Monthly State Let Construction Report For Waco District As Of Nov 10, 2024 Page 3 Of 4

Last Update: Sunday, November 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMCLENNAN
HighwayVA
FromVARIOUS
ToVARIOUS
CSJ0909-00-051
Proj IDSTP 2022(792)HES
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.100454340.00169118.0037.2
Work Order09-20-22
Work Began00-00-00
Work Completed
Time Computed11-19-22
Contract Working Days45
Addl Days Granted0
Working Days Charged14
Percent Time Used31
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0909-00-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08223044
Totals454340.000.00169118.0037.2

CountyMCLENNAN
HighwayVA
FromCORYELL AREA OFFICE
ToBELL AREA OFFICE
CSJ0909-00-065
Proj IDC 909-00-65
Work TypeBRIDGE MAINTENANCE
 
1817856.500.000.0
Work Order09-06-24
Work Began00-00-00
Work Completed
Time Computed10-06-24
Contract Working Days180
Addl Days Granted0
Working Days Charged19
Percent Time Used10
Contractor(s)
AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 0909-00-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243220
Totals1817856.500.000.000.0

CountyMCLENNAN
HighwayVA
FromVARIOUS
ToVARIOUS
CSJ0909-00-066
Proj IDSTP 2B24(519)HES
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
830318.160.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-16-24
Work Began00-00-00
Work Completed
Time Computed01-14-25
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0909-00-066
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243033
Totals830318.160.000.000.0

CountyMCLENNAN
HighwayVA
FromVARIOUS
ToVARIOUS
CSJ0909-00-068
Proj IDC 909-00-68
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2894300.495708.500.1
Work Order09-06-24
Work Began00-00-00
Work Completed
Time Computed10-06-24
Contract Working Days60
Addl Days Granted0
Working Days Charged5
Percent Time Used8
Contractor(s)
CENTERLINE TECHNOLOGIES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0909-00-068
RED SIXTEEN CONSTRUCTION, INC (4.29)
Contract #03243023
Totals2894300.495708.505708.500.1

CountyMCLENNAN
HighwayVA
FromVARIOUS
ToVARIOUS
CSJ0909-00-075
Proj IDF 2024(050)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1018951.351178068.5199.9
Work Order11-16-23
Work Began02-14-24
Work Completed
Time Computed02-14-24
Contract Working Days45
Addl Days Granted12
Working Days Charged46
Percent Time Used80
Contractor(s)
ODUM SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0909-00-075
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10233021
Totals1018951.3554357.461178068.5199.9

CountyMCLENNAN
HighwayVA
FromVARIOUS
ToVARIOUS
CSJ0909-00-094
Proj IDC 909-00-94
Work TypeTRAFFIC CONTROL DEVICES
 
2897993.382235587.7677.1
Work Order08-14-24
Work Began09-17-24
Work Completed
Time Computed11-25-24
Contract Working Days60
Addl Days Granted0
Working Days Charged31
Percent Time Used51
Contractor(s)
STRIPE-A-ZONE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0909-00-094
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05243218
Totals2897993.381898069.782235587.7677.1

CountyZERO COUNTIES
Highway
From
To
CSJ0909-00-097
Proj ID
Work Type
 
0.00701404.000.0
CountyBOSQUE
HighwayFM 219
FromFM 182
ToHILLSIDE ROAD IN CLIFTON
CSJ1054-02-023
Proj IDF 2023(363)
Work TypeREHABILITATION OF EXISTING ROAD
 
6.12510387524.229194954.5688.5
Work Order01-06-23
Work Began03-27-23
Work Completed
Time Computed02-05-23
Contract Working Days300
Addl Days Granted25
Working Days Charged324
Percent Time Used99
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0909-00-097
CHEROKEE SERVICES (0.05)
COLD CREEK CONSTRUCTION, LTD (0.89)
HODGES AND SON CONSTRUCTION COMPANY, INC. (0.69)
ODUM SERVICES, LLC (0.58)
ROADWAY SPECIALTIES, INC. (1.58)
STEEL EFFECTS (0.04)
TORO BRAVO CONSTRUCTION, LLC (0.17)
TRAFFIC HIGHWAY MAINTENANCE, LLC (1.16)
WEST TEXAS ROCK RESOURCES, LLC (0.11)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.63)
A-CORE CONCRETE CUTTING, INC. (0.09)
MARCOMS CONSTRUCTION LLC (0.79)
WILKO INDUSTRIAL, L.L.C. (0.07)
DALLAS LITE AND BARRICADE, INC. (0.02)
TORO BRAVO CONSTRUCTION, LLC (0.00)
Contract #12223036
Totals10387524.2215883.709896358.5695.2

CountyMCLENNAN
HighwayCS
From17TH STREET
To18TH STREET
CSJ0909-22-197
Proj IDSTP 2024(653)HES
Work TypeTRAFFIC CONTROL DEVICES
 
674737.27228008.9233.7
Work Order04-25-24
Work Began06-21-24
Work Completed
Time Computed05-27-24
Contract Working Days90
Addl Days Granted0
Working Days Charged83
Percent Time Used92
Contractor(s)
ELECNOR BELCO ELECTRIC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0909-22-197
BUYERS BARRICADES AUSTIN, LLC (1.23)
BROTHERS RDC PAVING, LLC (28.59)
ACCURATE DRILLING & CONSTRUCTION, INCORPORATED (0.96)
Contract #01243038
Totals674737.2728654.00228008.9233.7

CountyMCLENNAN
HighwayVA
FromVARIOUS
ToVARIOUS
CSJ0909-22-219
Proj IDF 2B24(282)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
598139.380.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-22-24
Work Began00-00-00
Work Completed
Time Computed11-20-24
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0909-22-219
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07243016
Totals598139.380.000.000.0

CountyBELL
HighwayCS
From.1 MI S OF LITTLE NOLAN RD
To.1 MI N OF LITTLE NOLAN RD
CSJ0909-36-182
Proj IDSTP 2023(049)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.205461858.81491736.5399.9
Work Order12-15-22
Work Began10-24-23
Work Completed
Time Computed03-15-23
Contract Working Days45
Addl Days Granted0
Working Days Charged40
Percent Time Used88
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0909-36-182
AUSTIN UNDERGROUND INCORPORATED (15.15)
TEXAS MATERIALS GROUP, INC. (9.74)
PRIMETEX MATERIALS LLC (0.86)
KRL CONSTRUCTION INC. (4.33)
D. I. J. CONSTRUCTION, INC. (2.16)
Contract #10223220
Totals461858.810.00491736.5399.9

CountyHILL
HighwayCR
FromCR 873 @ BRANCH OF ALLIGATOR CREEK
To(MAP #017)
CSJ0909-37-068
Proj IDBR 2021(316)
Work TypeBRIDGE REPLACEMENT
 
759759.1011050.001.4
Work Order09-18-24
Work Began11-04-24
Work Completed
Time Computed10-18-24
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PMCO CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0909-37-068
FORTSON CONTRACTING, INC. (2.08)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.76)
HODGES AND SON CONSTRUCTION COMPANY, INC. (6.34)
WOLFE CONSTRUCTION GROUP, INCORPORATED (1.32)
TORO BRAVO CONSTRUCTION, LLC (0.00)
Contract #08243029
Totals759759.1011050.0011050.001.4

CountyCORYELL
HighwayFM 182
From@ SOUTH HOG CREEK
To(STR #003)
CSJ1219-02-017
Proj IDBR 2023(976)
Work TypeBRIDGE REPLACEMENT
 
0.0091115074.631284152.0799.9
CountyCORYELL
HighwayFM 182
From@ HOG CREEK
To(STR #002)
CSJ1219-02-018
Proj IDBR 2023(976)
Work TypeBRIDGE REPLACEMENT
 
0.0181354818.521116458.5282.4
CountyCORYELL
HighwayFM 182
From@ HURST BRANCH
To(STR #001)
CSJ1219-02-020
Proj IDBR 2023(976)
Work TypeBRIDGE REPLACEMENT
 
8.9181037294.37682147.5065.7
Work Order08-03-23
Work Began10-16-23
Work Completed
Time Computed09-02-23
Contract Working Days270
Addl Days Granted0
Working Days Charged247
Percent Time Used91
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 1219-02-017
JB PINNACLE GROUP, LLC (1.95)
DIIBS SPECIALISTS, LLC (2.73)
MURRAY CONSTRUCTION (0.08)
D. I. J. CONSTRUCTION, INC. (0.90)
CND CONTRACTING (1.55)
WOLFE CONSTRUCTION GROUP, INCORPORATED (1.49)
PRIMATE CONSTRUCTION, LP (0.48)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.86)
HODGES AND SON CONSTRUCTION COMPANY, INC. (4.02)
TORO BRAVO CONSTRUCTION, LLC (0.00)
TIMBER T"S TREE SERVICE, LLC (1.35)
Contract #06233622
Totals3507187.52259713.603082758.0987.8

