 Page 4 Of 4

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHIDALGO
HighwayFM 676
FromTAYLOR RD.
ToFM 2220
CSJ1064-01-043
Proj IDSTP 2024(158)MM
Work TypeWIDEN NON-FREEWAY
 
10832564.50712564.436.5
CountyHIDALGO
HighwayFM 676
From@ EDINBURG MAIN CANAL STR#: K00011001
To.
CSJ1064-01-046
Proj IDBR 2024(076)
Work TypeBRIDGE REPLACEMENT
 
0.100979047.00748390.2576.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-18-24
Work Began07-11-24
Work Completed
Time Computed00-00-00
Contract Working Days472
Addl Days Granted21
Working Days Charged79
Percent Time Used16
Contractor(s)
TEXAS CORDIA CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1064-01-043
HIGHWAY BARRICADES AND SERVICES, LLC (1.11)
D&G ENERGY CORPORATION (6.57)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.15)
DUSTROL, INC. (0.32)
SOIL TECH ADVANCE INC. (0.61)
CERTIFIED PLACERS LLC (0.11)
Contract #03243205
Totals11811611.50389377.011460954.6812.3

CountyCAMERON
HighwayFM 1846
FromSAN JOSE RANCH ROAD
ToBUS 77
CSJ1065-02-039
Proj IDF 2022(108)
Work TypeREHABILITATION OF EXISTING ROAD
 
3889216.023983765.1799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-16-21
Work Began02-18-22
Work Completed
Time Computed00-00-00
Contract Working Days206
Addl Days Granted25
Working Days Charged235
Percent Time Used101
Contractor(s)
TEXAS CORDIA CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1065-02-039
HIGHWAY BARRICADES AND SERVICES, LLC (2.42)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (3.83)
SOIL TECH ADVANCE INC. (0.72)
DUSTROL, INC. (1.70)
GUERRA CONSTRUCTION COMPANY (0.61)
Contract #11213211
Totals3889216.021205.003983765.1799.9

CountySTARR
HighwayFM 755
FromFM 1017
ToFM 2294
CSJ1103-04-039
Proj IDC 1103-4-39
Work TypeSUPER-2 HIGHWAY
 
24639662.301906200.007.7
Work Order08-22-24
Work Began10-03-24
Work Completed
Time Computed10-03-24
Contract Working Days520
Addl Days Granted0
Working Days Charged18
Percent Time Used3
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1103-04-039
DEPENDABLE FENCE (5.76)
HIGHWAY BARRICADES AND SERVICES, LLC (3.01)
SOIL TECH ADVANCE INC. (1.09)
TEXAS HIGHWAY SYSTEMS, INC. (0.67)
Contract #07243203
Totals24639662.301906200.001906200.007.7

CountyCAMERON ETC
HighwayFM 801 ETC
FromIH 69E
ToFM 800
CSJ1137-01-031
Proj IDC 1137-1-31
Work TypeSEAL COAT
 
11.3816481370.350.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-28-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CK NEWBERRY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1137-01-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243217
Totals6481370.350.000.000.0

CountyCAMERON
HighwayFM 802
FromFM 1847
ToOLD PORT ISABEL RD.
CSJ1140-02-038
Proj IDNH 2B20(157)
Work TypeWIDEN NON-FREEWAY
 
6262978.187031757.5799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-20
Work Began01-04-21
Work Completed
Time Computed00-00-00
Contract Working Days230
Addl Days Granted91
Working Days Charged334
Percent Time Used104
Contractor(s)
TEXAS CORDIA CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1140-02-038
HIGHWAY BARRICADES AND SERVICES, LLC (1.58)
GREGORY PILE DRIVING, INC. (0.89)
DUSTROL, INC. (0.70)
TRAF-TEX, INC. (4.77)
EXTERIOR DESIGNS (1.30)
PURLITO, INC. (0.35)
G & E ESCOBEDO CONSTRUCTION, INC. (0.00)
MUNOZ FOUNDATION DRILLING, INC. (0.25)
HOUSTON SAWING & DRILLING (0.05)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.82)
Contract #08203218
Totals6262978.181637.547031757.5799.9

CountyHIDALGO
HighwayFM 1015
FromMILE 9
ToIH-2
CSJ1228-03-050
Proj IDC 1228-3-50
Work TypeREHABILITATION OF EXISTING ROAD
 
8435308.852931874.1234.7
Work Order10-23-23
Work Began01-08-24
Work Completed
Time Computed12-01-23
Contract Working Days294
Addl Days Granted0
Working Days Charged160
Percent Time Used54
Contractor(s)
REIM CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1228-03-050
HIGHWAY BARRICADES AND SERVICES, LLC (2.62)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (4.99)
TEXAS ICON CONSTRUCTION, LLC (0.15)
G & E ESCOBEDO CONSTRUCTION, INC. (0.00)
Contract #09233005
Totals8435308.85467934.322931874.1234.7

