Detail Letting Schedule for Val Verde County (FY 2004)
| Detail Letting Schedule for Val Verde County (FY 2004) | ||||
| Last Update: Tuesday, August 17, 2004 |
| Val Verde County (FY 2004) |
CCSJ: 0022-09-045 | |||
| District: | Laredo | Let Date: | NOV 2003 |
| Highway: | US 90 | Let Status: | Actual |
| Project ID: | STP 2002(448) | CSJ: | 0022-09-045 |
| Description: | MISCELLANEOUS CONTRUCTION | Handling Code: |
|
| Limits From: | 0.354 MI EAST OF BOX CANYON RD (186 | Fund Cat: | 11 |
| Limits To: | 0.042 MI WEST OF BOX CANYON RD (223 | Estimate: | $280,234 |
| Length: | 0.4 Miles | Actual: | $430,928 |
| District: | Laredo | Let Date: | NOV 2003 |
| Highway: | US 90 | Let Status: | Actual |
| Project ID: | STP 2003(151)HES | CSJ: | 0022-10-045 |
| Description: | HAZARD ELIMINATION AND SAFETY | Handling Code: |
|
| Limits From: | US 90 FROM .5 MI N OF US 277 | Fund Cat: | 11 |
| Limits To: | 2.5 MI SOUTH OF US 277 | Estimate: | $40,842 |
| Length: | 3.0 Miles | Actual: | $54,005 |
| District: | Laredo | Let Date: | NOV 2003 |
| Highway: | US 90 | Let Status: | Actual |
| Project ID: | NH 2003(716) | CSJ: | 0022-10-046 |
| Description: | MISCELLANEOUS CONSTRUCTION | Handling Code: |
|
| Limits From: | DEL RIO | Fund Cat: | 11 |
| Limits To: | AT THE INT OF US 277 & US 90 WEST | Estimate: | $596,497 |
| Length: | 0.4 Miles | Actual: | $657,908 |
|
Back... |
Totals for 0022-09-045 | ||
|---|---|---|---|
| Length: | 3.8 Miles | ||
| Estimate: | $917,573 | ||
| Actual: | $1,142,841 | ||
CCSJ: 0022-09-046 | |||
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | US 90 | Let Status: | Actual |
| Project ID: | CPM 22-5-19 | CSJ: | 0022-05-019 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY 2005) | Handling Code: |
|
| Limits From: | LOOP 25 (WEST OF LANGTRY) | Fund Cat: | 1 |
| Limits To: | 7.5 MI W OF WEST END OF PECOS BRIDGE | Estimate: | $289,582 |
| Length: | 9.4 Miles | Actual: | $266,470 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | US 90 | Let Status: | Actual |
| Project ID: | CPM 22-6-44 | CSJ: | 0022-06-044 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY 2005) | Handling Code: |
|
| Limits From: | 7.5 MI W OF WEST END OF PECOS BRIDGE | Fund Cat: | 1 |
| Limits To: | 1.3 MI WEST OF WEST END OF PECOS BRIDGE | Estimate: | $154,771 |
| Length: | 6.2 Miles | Actual: | $142,160 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | US 90 | Let Status: | Actual |
| Project ID: | CPM 22-9-46 | CSJ: | 0022-09-046 |
| Description: | FOR THE CONSTRUCTION OF SEAL COAT TYPE OF WORK (FY 2004) | Handling Code: |
|
| Limits From: | SPUR 349 | Fund Cat: | 1 |
| Limits To: | 0.364 MI N OF DEL RIO CITY LIMITS | Estimate: | $905,446 |
| Length: | 7.1 Miles | Actual: | $441,882 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | LP 25 | Let Status: | Actual |
| Project ID: | CPM 22-11-6 | CSJ: | 0022-11-006 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2005) | Handling Code: |
|
| Limits From: | US 90 WEST INTERSECTION OF LP 25 | Fund Cat: | 1 |
| Limits To: | US 90 EAST INTERSECTION OF LP 25 | Estimate: | $16,451 |
| Length: | 1.3 Miles | Actual: | $14,995 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | US 83 | Let Status: | Actual |
| Project ID: | CPM 37-6-74 | CSJ: | 0037-06-074 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2005) | Handling Code: |
|
| Limits From: | LP 225/SH 85(IN CARRIZO SPRINGS) | Fund Cat: | 1 |
| Limits To: | ASHERTON CITY LIMITS(10TH ST.) | Estimate: | $194,832 |
