Monthly State Let Construction Report For San Angelo District As Of Nov 10, 2024 Page 1 Of 2

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyRUNNELS
HighwayUS 83
FromTAYLOR COUNTY LINE
To6.9 MILES S OF TAYLOR COUNTY LINE
CSJ0034-03-019
Proj IDNH 2020(944)
Work TypeSUPER-2 HIGHWAY
 
17.32124461409.1625519889.7599.9
CountyRUNNELS
HighwayUS 83
From15.4 MI S OF TAYLOR CO LINE
ToUS 67
CSJ0034-05-040
Proj IDSTP 2020(945)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8.83935702.285202.3314.5
Work Order12-15-20
Work Began04-12-21
Work Completed
Time Computed03-16-21
Contract Working Days578
Addl Days Granted12
Working Days Charged587
Percent Time Used99
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0034-03-019
A BROTHERS MILLING, LLC (0.29)
CONTRACTORS SERVICE COMPANY (0.66)
DOUBLE A CONTRACTING, L.P. (0.26)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.36)
MAKIN" IT MOVE TRANSPORT,LLC (1.24)
D. I. J. CONSTRUCTION, INC. (1.90)
STRUCTURAL INTEGRITY GROUP LLC (0.12)
SOUTHEAST HIGHWAY GUARDRAIL & ATTENUATORS, LLC (1.44)
MARCOM"S MOWING SERVICE, LLC (0.84)
FARR FOUNDATION, INC. (1.15)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.97)
BARRICADES UNLIMITED (0.67)
CONTRACTORS SERVICE, LTD. (0.66)
BEAVER CONTRACTORS, LLC (8.97)
CHEROKEE SERVICES (0.12)
Contract #11203201
Totals24497111.443080.0025525092.0899.9

CountyRUNNELS ETC
HighwayFM 2887 ETC
FromUS 83
ToSH 158
CSJ0034-06-014
Proj IDSTP 2022(701)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
102.3864777670.454002830.1983.7
Work Order08-02-22
Work Began11-07-22
Work Completed
Time Computed10-31-22
Contract Working Days666
Addl Days Granted28
Working Days Charged465
Percent Time Used67
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0034-06-014
DIIBS SPECIALISTS, LLC (34.03)
Contract #06223618
Totals4777670.45186963.064002830.1983.7

CountyCONCHO ETC
HighwayUS 83 ETC
FromAT CONCHO RIVER
To.
CSJ0035-02-039
Proj IDBR 2024(719)
Work TypeBRIDGE MAINTENANCE
 
4356503.00919251.2521.1
Work Order03-21-24
Work Began06-25-24
Work Completed
Time Computed06-19-24
Contract Working Days431
Addl Days Granted0
Working Days Charged83
Percent Time Used19
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0035-02-039
S & S BRIDGE PAINTING, INC. (10.93)
GIBSON & ASSOCIATES, INC. (6.60)
HYDRO TECHNOLOGIES, INC. (3.21)
KING GEORGE TRAFFIC SOLUTIONS LLC (3.98)
Contract #02243019
Totals4356503.004500.00919251.2521.1

CountyCONCHO
HighwayUS 83
FromWEST BRYAN STREET IN EDEN
ToUS 87
CSJ0035-03-047
Proj IDF 2B24(364)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.1432231936.110.000.0
CountyCONCHO
HighwayUS 83
FromUS 87
To0.5 MILES SOUTH OF US 87
CSJ0035-04-032
Proj IDF 2B24(365)
Work TypeWIDEN NON-FREEWAY
 
0.4699258102.300.000.0
CountyCONCHO
HighwayUS 87
FromCONCHO STREET IN EDEN
ToSANTA FE STREET IN EDEN
CSJ0070-04-033
Proj IDC 70-4-33
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.1032630486.410.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days289
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0035-03-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11243209
Totals14120524.820.000.000.0

CountyTOM GREEN
HighwayUS 87
FromAT W 29TH STREET
To-
CSJ0069-07-111
Proj IDSTP 2024(725)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
604327.93396163.8565.5
CountyTOM GREEN
HighwayUS 87
FromAT 19TH STREET
To-
CSJ0069-07-112
Proj IDSTP 2024(710)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
383158.93172040.3044.9
Work Order02-02-24
Work Began07-26-24
Work Completed
Time Computed05-02-24
Contract Working Days116
Addl Days Granted0
Working Days Charged60
Percent Time Used51
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0069-07-111
VACA UNDERGROUND UTILITIES INC (49.74)
Contract #01243248
Totals987486.8674863.40568204.1557.5

