Detail Letting Schedule for Jones County (FY 2003)
| Detail Letting Schedule for Jones County (FY 2003) | ||||
| Last Update: Thursday, August 28, 2003 |
| Jones County (FY 2003) |
CCSJ: 0157-05-053 | |||
| District: | Abilene | Let Date: | JUL 2003 |
| Highway: | US 277 | Let Status: | Actual |
| Project ID: | C 157-5-53 | CSJ: | 0157-05-053 |
| Description: | REALIGN INTERSECTION | Handling Code: |
|
| Limits From: | N OF SH 92 | Fund Cat: | 1 |
| Limits To: | .421 MI SOUTH | Estimate: | $435,268 |
| Length: | 0.7 Miles | Actual: | $434,417 |
|
Bid Tabulations Back... |
Totals for 0157-05-053 | ||
|---|---|---|---|
| Length: | 0.7 Miles | ||
| Estimate: | $435,268 | ||
| Actual: | $434,417 | ||
CCSJ: 2859-01-008 | |||
| District: | Abilene | Let Date: | OCT 2002 |
| Highway: | FM 2833 | Let Status: | Actual |
| Project ID: | STP 2002(938) | CSJ: | 2859-01-008 |
| Description: | WIDEN TO ADD SHOULDERS, REHABILITATE EXISTING SECTION AND | Handling Code: |
|
| Limits From: | TAYLOR CO LINE | Fund Cat: | 1 |
| Limits To: | FM 1082 | Estimate: | $3,457,685 |
| Length: | 7.0 Miles | Actual: | $2,994,806 |
| District: | Abilene | Let Date: | OCT 2002 |
| Highway: | FM 2833 | Let Status: | Actual |
| Project ID: | STP 2002(938) | CSJ: | 2859-02-008 |
| Description: | WIDEN TO ADD SHOULDERS, REHABILITATE EXISTING SECTION AND | Handling Code: |
|
| Limits From: | TAYLOR COUNTY LINE | Fund Cat: | 1 |
| Limits To: | NEAR FM 3308 | Estimate: | $45,001 |
| Length: | 0.1 Miles | Actual: | $47,081 |
|
Back... |
Totals for 2859-01-008 | ||
| Length: | 7.1 Miles | ||
| Estimate: | $3,502,686 | ||
| Actual: | $3,041,887 | ||
|
| |