Letting Schedule for July, 2003 (FY 2003)
Letting Schedule for July, 2003 (FY 2003) | ||||
Last Update: Thursday, August 28, 2003 |
July, 2003 (FY 2003) | (see Links) |
SEP 2002 | OCT 2002 | NOV 2002 | DEC 2002 | JAN 2003 | FEB 2003 | MAR 2003 | APR 2003 | MAY 2003 | JUN 2003 | JUL 2003 | AUG 2003 | ||||||
CCSJ | County/ District |
Highway | Let Status | Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0915-12-257 | Bexar/ San Antonio |
VA | Actual | $9,950,038 | 11 | ENHANCE ROADWAYS, TRAILS, MARKERS THAT LEAD TO THE MISSIONS |
0915-12-281 | Bexar/ San Antonio |
CS | Actual | $3,983,045 | 7 | RECONSTRUCT & EXPAND 2 TO 4 LANE (CURBS, SIDEWALK, SIGNAL) |
0921-06-158 | Cameron/ Pharr |
CS | Actual | $1,087,439 | 11 | CONSTRUCT 4 LANE URBAN ON NEW LOCATION |
0091-04-047 | Collin/ Dallas |
SH 289 | Actual | $218,895 | 1 | TRAFFIC SIGNAL INSTALLATION |
0923-17-038 | Comanche/ Brownwood |
CR | Actual | $452,703 | 6 | REPLACE BRIDGE AND APPROACHES |
0261-03-047 | Dallas/ Dallas |
US 67 | Actual | $2,450,598 | 1 | SURFACE TEXTURING |
0918-00-085 | Dallas/ Dallas |
VA | Actual | $81,605 | 1 | RAILROAD CROSSING PAVEMENT MARKINGS AND SIGNING |
0918-45-198 | Dallas/ Dallas |
VA | Actual | $232,606 | 9 | CONSTRUCT HIKE AND BIKE TRAIL TO PARALLEL ALONG BERNAL |
0918-45-661 | Dallas/ Dallas |
CS | Actual | $1,512,177 | 10 | RECONSTRUCT CITY STREET |
2374-01-141 | Dallas/ Dallas |
IH 635 | Actual | $823,008 | 11 | GRADING, BASE AND PAVING, DRAINAGE, RETAINING WALL, SIGNING, |
2374-02-114 | Dallas/ Dallas |
IH 635 | Actual | $5,896,255 | 1 | MILL AND INLAY |
0918-46-062 | Denton/ Dallas |
CR | Actual | $363,211 | 6 | REPLACE BRIDGE AND APPROACHES |
1567-02-023 | Denton/ Dallas |
FM 423 | Actual | $2,522,141 | 1 | RESURFACE AND WIDEN ROADWAY |
0674-01-046 | El Paso/ El Paso |
FM 76 | Actual | $10,853,746 | 7 | WIDEN 4 LANE TO 6 LANE DIVIDED URBAN |
0172-13-001 | Ellis/ Dallas |
US 287 | Actual | $46,661,912 | 7 | CONSTRUCT FOUR LANE DIVIDED RURAL HIGHWAY ON NEW LOCATION |
0271-06-090 | Harris/ Houston |
IH 10 | Actual | $83,392,268 | 7 | RECONSTRUCT & WIDEN TO 8 MAINLANES, HOV LANES, & 3 - LANE |
0271-17-127 | Harris/ Houston |
IH 610 | Actual | 262,488,569 | 1 | RECONSTRUCT 8 - LANE FREEWAY, TMS & PROVISION FOR FUTURE |
0635-03-014 | Houston/ Lufkin |
FM 228 | Actual | $783,469 | 11 | REPLACE BRIDGE AND APPROACHES |
0786-01-070 | Jefferson/ Beaumont |
FM 364 | Actual | $8,055,064 | 4 | RECONSTRUCT HIGHWAY FROM 2 LANES TO 4 LANES |
0157-05-053 | Jones/ Abilene |
US 277 | Actual | $434,417 | 1 | REALIGN INTERSECTION |
0197-12-003 | Kaufman/ Dallas |
BU 175D | Actual | $85,671 | 1 | TRAFFIC SIGNAL INSTALLATION |
0495-01-049 | Kaufman/ Dallas |
SP 557 | Actual | $1,493,867 | 1 | MILL AND INLAY |
0918-11-041 | Kaufman/ Dallas |
CR | Actual | $760,384 | 6 | REPLACE BR & APPRS |
1191-03-025 | Limestone/ Waco |
FM 1245 | Actual | $5,181,142 | 1 | ADD SHOULDERS, BASE OVERLAY, TWO COURSE SURFACE TREATMENT |
0700-04-031 | Llano/ Austin |