CountyTOM GREEN
HighwayUS 87
FromAT 23RD ST
To.
CSJ0069-07-116
Proj IDF 2B24(366)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
671024.200.000.0
CountyTOM GREEN
HighwayUS 87
FromAT W HARRIS AVE
To.
CSJ0069-07-117
Proj IDF 2B24(366)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
858922.200.000.0
CountyTOM GREEN
HighwayUS 87
FromAT W CONCHO AVE
To.
CSJ0069-07-118
Proj IDF 2B24(366)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
325432.200.000.0
CountyTOM GREEN
HighwayUS 87
FromAT JACKSON ST
To.
CSJ0070-02-100
Proj IDF 2B24(548)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
592480.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-24
Work Began00-00-00
Work Completed
Time Computed12-17-24
Contract Working Days143
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0069-07-116
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08243229
Totals2447858.800.000.000.0

CountyTOM GREEN
HighwayUS 87
FromAT KNICKERBOCKER ROAD (RM 584)
To-
CSJ0070-02-098
Proj IDSTP 2B24(131)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
387132.890.000.0
CountyTOM GREEN
HighwayVA
FromDISTRICT WIDE
To.
CSJ0907-00-229
Proj IDF 2B24(130)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1242755.930.000.0
CountyTOM GREEN
HighwayRM 584
FromLAKE NASWORTHY
ToUS 87
CSJ2574-01-051
Proj IDF 2B24(130)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1226190.000.000.0
Work Order07-30-24
Work Began00-00-00
Work Completed
Time Computed10-28-24
Contract Working Days230
Addl Days Granted0
Working Days Charged1
Percent Time Used0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0070-02-098
D&G ENERGY CORPORATION (12.96)
DIIBS SPECIALISTS, LLC (1.30)
Contract #06243225
Totals2856078.820.000.000.0

CountyTOM GREEN
HighwayUS 87
FromSOUTH CONCHO RIVER
ToCONCHO COUNTY LINE
CSJ0070-02-099
Proj IDSTP 2024(659)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4084306.034020177.0798.4
Work Order02-05-24
Work Began04-15-24
Work Completed
Time Computed04-15-24
Contract Working Days302
Addl Days Granted0
Working Days Charged138
Percent Time Used45
Contractor(s)
SCOUT 5 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0070-02-099
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01243025
Totals4084306.0312293.684020177.0798.4

CountyIRION
HighwayUS 67
FromTOM GREEN CO LINE
To10.2 MILES SOUTH OF TOM GREEN CO LINE
CSJ0077-05-031
Proj IDF 2B24(013)
Work TypeOVERLAY
 
44.77252231940.640.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-07-24
Work Began00-00-00
Work Completed
Time Computed02-05-25
Contract Working Days448
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0077-05-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08243203
Totals52231940.640.000.000.0

CountyTOM GREEN
HighwayUS 67
From@ US 87
To.
CSJ0077-06-101
Proj IDSTP 2020(905)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.2001130457.591080469.0199.9
Work Order08-26-20
Work Began01-07-21
Work Completed
Time Computed11-24-20
Contract Working Days127
Addl Days Granted80
Working Days Charged298
Percent Time Used143
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0077-06-101
LIGHT IT UP ELECTRIC (34.69)
FLASHER EQUIPMENT COMPANY (3.28)
FIBERTEL, LLC (0.00)
TRIPLE H FIELD SERVICES, LLC (0.00)
Contract #06203025
Totals1130457.590.001080469.0199.9

CountyTOM GREEN
HighwayBU 67-H
FromAT ARDEN ROAD
To-
CSJ0077-09-011
Proj IDSTP 2023(568)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
525028.50413670.0078.7
Work Order09-06-23
Work Began05-07-24
Work Completed
Time Computed12-05-23
Contract Working Days58
Addl Days Granted0
Working Days Charged43
Percent Time Used74
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0077-09-011
VACA UNDERGROUND UTILITIES INC (55.33)
D. I. J. CONSTRUCTION, INC. (9.29)
Contract #08233054
Totals525028.501300.00413670.0078.7

