Detail Letting Schedule for Panola County (FY 2003)

 
 
Last Update: Thursday, August 28, 2003
Panola County (FY 2003)

CCSJ: 0732-01-015

District: Atlanta Let Date: JUL 2003
Highway: FM 124 Let Status: Actual
Project ID: BR 2003(34) CSJ: 0732-01-015
Description: REPLACE BRIDGE AND APPROACHES Handling
Code:
 
Limits From: AT BUCKNER CREEK Fund Cat: 6
Limits To: 2.2 KM NE OF US 79 Estimate: $711,934
Length: 0.3 Miles Actual: $684,000
 
Bid Tabulations
Back...

Totals for 0732-01-015
Length: 0.3 Miles
Estimate: $711,934
Actual: $684,000


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract