Detail Letting Schedule for Hays County (FY 2001)
| Detail Letting Schedule for Hays County (FY 2001) | ||||
| Last Update: Friday, August 31, 2001 | ||||
| Updated from Design & Construction Information System (DCIS) on: August 31, 2001 |
| Hays County (FY 2001) |
CCSJ: 0016-02-071 | |||
| District: | Austin | Let Date: | JUL 2001 |
| Highway: | IH 35 | Let Status: | Actual |
| Project ID: | I 35-3(222) | CSJ: | 0016-02-071 |
| Description: | ADD 1 MAIN LANE IN EACH DIRECTION (3RD LANE) | Handling Code: |
|
| Limits From: | 1.0 MI N OF BLANCO RIVER | Fund Cat: | 1 |
| Limits To: | 760.7' N OF N END LP 82 OVERPASS | Estimate: | $16,987,142 |
| Length: | 2.8 Miles | Actual: | $17,743,483 |
|
Bid Tabulations Back... |
Totals for 0016-02-071 | ||
|---|---|---|---|
| Length: | 2.8 Miles | ||
| Estimate: | $16,987,142 | ||
| Actual: | $17,743,483 | ||
CCSJ: 0113-07-045 | |||
| District: | Austin | Let Date: | NOV 2000 |
| Highway: | US 290 | Let Status: | Actual |
| Project ID: | STP 2001(71)HES | CSJ: | 0113-05-038 |
| Description: | SAFETY TREAT DRAINAGE STRUCTURES | Handling Code: |
|
| Limits From: | US 281 IN JOHNSON CITY | Fund Cat: | 4A |
| Limits To: | 6.62 MI W OF HAYS C/L | Estimate: | $62,858 |
| Length: | 2.5 Miles | Actual: | $53,167 |
| District: | Austin | Let Date: | NOV 2000 |
| Highway: | US 290 | Let Status: | Actual |
| Project ID: | STP 2001(71)HES | CSJ: | 0113-06-022 |
| Description: | SAFETY TREAT DRAINAGE STRUCTURES | Handling Code: |
|
| Limits From: | 6.62 MI W OF HAYS C/L | Fund Cat: | 4A |
| Limits To: | HAYS C/L | Estimate: | $55,374 |
| Length: | 8.2 Miles | Actual: | $47,109 |
| District: | Austin | Let Date: | NOV 2000 |
| Highway: | US 290 | Let Status: | Actual |
| Project ID: | STP 2001(71)HES | CSJ: | 0113-07-045 |
| Description: | SAFETY TREAT DRAINAGE STRUCTURES | Handling Code: |
|
| Limits From: | BLANCO C/L | Fund Cat: | 4A |
| Limits To: | DRIPPING SPRINGS | Estimate: | $196,100 |
| Length: | 8.2 Miles | Actual: | $169,886 |
| District: | Austin | Let Date: | NOV 2000 |
| Highway: | US 281 | Let Status: | Actual |
| Project ID: | STP 2001(71)HES | CSJ: | 0253-01-038 |
| Description: | SAFETY TREAT DRAINAGE STRUCTURES | Handling Code: |
|
| Limits From: | US 290 | Fund Cat: | 4A |
| Limits To: | 6.24 MI N OF COMAL C/L | Estimate: | $132,245 |
| Length: | 12.6 Miles | Actual: | $106,552 |
| District: | Austin | Let Date: | NOV 2000 |
| Highway: | US 281 | Let Status: | Actual |
| Project ID: | STP 2001(71)HES | CSJ: | 0253-02-022 |
| Description: | SAFETY TREAT DRAINAGE STRUCTURES | Handling Code: |
|
| Limits From: | 6.24 MI N OF COMAL C/L | Fund Cat: | 4A |
| Limits To: | COMAL C/L | Estimate: | $40,105 |
| Length: | 6.3 Miles | Actual: | $32,734 |
|
Back... |
Totals for 0113-07-045 | ||
| Length: | 37.8 Miles | ||
| Estimate: | $486,682 | ||
| Actual: | $409,448 | ||
Top... Back... Letting Schedule Doing Business with TxDOT |