| Length: | 8.0 Miles | Actual: | $178,392 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | US 83 | Let Status: | Actual |
| Project ID: | CPM 37-6-75 | CSJ: | 0037-06-075 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2005) | Handling Code: |
|
| Limits From: | ASHERTON CITY LIMITS | Fund Cat: | 1 |
| Limits To: | 1.5 MI SOUTH OF FM 2688 | Estimate: | $224,787 |
| Length: | 10.3 Miles | Actual: | $205,110 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | US 83 | Let Status: | Actual |
| Project ID: | CPM 37-8-32 | CSJ: | 0037-08-032 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2005) | Handling Code: |
|
| Limits From: | 1.5 MI SOUTH OF FM 2688 | Fund Cat: | 1 |
| Limits To: | FM 133 | Estimate: | $36,601 |
| Length: | 1.6 Miles | Actual: | $33,485 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | US 83 | Let Status: | Actual |
| Project ID: | CPM 37-10-24 | CSJ: | 0037-10-024 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | 0.9 MI WEST OF IH 35 | Fund Cat: | 1 |
| Limits To: | IH 35 | Estimate: | $23,711 |
| Length: | 0.9 Miles | Actual: | $21,850 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 1556 | Let Status: | Actual |
| Project ID: | CPM 37-13-10 | CSJ: | 0037-13-010 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | SH 85 | Fund Cat: | 1 |
| Limits To: | US 83 | Estimate: | $36,110 |
| Length: | 2.5 Miles | Actual: | $33,574 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 1917 | Let Status: | Actual |
| Project ID: | CPM 37-15-8 | CSJ: | 0037-15-008 |
| Description: | FOR THE CONSTRUCTION OF SEAL COAT TYPE WORK | Handling Code: |
|
| Limits From: | SH 85 | Fund Cat: | 1 |
| Limits To: | FM 1557 | Estimate: | $64,918 |
| Length: | 4.6 Miles | Actual: | $59,003 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | SH 44 | Let Status: | Actual |
| Project ID: | CPM 237-4-11 | CSJ: | 0237-04-011 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | DUVAL/WEBB COUNTY LINE | Fund Cat: | 1 |
| Limits To: | US 59 ( WEST OF FREER) | Estimate: | $206,574 |
| Length: | 9.6 Miles | Actual: | $189,301 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | SH 44 | Let Status: | Actual |
| Project ID: | CPM 237-6-30 | CSJ: | 0237-06-030 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2005) | Handling Code: |
|
| Limits From: | 1.0 MI W OF FM 3196 | Fund Cat: | 1 |
| Limits To: | SH 359 | Estimate: | $301,755 |
| Length: | 12.7 Miles | Actual: | $276,335 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 133 | Let Status: | Actual |
| Project ID: | CPM 237-7-8 | CSJ: | 0237-07-008 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY 2005) | Handling Code: |
|
| Limits From: | US 83 (CATARINA) | Fund Cat: | 1 |
| Limits To: | LA SALLE COUNTY LINE | Estimate: | $259,122 |
| Length: | 13.7 Miles | Actual: | $237,962 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | US 57 | Let Status: | Actual |
| Project ID: | CPM 276-1-31 | CSJ: | 0276-01-031 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2005) | Handling Code: |
|
| Limits From: | 6.4 MI WEST OF FM 481 (RM 378) | Fund Cat: | 1 |
| Limits To: | FM 481 | Estimate: | $159,320 |
| Length: | 6.4 Miles | Actual: | $147,264 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 1591 | Let Status: | Actual |
| Project ID: | CPM 299-5-11 | CSJ: | 0299-05-011 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | US 277 | Fund Cat: | 1 |
| Limits To: | FM 1908 | Estimate: | $24,172 |
| Length: | 2.2 Miles | Actual: | $21,925 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 1908 | Let Status: | Actual |
