Detail Letting Schedule for San Augustine County (FY 2003)
|
Detail Letting Schedule for San Augustine County (FY 2003) |
|
Last Update: Thursday, August 28, 2003 |
San Augustine County (FY 2003) |
CCSJ: 1680-03-021
|
District: |
Lufkin |
Let Date: |
JUL 2003 |
Highway: |
FM 1751 |
Let Status: |
Actual |
Project ID: |
BR 2003(1) |
CSJ: |
1680-03-021 |
Description: |
REPLACE BRIDGES AND APPROACHES |
Handling Code: |
|
Limits From: |
AT CHIAMON CREEK & RELIEF |
Fund Cat: |
11 |
Limits To: |
. |
Estimate: |
$716,902 |
Length: |
0.4 Miles |
Actual: |
$687,928 |
|
Bid Tabulations Back...
|
Totals for 1680-03-021 |
Length: |
0.4 Miles |
Estimate: |
$716,902 |
Actual: |
$687,928 |
Handling Code |
Definition |
XX |
Project not processed through statewide letting |
TR |
Transfer of funds |
LC |
Project let through local entity |
NC |
Project not charged against district apportionment |
Let Status |
Definition |
Tentative |
Estimated letting date for this project |
Approved |
Project has administrative approval to be let |
Actual |
Project was let to contract |
|