CountyCROCKETT
HighwayIH 10
From15.9 MI E OF PECOS CL
To29.0 MI E OF PECOS CL
CSJ0140-10-034
Proj IDSTP 2022(702)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1835737.71546026.3332.9
CountyCROCKETT
HighwayIH 10
From38 MI E OF PECOS CL
ToSUTTON CL
CSJ0141-01-057
Proj IDSTP 2022(702)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
14.964488369.08160698.4632.9
CountySUTTON
HighwayIH 10
FromCROCKETT CL
To10.179 MI E OF CROCKETT CL
CSJ0141-02-034
Proj IDSTP 2022(702)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2959644.922239336.8975.6
Work Order08-02-22
Work Began10-05-22
Work Completed
Time Computed10-03-22
Contract Working Days455
Addl Days Granted153
Working Days Charged522
Percent Time Used85
Contractor(s)
ATLANTIC SPECIALTY INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0140-10-034
JE CASEY, LLC (6.01)
RPV CONSTRUCTION, LLC (8.28)
RELMCO, INC. (89.76)
DIIBS SPECIALISTS, LLC (10.01)
Contract #06223413
Totals5283751.71403683.572946061.6856.8

CountySUTTON ETC
HighwayIH 10
FromUS 277
To7.543 MILES E OF US 277
CSJ0141-04-039
Proj IDSTP 2023(403)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
9433781.018812638.8893.4
Work Order03-16-23
Work Began10-18-23
Work Completed
Time Computed05-15-23
Contract Working Days814
Addl Days Granted0
Working Days Charged156
Percent Time Used19
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0141-04-039
J. H. ODEN CONTRACTING COMPANY (2.88)
SOUTH TEXAS TRAFFIC ALLIANCE INC. (0.43)
STRATA FOUNDATION DRILLING, LLC (0.37)
Contract #02233245
Totals9433781.016000.008812638.8893.4

CountyKIMBLE
HighwayIH 10
FromLLANO RIVER
ToKERR COUNTY LINE
CSJ0142-01-076
Proj IDF 2023(680)
Work TypeOVERLAY
 
20144525.2820983901.8099.9
Work Order06-14-23
Work Began04-15-24
Work Completed
Time Computed09-12-23
Contract Working Days107
Addl Days Granted4
Working Days Charged126
Percent Time Used113
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0142-01-076
BARRICADES UNLIMITED (0.19)
PRIMATE CONSTRUCTION, LP (2.69)
TRP CONSTRUCTION GROUP, LLC (2.73)
Contract #05233205
Totals20144525.28692229.8120983901.8099.9

CountyTOM GREEN
HighwayUS 277
FromAT GRAND CANAL ROAD
To.
CSJ0159-01-045
Proj IDF 2B24(367)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3735644.550.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days175
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0159-01-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11243023
Totals3735644.550.000.000.0

CountyTOM GREEN
HighwaySL 378
FromFM 1223
ToUS 87
CSJ0159-07-007
Proj IDF 2022(950)
Work TypeWIDEN NON-FREEWAY
 
2.10535920948.3912989844.1936.1
CountyTOM GREEN
HighwaySL 378
FromFM 1223
ToUS 87
CSJ0159-07-008
Proj IDF 2022(142)
Work TypeRIGHT OF WAY
 
2.1053859499.752423727.4862.7
Work Order04-26-23
Work Began08-14-23
Work Completed
Time Computed07-25-23
Contract Working Days481
Addl Days Granted63
Working Days Charged71
Percent Time Used13
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0159-07-007
AUSTIN ENGINEERING CO., INC. (9.96)
REECE ALBERT, INC. (20.34)
K. L. DURHAM CONSTRUCTION, L.L.C. (0.37)
BLACK ROCK CONSTRUCTION (0.55)
TORO BRAVO CONSTRUCTION, LLC (4.39)
D. I. J. CONSTRUCTION, INC. (0.59)
CLEARFIELD CONSTRUCTION, LLC (0.78)
J. H. ODEN CONTRACTING COMPANY (0.17)
USA AMTECH, INC. (3.62)
WILLIS ELECTRIC CO., LP (2.98)
DIIBS SPECIALISTS, LLC (0.11)
PRIMATE CONSTRUCTION, LP (0.41)
INTEGRITY TRAFFIC SERVICES OF TEXAS, LLC (0.15)
Contract #03233205
Totals39780448.141446615.5415413571.6738.7

CountyCOKE
HighwaySH 70
FromNOLAN COUNTY LINE
ToUS 277
CSJ0264-04-053
Proj IDF 2023(767)
Work TypeSUPER-2 HIGHWAY
 
5.44810756216.998150788.6175.7
CountyCOKE
HighwayUS 277
FromSH 70
ToSH 158 WEST IN BRONTE
CSJ0264-04-054
Proj IDF 2023(767)
Work TypeSUPER-2 HIGHWAY
 
8.28514136940.969617331.0268.0
Work Order12-13-23
Work Began02-01-24
Work Completed
Time Computed03-12-24
Contract Working Days467
Addl Days Granted0
Working Days Charged173
Percent Time Used37
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0264-04-053
CLEARFIELD CONSTRUCTION, LLC (7.15)
DK CONTRACTING, LLC (0.75)
DOUBLE A CONTRACTING, L.P. (0.54)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.23)
BARRICADES UNLIMITED (0.18)
D. I. J. CONSTRUCTION, INC. (1.27)
HJC FARMS, INC. (5.11)
K. L. DURHAM CONSTRUCTION, L.L.C. (1.24)
SCR CIVIL CONSTRUCTION, LLC (1.51)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.13)
PREMIER WIRE FENCE, LTD. (0.03)
Contract #11233002
Totals24893157.953517698.3417768119.6371.3

CountyCOKE
HighwayUS 277
FromSH 158 WEST IN BRONTE
ToTOM GREEN COUNTY LINE
CSJ0264-05-029
Proj IDF 2023(774)
Work TypeSUPER-2 HIGHWAY
 
13.81336110047.6918966081.2852.5
CountyCOKE
HighwayUS 277
FromAT COLORADO RIVER
To.
CSJ0264-05-030
Proj IDBR 2023(775)
Work TypeBRIDGE REPLACEMENT
 
0.0015756257.802238051.3038.8
Work Order07-19-23
Work Began01-02-24
Work Completed
Time Computed10-17-23
Contract Working Days557
Addl Days Granted0
Working Days Charged199
Percent Time Used35
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0264-05-029
J & M CONTRACTING, COMPANY (11.43)
CONTRACTORS SERVICE, LTD. (0.46)
HJC FARMS, INC. (1.74)
DOUBLE A CONTRACTING, L.P. (0.73)
COPPELL CONSTRUCTION CO., INC. (18.67)
PROFESSIONAL TRAFFIC CONTROL LLC (0.07)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.09)
TORO BRAVO CONSTRUCTION, LLC (0.04)
SK CONCRETE SERVICES LLC (0.02)
S & S BRIDGE PAINTING, INC. (0.01)
Contract #06233006
Totals41866305.494614362.4121204132.5850.6

CountyKIMBLE
HighwayPR 73
FromAT SOUTH LLANO RIVER
To.
CSJ0474-01-005
Proj IDC 474-1-5
Work TypeBRIDGE REPLACEMENT
 
0.0052649387.402520503.4399.9
Work Order09-29-21
Work Began02-17-22
Work Completed
Time Computed12-28-21
Contract Working Days150
Addl Days Granted0
Working Days Charged337
Percent Time Used224
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0474-01-005
TEXAS SHAFTS, INC. (5.47)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.94)
DIIBS SPECIALISTS, LLC (1.10)
FLASHER EQUIPMENT COMPANY (0.55)
Contract #08213042
Totals2649387.400.002520503.4399.9

CountyGLASSCOCK
HighwaySH 137
FromSH 158
ToREAGAN COUNTY LINE
CSJ0494-08-016
Proj IDF 2023(570)
Work TypeSUPER-2 HIGHWAY
 
23391036.428832422.4637.7
CountyREAGAN
HighwaySH 137
FromGLASSCOCK COUNTY LINE
To11.5 MILES SOUTH OF GLASSCOCK CL
CSJ0494-09-018
Proj IDF 2023(571)
Work TypeSUPER-2 HIGHWAY
 
9602614.299226411.1896.0
Work Order05-11-23
Work Began08-21-23
Work Completed
Time Computed08-09-23
Contract Working Days655
Addl Days Granted0
Working Days Charged276
Percent Time Used42
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0494-08-016
BLACK JACK ENERGY SERVICES, LLC (17.43)
CONTRACTORS SERVICE, LTD. (0.54)
DOUBLE A CONTRACTING, L.P. (2.07)
J. H. ODEN CONTRACTING COMPANY (0.99)
J & M CONTRACTING, COMPANY (3.04)
MARCOMS CONSTRUCTION LLC (0.27)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.17)
WILLIS ELECTRIC CO., LP (0.44)
HJC FARMS, INC. (0.34)
TEXOP CONSTRUCTION (0.26)
TRP CONSTRUCTION GROUP, LLC (1.21)
D. I. J. CONSTRUCTION, INC. (0.32)
Contract #04233205
Totals32993650.711332323.3118058833.6454.7