| Project ID: | CPM 299-5-12 | CSJ: | 0299-05-012 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | FM 1591 | Fund Cat: | 1 |
| Limits To: | FM 1590 | Estimate: | $23,961 |
| Length: | 2.3 Miles | Actual: | $21,672 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 1589 | Let Status: | Actual |
| Project ID: | CPM 299-7-10 | CSJ: | 0299-07-010 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | US 277 SOUTH | Fund Cat: | 1 |
| Limits To: | US 277 NORTH | Estimate: | $36,151 |
| Length: | 2.1 Miles | Actual: | $33,740 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 1664 | Let Status: | Actual |
| Project ID: | CPM 299-8-6 | CSJ: | 0299-08-006 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | US 277 NORTH | Fund Cat: | 1 |
| Limits To: | US 277 SOUTH | Estimate: | $55,933 |
| Length: | 4.8 Miles | Actual: | $50,694 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 186 | Let Status: | Actual |
| Project ID: | CPM 301-4-13 | CSJ: | 0301-04-013 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | LP 225 | Fund Cat: | 1 |
| Limits To: | END OF PAVEMENT | Estimate: | $177,037 |
| Length: | 14.3 Miles | Actual: | $164,339 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | SH 339 | Let Status: | Actual |
| Project ID: | CPM 623-2-24 | CSJ: | 0623-02-024 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | FM 716 | Fund Cat: | 1 |
| Limits To: | SH 285 (BROOKS/DUVAL COUNTY LINE) | Estimate: | $130,689 |
| Length: | 11.3 Miles | Actual: | $119,372 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 65 | Let Status: | Actual |
| Project ID: | CPM 652-1-31 | CSJ: | 0652-01-031 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | FM 1433 | Fund Cat: | 1 |
| Limits To: | DIMMIT COUNTY LINE | Estimate: | $78,659 |
| Length: | 3.7 Miles | Actual: | $72,621 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 65 | Let Status: | Actual |
| Project ID: | CPM 652-2-16 | CSJ: | 0652-02-016 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY 2004) | Handling Code: |
|
| Limits From: | DIMMIT/ZAVALA COUNTY LINE | Fund Cat: | 1 |
| Limits To: | SH 85 | Estimate: | $141,862 |
| Length: | 7.7 Miles | Actual: | $129,692 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | RM 334 | Let Status: | Actual |
| Project ID: | CPM 876-2-28 | CSJ: | 0876-02-028 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY 2005) | Handling Code: |
|
| Limits From: | BRACKETTVILLE CITY LIMITS | Fund Cat: | 1 |
| Limits To: | UVALDE COUNTY LINE | Estimate: | $219,228 |
| Length: | 20.7 Miles | Actual: | $197,513 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 395 | Let Status: | Actual |
| Project ID: | CPM 878-5-18 | CSJ: | 0878-05-018 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY 2005) | Handling Code: |
|
| Limits From: | FM 1025 | Fund Cat: | 1 |
| Limits To: | FM 582 | Estimate: | $61,892 |
| Length: | 6.0 Miles | Actual: | $55,148 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 1916 | Let Status: | Actual |
| Project ID: | CPM 963-2-6 | CSJ: | 0963-02-006 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | FM 190 | Fund Cat: | 1 |
| Limits To: | END OF PAVEMENT | Estimate: | $31,587 |
| Length: | 3.0 Miles | Actual: | $28,239 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 2030 | Let Status: | Actual |
| Project ID: | CPM 1229-6-8 | CSJ: | 1229-06-008 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | FM 1021 NORTH | Fund Cat: | 1 |
| Limits To: | FM 1021 SOUTH | Estimate: | $83,602 |
| Length: | 5.0 Miles | Actual: | $77,271 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 1433 | Let Status: | Actual |
| Project ID: | CPM 1424-1-8 | CSJ: | 1424-01-008 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | FM 65 | Fund Cat: | 1 |
| Limits To: | DIMMIT COUNTY LINE | Estimate: | $13,903 |
| Length: | 1.1 Miles | Actual: | $12,910 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 1433 | Let Status: | Actual |
| Project ID: | CPM 1424-2-13 | CSJ: | 1424-02-013 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | DIMMIT/ZAVALA COUNTY LINE | Fund Cat: | 1 |
| Limits To: | US 83 | Estimate: | $102,312 |
| Length: | 7.4 Miles | Actual: | $94,869 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 1588 | Let Status: | Actual |
| Project ID: | CPM 1508-1-9 | CSJ: | 1508-01-009 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | END OF ROAD (CO RDS 129 & 131) | Fund Cat: | 1 |
| Limits To: | US 277 | Estimate: | $83,785 |
| Length: | 3.5 Miles | Actual: | $77,107 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 3408 | Let Status: | Actual |
| Project ID: | CPM 1545-3-9 | CSJ: | 1545-03-009 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | IH 35 | Fund Cat: | 1 |
| Limits To: | 3.92 MI EAST(END OF PAVEMENT) | Estimate: | $49,100 |
| Length: | 3.9 Miles | Actual: | $45,505 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | RM 2523 | Let Status: | Actual |
| Project ID: | CPM 1592-1-13 | CSJ: | 1592-01-013 |
| Description: | FOR THE CONSTRUCTION OF SEAL COAT TYPE OF WORK (FY 2004) | Handling Code: |
|
| Limits From: | 8.3 MILES SOUTH OF KINNEY CO LINE | Fund Cat: | 1 |
| Limits To: | US 90 | Estimate: | $82,508 |
| Length: | 6.1 Miles | Actual: | $76,483 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 1668 | Let Status: | Actual |
| Project ID: | CPM 1593-1-21 | CSJ: | 1593-01-021 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | END OF PAVEMENT (CO RD 217) | Fund Cat: | 1 |
| Limits To: | FM 393 | Estimate: | $93,827 |
| Length: | 8.5 Miles | Actual: | $84,424 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 1867 | Let Status: | Actual |
| Project ID: | CPM 1799-2-14 | CSJ: | 1799-02-014 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | DIMMIT/ZAVALA COUNTY LINE | Fund Cat: | 1 |
| Limits To: | END OF PAVEMENT | Estimate: | $98,869 |
| Length: | 7.8 Miles | Actual: | $90,774 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | RM 1865 | Let Status: | Actual |
| Project ID: | CPM 1800-2-4 | CSJ: | 1800-02-004 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY 2005) | Handling Code: |
|
| Limits From: | END OF PAVEMENT (PUMPVILLE) | Fund Cat: | 1 |
| Limits To: | TERRELL COUNTY LINE | Estimate: | $24,057 |
| Length: | 2.2 Miles | Actual: | $21,861 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 1918 | Let Status: | Actual |
| Project ID: | CPM 1813-1-7 | CSJ: | 1813-01-007 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | FM 1407 | Fund Cat: | 1 |
| Limits To: | FM 191 | Estimate: | $11,434 |
| Length: | 1.2 Miles | Actual: | $10,212 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 1908 | Let Status: | Actual |
| Project ID: | CPM 1814-1-9 | CSJ: | 1814-01-009 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | SH 131 | Fund Cat: | 1 |
| Limits To: | MAVERICK COUNTY LINE | Estimate: | $106,458 |
| Length: | 10.5 Miles | Actual: | $94,546 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 393 | Let Status: | Actual |