CountyBELL
HighwayFM 1123
From@ CATHEY CREEK
To(STR #005)
CSJ1308-01-025
Proj IDBR 2024(990)
Work TypeBRIDGE REPLACEMENT
 
0.0141426442.93937209.1365.7
CountyBELL
HighwayFM 1123
From@ MOON BRANCH
To(STR #003)
CSJ1308-01-027
Proj IDBR 2024(990)
Work TypeBRIDGE REPLACEMENT
 
0.0091435698.69146790.0010.2
CountyBELL
HighwayFM 1123
From@ RUNNELLS CREEK
To(STR #004)
CSJ1308-01-028
Proj IDBR 2024(990)
Work TypeBRIDGE REPLACEMENT
 
0.0182321660.40122250.005.2
Work Order06-26-24
Work Began07-26-24
Work Completed
Time Computed07-26-24
Contract Working Days255
Addl Days Granted0
Working Days Charged65
Percent Time Used25
Contractor(s)
C. E. BARKER, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1308-01-025
SOUTH TEXAS TRAFFIC ALLIANCE INC. (1.38)
A K FUQUAY CONSTRUCTION (0.86)
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (0.27)
ROADWAY SPECIALTIES, INC. (1.57)
TORO BRAVO CONSTRUCTION, LLC (1.17)
HODGES AND SON CONSTRUCTION COMPANY, INC. (6.65)
Contract #05243019
Totals5183802.02400354.441206249.1323.2

CountyBELL
HighwayFS 439
FromFM 439
ToSOUTH NOLAN CREEK
CSJ2057-01-010
Proj IDC 2057-1-10
Work TypeREHABILITATION OF EXISTING ROAD
 
1357784.160.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2057-01-010
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06243024
Totals1357784.160.000.000.0

CountyMCLENNAN
HighwayFM 2113
From0.156 MI SOUTHWEST OF FM 2063
To0.101 MI. NORTHEAST OF FM 1695
CSJ2060-01-037
Proj IDF 2021(489)
Work TypeREHABILITATION OF EXISTING ROAD
 
2.23915387558.2713028947.3684.7
Work Order02-16-22
Work Began04-26-22
Work Completed
Time Computed03-18-22
Contract Working Days510
Addl Days Granted0
Working Days Charged519
Percent Time Used101
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2060-01-037
MOBILE ENTERPRISES, INC. (0.09)
CEN TEX HYDROSEED, INC. (1.39)
FLASHER EQUIPMENT COMPANY (0.92)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.30)
QMF STEEL, INC. (0.66)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.41)
DUSTIN ALLEN, INC. (0.35)
KLP COMMERCIAL, L.L.C. (9.48)
WYLIE DRILLING & DRAINAGE, INC. (0.37)
POTTER TRUCKING (1.93)
HERMANOS STEEL, LLC (0.00)
Contract #01223233
Totals15387558.27212330.3813028947.3684.7

CountyBELL
HighwayFM 2410
FromFM 3481
ToIH 14
CSJ2304-02-044
Proj IDC 2304-2-44
Work TypeREHABILITATION OF EXISTING ROAD
 
6.6569585340.608465961.9588.8
Work Order04-19-23
Work Began06-16-23
Work Completed
Time Computed05-19-23
Contract Working Days150
Addl Days Granted0
Working Days Charged189
Percent Time Used126
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2304-02-044
BEAR CREEK CONSTRUCTION, LLC (14.74)
DUSTROL, INC. (0.73)
FORTSON CONTRACTING, INC. (0.11)
J. H. ODEN CONTRACTING COMPANY (4.31)
SAN-ANN-CO., INC. (1.72)
TRP CONSTRUCTION GROUP, LLC (1.85)
CEN-TREE SOLUTIONS LLC (0.50)
Contract #03233208
Totals9585340.6078144.458465961.9588.8

CountyBOSQUE
HighwayFM 2114
FromCR 3620
ToBRAZOS RIVER
CSJ2305-01-014
Proj IDSTP 2023(895)VRU
Work TypeREHABILITATION OF EXISTING ROAD
 
