Detail Letting Schedule for Wood County (FY 2001)

Texas Department of Transportation Logo (Registered Trademark)
 
 
Last Update: Friday, August 31, 2001
 
Updated from Design & Construction Information System (DCIS) on: August 31, 2001
Wood County (FY 2001)

CCSJ: 0096-02-043

District: Tyler Let Date: MAR 2001
Highway: US 80 Let Status: Actual
Project ID: CPM 96-2-43 CSJ: 0096-02-043
Description: REHABILITATE ROADWAY & IMPROVE STRUCTURE SAFETY Handling
Code:
 
Limits From: FM 778 IN CROW, E Fund Cat: 14
Limits To: .4 MI W OF FM 14 IN HAWKINS (EBL ONLY) Estimate: $1,390,684
Length: 6.2 Miles Actual: $1,391,143
 
Back...

Totals for 0096-02-043
Length: 6.2 Miles
Estimate: $1,390,684
Actual: $1,391,143


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract