SEP 2001 | OCT 2001 | NOV 2001 | DEC 2001 | JAN 2002 | FEB 2002 | MAR 2002 | APR 2002 | MAY 2002 | JUN 2002 | JUL 2002 | AUG 2002 | ||||||
CCSJ | County/ District |
Highway | Let Status | Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
2412-02-012 | Bee/ Corpus Christi |
FM 351 | Actual | $5,889,738 | 1 | CONSTRUCT 5 LANE CURB AND GUTTER SECTION IN THE URBAN AREAS |
0184-02-042 | Bell/ Waco |
SH 36 | Actual | $19,984,243 | 10 | REPLACE BRIDGE AND APPROACHES |
0909-36-098 | Bell/ Waco |
CR | Actual | $12,264,263 | 12 | RECONSTRUCT COUNTY ROAD TO FIVE LANE URBAN ALONG CLEAR CR RD |
0046-04-047 | Bowie/ Atlanta |
US 82 | Actual | $627,687 | 1 | RESTORE PAVEMENT DAMAGED BY MOISTURE INFILTRATION |
0917-29-075 | Brazos/ Bryan |
CR | Actual | $702,511 | 6 | REPLACE BRIDGES AND APPROACHES |
0054-06-074 | Brown/ Brownwood |
US 67 | Actual | $3,919,168 | 1 | RECONSTRUCT INTERSECTION |
0684-01-052 | Cameron/ Pharr |
FM 511 | Actual | $1,870,331 | 10 | REPLACE BRIDGE AND APPROACHES |
0047-15-004 | Collin/ Dallas |
SP 359 | Actual | $81,800 | 1 | TRAFFIC SIGNAL INSTALLATION |
0091-04-046 | Collin/ Dallas |
SH 289 | Actual | $168,668 | 1 | ADDITION OF A LEFT TURN LANE |
0918-24-086 | Collin/ Dallas |
VA | Actual | $194,735 | 7 | CONSTRUCT TURNS LANES AND SIGNALS |
1012-03-012 | Collin/ Dallas |
FM 981 | Actual | $571,540 | 6 | REPLACE BRIDGE AND APPROACHES |
0918-00-060 | Dallas/ Dallas |
VA | Actual | $1,269,460 | 1 | ATTENUATOR UPGRADE |
0918-45-555 | Dallas/ Dallas |
CS | Actual | $554,150 | 5 | PROVIDE UPDATED SIGNAL TIMING PLANS AND INCIDENT - RELATED |
0195-03-055 | Denton/ Dallas |
IH 35E | Actual | $3,231,939 | 11 | REPLACE BRIDGE AND APPROACHES |
0906-00-093 | Ector/ Odessa |
VA | Actual | $65,119 | 1 | UPGRADE LARGE GUIDE SIGNS |
0001-04-079 | El Paso/ El Paso |
US 85 | Actual | $2,068,096 | 1 | REMOVE EXISTING MEDIAN, INSTALL CTB BARRIER, DRAINAGE STR, |
0924-06-208 | El Paso/ El Paso |
CS | Actual | $1,659,650 | 9 | PURCHASE RIGHT OF WAY |
0111-03-045 | Fort Bend/ Houston |
FM 521 | Actual | $38,738 | 10 | RAILROAD GRADE CROSSING REPLANKING |
0675-02-050 | Freestone/ Bryan |
IH 45 | Actual | $531,315 | 1 | REHABILITATION OF EXISTING ROAD CONSISTING OF GRADING, |
0901-19-105 | Grayson/ Paris |
CR | Actual | $642,550 | 10 | REPLACE BRIDGE & APPROACHES |
0027-13-177 | Harris/ Houston |
US 59 | Actual | $60,160 | 10 | RAILROAD GRADE CROSSING REPLANKING |
0027-13-178 | Harris/ Houston |
US 59 | Actual | $60,160 | 10 | RAILROAD GRADE CROSSING REPLANKING |
0271-16-117 | Harris/ Houston |
IH 610 | Actual | $5,434,594 | 1 | GRIND EXIST PAVEMENT ADD BONDED CONCRETE O / L, RECONSTRUCT |
0389-05-090 | Harris/ Houston |
SH 146 | Actual | $165,440 | 10 | RAILROAD GRADE CROSSING REPLANKING |
0598-01-067 | Harris/ Houston |
SH 288 | Actual | $1,863,939 | 1 | FULL DEPTH CONCRETE REPAIR AND CRACK & JOINT SEAL MAINLANES |
0010-02-066 | Hopkins/ Paris |
IH 30 | Actual | $9,043,231 | 1 | OVERPASS STRUCTURE, UNDERPASS AT RADIO RD, RECONSTRUCT |
0642-05-019 | Kaufman/ Dallas |