4.3408851170.305168801.7858.3
CountyBOSQUE
HighwayFM 2114
FromFM 56
ToCR 3620
CSJ2305-01-017
Proj IDF 2023(896)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.8564259319.622255082.3452.9
Work Order07-19-23
Work Began09-19-23
Work Completed
Time Computed08-18-23
Contract Working Days315
Addl Days Granted0
Working Days Charged224
Percent Time Used71
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2305-01-014
ROADWAY SPECIALTIES, INC. (1.68)
CAP RIVER LLC (2.02)
CHEROKEE SERVICES (0.06)
MURRAY CONSTRUCTION (0.56)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (3.30)
PROFESSIONAL TRAFFIC CONTROL LLC (0.11)
COLD CREEK CONSTRUCTION, LTD (1.28)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.90)
SAN-ANN-CO., INC. (0.29)
TRAFFIC HIGHWAY MAINTENANCE, LLC (1.22)
MG DRILLING FOUNDATION, LLC (0.00)
Contract #06233209
Totals13110489.92323832.397423884.1256.6

CountyMCLENNAN
HighwaySL 340
FromFM 3051
ToUS 84
CSJ2311-01-042
Proj IDF 2024(330)
Work TypeOVERLAY
 
1.8123759444.643740147.9799.6
Work Order01-04-24
Work Began04-15-24
Work Completed
Time Computed02-03-24
Contract Working Days75
Addl Days Granted0
Working Days Charged80
Percent Time Used106
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 2311-01-042
J & M CONSTRUCTION COMPANY (0.00)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.54)
DIIBS SPECIALISTS, LLC (5.76)
MURRAY CONSTRUCTION (0.22)
CHEROKEE SERVICES (0.81)
PAVEMENT MARKINGS INC. (3.09)
WILKO INDUSTRIAL, L.L.C. (3.46)
J & M CONTRACTING, COMPANY (2.46)
Contract #11233209
Totals3759444.6412473.353740147.9799.6

CountyBELL
HighwaySL 121
FromLAKE RD (FM 439)
ToSOUTH OF W AVENUE O
CSJ2502-01-021
Proj IDF 2021(093)
Work TypeWIDEN NON-FREEWAY
 
3.08429180209.0026755138.5992.0
Work Order11-15-21
Work Began01-04-22
Work Completed
Time Computed12-15-21
Contract Working Days480
Addl Days Granted18
Working Days Charged539
Percent Time Used108
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2502-01-021
TOTAL HIGHWAY MAINTENANCE, LLC (0.43)
TRP CONSTRUCTION GROUP, LLC (0.84)
VOGES DRILLING CO. (0.00)
DIIBS SPECIALISTS, LLC (0.41)
TEXAS MATERIALS GROUP, INC. (20.08)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (9.02)
CEN TEX HYDROSEED, INC. (1.46)
EAGLE CONSTRUCTION LLC (1.07)
GEORGE MEEKS LANDPRO, INC. (0.21)
FARR FOUNDATION, INC. (0.86)
R K STEPHENS CONSTRUCTION, LLC (7.11)
CHEROKEE SERVICES (0.18)
J.H. PAINTING COMPANY (0.10)
HERMANOS STEEL, LLC (0.26)
DIAMOND K MATERIALS (0.20)
MILLER SPRINGS MATERIALS, L.L.C. (2.21)
PANTHER CREEK TRANSPORTATION, INC. (0.03)
KELLER NORTH AMERICA, INC. (0.00)
HODGES AND SON CONSTRUCTION COMPANY, INC. (0.62)
HERMANOS STEEL, LLC (0.00)
CENTRAL TEXAS CURB CUTTERS (0.06)
HARD AS A ROCK CONCRETE CONSTRUCTION LLC (3.58)
GORDILLO TRUCKING, INC, (0.10)
FOSTER FENCE, LTD. (0.23)
PENHALL COMPANY (0.07)
Contract #08213207
Totals29180209.00400391.0726755138.5992.0

CountyMCLENNAN
HighwayFM 1695
FromUS 84
ToFM 2063
CSJ2506-01-045
Proj IDSTP 2B24(285)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
463681.00180960.0039.0
Work Order08-14-24
Work Began09-23-24
Work Completed
Time Computed09-13-24
Contract Working Days60
Addl Days Granted0
Working Days Charged22
Percent Time Used36
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 2506-01-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07243223
Totals463681.00151860.00180960.0039.0

page 1 | page 2 | page 3 | page 4