Detail Letting Schedule for Wilson County (FY 2002)
| Detail Letting Schedule for Wilson County (FY 2002) | ||||
| Last Update: Thursday, September 5, 2002 | ||||
| Updated from Design & Construction Information System (DCIS) on: August 30, 2002 |
| Wilson County (FY 2002) |
CCSJ: 0366-09-023 | |||
| District: | San Antonio | Let Date: | JUL 2002 |
| Highway: | FM 541 | Let Status: | Actual |
| Project ID: | MG 2002(712) | CSJ: | 0366-09-023 |
| Description: | REHAB NARROW PVM'T & WIDEN SHOULDERS | Handling Code: |
|
| Limits From: | US 181 | Fund Cat: | 1 |
| Limits To: | MARCELINAS CREEK | Estimate: | $1,364,003 |
| Length: | 3.3 Miles | Actual: | $1,145,054 |
|
Back... |
Totals for 0366-09-023 | ||
|---|---|---|---|
| Length: | 3.3 Miles | ||
| Estimate: | $1,364,003 | ||
| Actual: | $1,145,054 | ||
CCSJ: 0915-14-018 | |||
| District: | San Antonio | Let Date: | APR 2002 |
| Highway: | CR | Let Status: | Actual |
| Project ID: | BR 96(214)OX | CSJ: | 0915-14-018 |
| Description: | REPLACE BRIDGE & APPROACHES | Handling Code: |
|
| Limits From: | ON CR 474 AT ECLETO CREEK | Fund Cat: | 6 |
| Limits To: | . | Estimate: | $206,424 |
| Length: | 0.1 Miles | Actual: | $189,165 |
| District: | San Antonio | Let Date: | APR 2002 |
| Highway: | CR | Let Status: | Actual |
| Project ID: | BR 2000(781)OX | CSJ: | 0915-14-024 |
| Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
| Limits From: | CR 144 AT DRAW | Fund Cat: | 6 |
| Limits To: | . | Estimate: | $153,301 |
| Length: | 0.1 Miles | Actual: | $114,800 |
|
Back... |
Totals for 0915-14-018 | ||
| Length: | 0.2 Miles | ||
| Estimate: | $359,725 | ||
| Actual: | $303,965 | ||
CCSJ: 1548-01-011 | |||
| District: | San Antonio | Let Date: | SEP 2001 |
| Highway: | FM 1303 | Let Status: | Actual |
| Project ID: | CSR 1548-1-11 | CSJ: | 1548-01-011 |
| Description: | REHAB & WIDEN NARROW PAVEMENT & SHOULDER | Handling Code: |
|
| Limits From: | 3.70 MI N OF FM 536, NW OF FLORESVILLE | Fund Cat: | 1 |
| Limits To: | FM 775 AT CANADA VERDE | Estimate: | $1,448,578 |
| Length: | 3.9 Miles | Actual: | $1,210,132 |
| District: | San Antonio | Let Date: | SEP 2001 |
| Highway: | FM 1303 | Let Status: | Actual |
| Project ID: | CSR 1548-1-12 | CSJ: | 1548-01-012 |
| Description: | REHAB & WIDEN NARROW PAVEMENT & SHOULDER | Handling Code: |
|
| Limits From: | FM 775 AT CANADA VERDE | Fund Cat: | 1 |
| Limits To: | BEXAR COUNTY LINE | Estimate: | $1,334,080 |
| Length: | 3.4 Miles | Actual: | $1,140,210 |
| District: | San Antonio | Let Date: | SEP 2001 |
| Highway: | FM 1303 | Let Status: | Actual |
| Project ID: | CSR 1548-1-13 | CSJ: | 1548-01-013 |
| Description: | REHAB & WIDEN NARROW PAVEMENT & SHOULDER | Handling Code: |
|
| Limits From: | FM 536, N | Fund Cat: | 1 |
| Limits To: | 3.70 MI (LABATT RD) | Estimate: | $1,362,798 |
| Length: | 3.7 Miles | Actual: | $1,144,867 |
| District: | San Antonio | Let Date: | SEP 2001 |
| Highway: | FM 1303 | Let Status: | Actual |
| Project ID: | CSR 1548-2-5 | CSJ: | 1548-02-005 |
| Description: | WIDEN ROADWAY, SEAL & ACP OVERLAY | Handling Code: |
|
| Limits From: | LOOP 1604 | Fund Cat: | 1 |
| Limits To: | WILSON COUNTY LINE | Estimate: | $905,689 |
| Length: | 2.2 Miles | Actual: | $721,796 |
|
Back... |
Totals for 1548-01-011 | ||
| Length: | 13.2 Miles | ||
| Estimate: | $5,051,145 | ||
| Actual: | $4,217,005 | ||
Top... Back... Letting Schedule Doing Business with TxDOT |