FM 986 | Actual | $101,400 | 1 | TRAFFIC SIGNAL INSTALLATION |
0915-15-014 | Kerr/ San Antonio |
CS | Actual | $1,349,312 | 6 | REPLACE BRIDGE & APPROACHES |
0017-08-067 | La Salle/ Laredo |
IH 35 | Actual | $5,103,252 | 1 | RECONSTRUCT NORTHBOUND AND MILL AND OVERLAY SOUTHBOUND |
0018-10-007 | La Salle/ Laredo |
BI 35-B | Actual | $6,827,374 | 1 | PREVENTIVE MAINTENANCE - OVERLAY (FY 2002) |
0068-02-042 | Lynn/ Lubbock |
US 87 | Actual | $10,063,257 | 1 | REHABILITATION OF EXISTING ROAD |
0223-01-025 | Marion/ Atlanta |
SH 49 | Actual | $857,887 | 1 | REHABILITATE AND WIDEN EXISTING 2 - LANE HIGHWAY |
0209-01-046 | McLennan/ Waco |
US 77 | Actual | $8,179,592 | 3 | WIDEN FROM 2 LANE TO 4 LANE DIVIDED WITH LEFT TURN LANE |
0177-14-021 | Montgomery/ Houston |
LP 494 | Actual | $615,029 | 11 | ADD LEFT TURN LANES |
0006-03-119 | Nolan/ Abilene |
IH 20 | Actual | $5,067,317 | 1 | PLANING, EXCAVATION, FLEXIBLE BASE, UNDERSEAL, AND ASPHALT |
2839-02-012 | Palo Pinto/ Fort Worth |
SH 337 | Actual | $2,219,125 | 1 | MILL EXISTING PAVEMENT AND OVERLAY 3 INCHES |
0902-38-020 | Parker/ Fort Worth |
CR | Actual | $358,184 | 6 | REPLACE BRIDGE |
0275-01-133 | Potter/ Amarillo |
IH 40 | Actual | $2,148,726 | 11 | WIDEN EXISTING ROADWAY (NFR) |
0424-05-019 | Rusk/ Tyler |
FM 3231 | Actual | $1,773,688 | 10 | CONSTRUCT 2 - LN NON - FRWY ON NEW LOCATION |
0008-14-096 | Tarrant/ Fort Worth |
IH 820 | Actual | $736,670 | 11 | CONSTRUCT SOUTH FRONTAGE ROAD |
0171-05-055 | Tarrant/ Fort Worth |
SH 199 | Actual | $8,680,621 | 2 | RECONSTRUCT ROADWAY |
0034-01-107 | Taylor/ Abilene |
US 83 | Actual | $19,989,242 | 1 | WIDEN EXISTING 4 LANE DIVIDED FREEWAY TO 6 LANE DIVIDED |
2102-01-023 | Travis/ Austin |
RM 2244 | Actual | $6,673,493 | 1 | CONST 4 - LN URBAN RDWY |
3136-01-099 | Travis/ Austin |
LP 1 | Actual | $3,036,837 | 2 | INSTALL CONDUIT & DETECTION AND FREEWAY TRAFFIC MGMT SYSTEM |
0520-02-041 | Upshur/ Atlanta |
SH 155 | Actual | $1,354,176 | 1 | REHABILITATE EXISTING 2 - LANE RURAL HIGHWAY |
0022-06-043 | Val Verde/ Laredo |
US 90 | Actual | $3,529,949 | 1 | FOR THE CONSTRUCTION OF SEAL COAT TYPE WORK |
2350-01-032 | Victoria/ Yoakum |
LP 463 | Actual | $10,749,588 | 11 | CONSTRUCT GRADE SEPARATION INTERCHANGE AND MAIN LANES |
0043-08-066 | Wichita/ Wichita Falls |
US 287 | Actual | $12,394,717 | 1 | FULL - DEPTH CRCP OVERLAY |
0156-14-015 | Wichita/ Wichita Falls |
BU 277A | Actual | $3,376,329 | 1 | WIDEN, IMPROVE SHOULDERS AND DRAINAGE |
0249-01-033 | Wichita/ Wichita Falls |
US 281 | Actual | $5,104,323 | 1 | CONCRETE OVERLAY |
0327-10-027 | Willacy/ Pharr |
US 77 | Actual | $18,698,203 | 1 | CONSTRUCT INTERCHANGE |
0015-09-128 | Williamson/ Austin |
IH 35 | Actual | $281,786 | 10 | RELOCATE RAMP |
0986-01-032 | Williamson/ Austin |
FM 619 | Actual | $791,487 | 6 | REPLACE BRIDGE & APPROACHES |
0915-14-018 | Wilson/ San Antonio |
CR | Actual | $303,965 | 6 | REPLACE BRIDGE & APPROACHES |
0910-35-021 | Wood/ Tyler |
CR | Actual | $369,717 | 6 | REPLACE BRIDGE AND APPROACHES STR# AA0271 - 001 |