Monthly Local Let Maintenance Report For Pharr District As Of Oct 10, 2024 Page 3 Of 3
Last Update: Thursday, October 10, 2024
 |
|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | HIDALGO |
Highway | SH0495 |
From | VARIOUS COUNTIES |
To | IN THE PHARR DISTRICT |
CSJ | 6471-22-001 |
Proj ID | MMC - 647122001 |
Work Type | ASPHALTIC PATCHING MATERIAL |
|
| 0.010 | 159950.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
WALLER COUNTY ASPHALT INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6471-22-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08242107 |
| Totals | 159950.00 | 0.00 | 0.00 | 0.0 |
|
County | CAMERON |
Highway | IH0069E |
From | CITY OF HARLINGEN |
To | VARIOUS ROADWAYS |
CSJ | 6471-71-001 |
Proj ID | MMA - 647171001 |
Work Type | TRAFFIC SIGNAL MAINTENANCE |
|
| 0.010 | 99600.00 | | 4150.00 | 4.1 |
Work Order | 09-01-24 |
Work Began | 09-01-24 |
Work Completed | |
Time Computed | 09-01-24 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 30 |
Percent Time Used | 4 |
Contractor(s) |
CITY OF HARLINGEN |
SUBCONTRACTOR(S) FOR CCSJ: 6471-71-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08242135 |
| Totals | 99600.00 | 4150.00 | 4150.00 | 4.1 |
|