CountyHIDALGO
HighwayFM 1015
FromIH-2
To2.584 MILES SOUTH OF IH-2
CSJ1228-03-051
Proj IDC 1228-3-51
Work TypeREHABILITATION OF EXISTING ROAD
 
11217266.064677879.4741.7
Work Order11-01-23
Work Began01-10-24
Work Completed
Time Computed12-01-23
Contract Working Days410
Addl Days Granted0
Working Days Charged199
Percent Time Used48
Contractor(s)
TEXAS CORDIA CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1228-03-051
SOIL TECH ADVANCE INC. (0.15)
HIGHWAY BARRICADES AND SERVICES, LLC (2.28)
EXTERIOR DESIGNS (0.46)
TOP NOTCH CONSTRUCTION (0.00)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (4.47)
DUSTROL, INC. (2.96)
DEPENDABLE FENCE (0.56)
G & E ESCOBEDO CONSTRUCTION, INC. (0.00)
Contract #09233211
Totals11217266.06375736.104677879.4741.7

CountyHIDALGO
HighwayFM 1015
FromUS 281
ToPROGRESO BRIDGE
CSJ1228-04-015
Proj IDC 1228-4-15
Work TypeREHABILITATION OF EXISTING ROAD
 
20273402.950.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-23-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days410
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 1228-04-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243007
Totals20273402.950.000.000.0

CountyWILLACY
HighwayFM 1018
FromIH-69E NB FRONTAGE RD.
ToFM 1420
CSJ1236-01-015
Proj IDF 2021(843)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
12.37512441758.7012090239.2797.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-16-21
Work Began11-08-21
Work Completed
Time Computed00-00-00
Contract Working Days379
Addl Days Granted55
Working Days Charged434
Percent Time Used100
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1236-01-015
GP7 CONSTRUCTION INC. (6.65)
HIGHWAY BARRICADES AND SERVICES, LLC (3.08)
SOIL TECH ADVANCE INC. (4.30)
Contract #08213009
Totals12441758.7014740.0012090239.2797.1

CountyHIDALGO
HighwayFM 1425
FromMILE 12 N. RD.
ToIH-2
CSJ1428-01-027
Proj IDF 2B23(005)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.5008656176.692116569.1024.4
CountyHIDALGO
HighwayFM 1425
FromIH-2
ToBUS 83
CSJ1428-01-028
Proj IDF 2B23(005)
Work TypeREHABILITATION OF EXISTING ROAD
 
683724.680.000.0
CountyHIDALGO
HighwayFM 1425
FromSH 107
ToMILE 12 N. RD.
CSJ1428-01-033
Proj IDSTP 2B23(002)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3917294.763489834.8489.0
Work Order08-07-23
Work Began09-12-23
Work Completed
Time Computed09-11-23
Contract Working Days487
Addl Days Granted14
Working Days Charged239
Percent Time Used47
Contractor(s)
ASAGO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1428-01-027
TEXAS ICON CONSTRUCTION, LLC (2.44)
HIGHWAY BARRICADES AND SERVICES, LLC (3.33)
Contract #06233413
Totals13257196.13212904.925606403.9442.2

CountyWILLACY
HighwayFM 490
From0.74 MI E OF FM 1015
To@ WILLACY CO. MAIN CANAL
CSJ1430-01-025
Proj IDBR 2B23(009)
Work TypeBRIDGE REPLACEMENT
 
929232.95957772.0699.9
CountyWILLACY
HighwayFM 490
From0.70 MI E OF FM 1015
To@ DELTA LAKE DRAIN
CSJ1430-01-026
Proj IDBR 2B23(009)
Work TypeBRIDGE REPLACEMENT
 
1044061.451000733.7895.8
CountyWILLACY
HighwayFM 490
FromFM 1015
ToFM 1425
CSJ1430-01-031
Proj IDSTP 2B23(003)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.2233970779.903750237.3195.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-26-23
Work Began10-31-23
Work Completed
Time Computed00-00-00
Contract Working Days136
Addl Days Granted0
Working Days Charged154
Percent Time Used113
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1430-01-025
TEXAS ICON CONSTRUCTION, LLC (0.86)
TEXAS HIGHWAY SYSTEMS, INC. (0.59)
SOIL TECH ADVANCE INC. (4.64)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.01)
HIGHWAY BARRICADES AND SERVICES, LLC (1.31)
DEPENDABLE FENCE (3.33)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.22)
HOUSTON SAWING & DRILLING (0.10)
Contract #06233611
Totals5944074.30105344.055708743.1596.4

CountyCAMERON
HighwaySH 4
FromIH-69E
ToSH 48
CSJ1504-01-037
Proj IDF 2B23(010)
Work TypeREHABILITATION OF EXISTING ROAD
 