SH 71 | Actual | $857,573 | 8 | MILL, SEAL, & OVERLAY |
0055-08-097 | McLennan/ Waco |
US 84 | Actual | $85,163 | 10 | CONSTRUCTION OF SCENIC ENHANCEMENT CONSISTING OF CITY OF |
0258-09-118 | McLennan/ Waco |
SH 6 | Actual | $3,517,240 | 6 | REPLACE BRIDGE AND APPROACHES |
0909-00-041 | McLennan/ Waco |
VA | Actual | $963,634 | 11 | CONSTRUCT / RECONSTRUCT ADA RAMPS |
0092-06-094 | Navarro/ Dallas |
IH 45 | Actual | $3,557,933 | 6 | REPLACE BRIDGES AND APPROACHES |
0732-01-015 | Panola/ Atlanta |
FM 124 | Actual | $684,000 | 6 | REPLACE BRIDGE AND APPROACHES |
0902-38-035 | Parker/ Fort Worth |
CR | Actual | $698,390 | 6 | REPLACE BRIDGE AND APPROACHES |
0441-07-064 | Pecos/ Odessa |
IH 10 | Actual | $990,768 | 1 | PAVEMENT OVERLAY |
0176-04-076 | Polk/ Lufkin |
US 59 | Actual | $3,914,494 | 8 | IMPROVE GUARDRAIL TO DESIGN STANDARDS, SAFETY TREAT FIXED |
0904-00-085 | Potter/ Amarillo |
VA | Actual | $777,017 | 1 | THERMOPLASTIC STRIPING |
0371-03-105 | Refugio/ Corpus Christi |
US 77 | Actual | $823,351 | 1 | MILL & INLAY AND SEAL COAT (N. & S. BOUND LANES) |
1680-03-021 | San Augustine/ Lufkin |
FM 1751 | Actual | $687,928 | 11 | REPLACE BRIDGES AND APPROACHES |
0403-01-037 | San Jacinto/ Lufkin |
SH 156 | Actual | $1,488,595 | 8 | SAFETY TREAT FIXED OBJECTS |
0923-25-002 | San Saba/ Brownwood |
CR | Actual | $597,183 | 6 | REPLACE BRIDGE |
0081-12-020 | Tarrant/ Fort Worth |
IH 35W | Actual | $7,993,249 | 7 | CONSTRUCT INTERCHANGE |
0172-09-013 | Tarrant/ Fort Worth |
US 287 | Actual | $7,870,764 | 7 | ADD INTERCHANGE AT HERITAGE PARKWAY & NECESSARY CONNECTIONS |
0902-48-403 | Tarrant/ Fort Worth |
CS | Actual | $3,047,336 | 10 | RECONSTRUCT PAVEMENT WITH CONCRETE AND DRAINAGE |
0902-48-501 | Tarrant/ Fort Worth |
VA | Actual | $668,717 | 1 | REPLACE DYNAMIC MESSAGE SIGNS |
0902-48-548 | Tarrant/ Fort Worth |
VA | Actual | $290,250 | 7 | THE T EMPLOYER TRIP REDUCTION |
0902-48-549 | Tarrant/ Fort Worth |
VA | Actual | $1,118,500 | 7 | VEHICLE ACQUISITION YEAR 3 |
0902-48-550 | Tarrant/ Fort Worth |
VA | Actual | $750,000 | 7 | PE FOR LIGHT RAIL STUDY IN FORT WORTH |
0902-48-551 | Tarrant/ Fort Worth |
VA | Actual | $2,880,000 | 5 | SERVICE IMPROVEMENTS FOR TRE AT THE RICHLAND HILLS AND |
0902-48-552 | Tarrant/ Fort Worth |
CS | Actual | $650,000 | 5 | PARK AND RIDE FACILITY |
0902-48-553 | Tarrant/ Fort Worth |
VA | Actual | $462,000 | 5 | PARK AND RIDE FACILITY |
0902-48-554 | Tarrant/ Fort Worth |
VA | Actual | $1,480,000 | 5 | DESIGN AND INITIAL CONSTRUCTION |
0908-00-053 | Taylor/ Abilene |
VA | Actual | $443,435 | 1 | THERMOPLASTIC PAVEMENT MARKINGS |
0114-02-076 | Travis/ Austin |
US 290 | Actual | $281,075 | 10 | CONSTRUCT TURN LANES |
0319-02-027 | Trinity/ Lufkin |
SH 94 | Actual | $4,159,104 | 11 | WIDEN ROADWAY TO 28 FT |
0275-13-063 | Wheeler/ Childress |
IH 40 | Actual | $935,447 | 1 | MISCELLANEOUS WORK |
2211-01-017 | Williamson/ Austin |
FM 2338 | Actual | $30,000 | 10 | REMOVE AND REINSTALL TRAFFIC SIGNAL |
|
|