1.57320955780.746841532.3332.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-07-23
Work Began01-08-24
Work Completed
Time Computed00-00-00
Contract Working Days445
Addl Days Granted11
Working Days Charged173
Percent Time Used37
Contractor(s)
POSILLICO CIVIL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1504-01-037
DUSTROL, INC. (1.82)
HIGHWAY BARRICADES AND SERVICES, LLC (1.88)
TRAF-TEX, INC. (3.03)
CERTIFIED PLACERS LLC (1.54)
AMERICAN FENCE (0.04)
SOIL TECH ADVANCE INC. (0.03)
TEXAS CORDIA CONSTRUCTION, LLC (0.05)
Contract #06233410
Totals20955780.74606362.496841532.3332.6

CountyHIDALGO ETC
HighwayFM 907 ETC
From0.1 MILES NORTH OF MILE 17 1/2 N. RD.
To0.1 MILES SOUTH OF MILE 17 1/2 N RD.
CSJ1586-01-089
Proj IDF 2022(934)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1313573.101235281.1296.6
Work Order09-20-22
Work Began03-13-23
Work Completed
Time Computed03-13-23
Contract Working Days140
Addl Days Granted50
Working Days Charged190
Percent Time Used100
Contractor(s)
D&G ENERGY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1586-01-089
VALLEY STRIPING CORP. (10.70)
R&T CONSTRUCTION (0.80)
Contract #08223031
Totals1313573.100.001235281.1296.6

CountyHIDALGO
HighwayFM 1925
FromFM 907 (ALAMO RD)
ToSHARP RD.
CSJ1803-02-035
Proj IDF 2024(623)
Work TypeWIDEN NON-FREEWAY
 
1.6218283398.472897858.2934.9
Work Order02-05-24
Work Began03-06-24
Work Completed
Time Computed03-06-24
Contract Working Days334
Addl Days Granted0
Working Days Charged104
Percent Time Used31
Contractor(s)
ASAGO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1803-02-035
HIGHWAY BARRICADES AND SERVICES, LLC (1.79)
D&G ENERGY CORPORATION (2.80)
IZAGUIRRE CONSTRUCTION LLC (3.49)
TEXAS ICON CONSTRUCTION, LLC (0.46)
Contract #01243209
Totals8283398.47237216.672897858.2934.9

CountyHIDALGO
HighwayFM 1925
FromM RD/GWIN RD
To.
CSJ1803-02-049
Proj IDSTP 2B23(011)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200346821.94326543.8694.3
Work Order08-17-23
Work Began02-23-24
Work Completed
Time Computed12-15-23
Contract Working Days143
Addl Days Granted0
Working Days Charged144
Percent Time Used100
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1803-02-049
TEXAS HIGHWAY SYSTEMS, INC. (0.56)
HIGHWAY BARRICADES AND SERVICES, LLC (3.11)
TEXAS ICON CONSTRUCTION, LLC (3.47)
Contract #06233644
Totals346821.94593.10326543.8694.3

CountyCAMERON
HighwayFM 2556
From0.36 MILES NORTH OF ARROYO COLORADO
To0.35 MILES SOUTH OF ARROYO COLORADO
CSJ2529-02-010
Proj IDSTP 2B24(212)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
7945428.50693237.008.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-22-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days225
Addl Days Granted0
Working Days Charged16
Percent Time Used7
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2529-02-010
RIO GRANDE REBAR RODBUSTERS, LLC. (4.12)
HIGHWAY BARRICADES AND SERVICES, LLC (0.43)
SOIL TECH ADVANCE INC. (1.26)
DEPENDABLE FENCE (0.77)
TEXAS HIGHWAY SYSTEMS, INC. (0.28)
Contract #07243006
Totals7945428.50693237.00693237.008.7

CountyCAMERON
HighwayFM 3069
FromFM 510
ToFM 2480
CSJ3093-01-002
Proj IDSTP 2022(729)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.0005289300.975576409.3299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-20-22
Work Began11-07-22
Work Completed
Time Computed00-00-00
Contract Working Days224
Addl Days Granted26
Working Days Charged206
Percent Time Used82
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3093-01-002
TEXAS ICON CONSTRUCTION, LLC (1.97)
HIGHWAY BARRICADES AND SERVICES, LLC (3.58)
Contract #08223215
Totals5289300.970.005576409.3299.9

CountyWILLACY
HighwayFM 1425
FromSH 186
ToFM 490
CSJ3343-02-016
Proj IDC 3343-2-16
Work TypeREHABILITATION OF EXISTING ROAD
 
3015724.30987550.4032.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-18-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days184
Addl Days Granted0
Working Days Charged27
Percent Time Used14
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3343-02-016
TEXAS ICON CONSTRUCTION, LLC (3.37)
TEXAS HIGHWAY SYSTEMS, INC. (0.92)
PAVEMENT MARKINGS INC. (1.98)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (3.06)
Contract #03243022
Totals3015724.30517059.32987550.4032.7

page 1 | page 2 | page 3 | page 4