| Project ID: | CPM 1937-2-22 | CSJ: | 1937-02-022 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | FM 2691 | Fund Cat: | 1 |
| Limits To: | FM 1668 | Estimate: | $98,971 |
| Length: | 9.2 Miles | Actual: | $88,684 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 1572 | Let Status: | Actual |
| Project ID: | CPM 2012-2-14 | CSJ: | 2012-02-014 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY 2005) | Handling Code: |
|
| Limits From: | SH 131 | Fund Cat: | 1 |
| Limits To: | US 90 | Estimate: | $170,298 |
| Length: | 16.1 Miles | Actual: | $152,435 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | RM 3008 | Let Status: | Actual |
| Project ID: | CPM 2012-3-9 | CSJ: | 2012-03-009 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2005) | Handling Code: |
|
| Limits From: | FM 2523 | Fund Cat: | 1 |
| Limits To: | US 90 | Estimate: | $137,151 |
| Length: | 13.0 Miles | Actual: | $122,627 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 2522 | Let Status: | Actual |
| Project ID: | CPM 2434-1-8 | CSJ: | 2434-01-008 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY 2004) | Handling Code: |
|
| Limits From: | FM 190 | Fund Cat: | 1 |
| Limits To: | US 83 | Estimate: | $53,571 |
| Length: | 4.9 Miles | Actual: | $48,100 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 1986 | Let Status: | Actual |
| Project ID: | CPM 2449-1-7 | CSJ: | 2449-01-007 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | FM 1436 NORTH | Fund Cat: | 1 |
| Limits To: | FM 1436 SOUTH | Estimate: | $69,851 |
| Length: | 6.5 Miles | Actual: | $62,670 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 395 | Let Status: | Actual |
| Project ID: | CPM 2484-1-6 | CSJ: | 2484-01-006 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY 2005) | Handling Code: |
|
| Limits From: | FM 582 | Fund Cat: | 1 |
| Limits To: | DIMMIT COUNTY LINE | Estimate: | $38,589 |
| Length: | 3.8 Miles | Actual: | $34,271 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 395 | Let Status: | Actual |
| Project ID: | CPM 2484-2-7 | CSJ: | 2484-02-007 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2005) | Handling Code: |
|
| Limits From: | DIMMIT/ZAVALA COUNTY LINE | Fund Cat: | 1 |
| Limits To: | FM 65 | Estimate: | $8,633 |
| Length: | 0.8 Miles | Actual: | $7,711 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 1433 | Let Status: | Actual |
| Project ID: | CPM 2628-1-6 | CSJ: | 2628-01-006 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | US 83 | Fund Cat: | 1 |
| Limits To: | FM 65 | Estimate: | $53,933 |
| Length: | 2.1 Miles | Actual: | $49,024 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | RM 2804 | Let Status: | Actual |
| Project ID: | CPM 2752-1-6 | CSJ: | 2752-01-006 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2005) | Handling Code: |
|
| Limits From: | END OF PAVEMENT | Fund Cat: | 1 |
| Limits To: | LP 166 | Estimate: | $67,944 |
| Length: | 6.6 Miles | Actual: | $60,396 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | RM 3348 | Let Status: | Actual |
| Project ID: | CPM 2752-2-5 | CSJ: | 2752-02-005 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2005) | Handling Code: |
|
| Limits From: | US 90 | Fund Cat: | 1 |
| Limits To: | END OF PAVEMENT | Estimate: | $60,750 |
| Length: | 6.0 Miles | Actual: | $53,927 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 2895 | Let Status: | Actual |
| Project ID: | CPM 2988-2-11 | CSJ: | 2988-02-011 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2005) | Handling Code: |
|
| Limits From: | US 59 | Fund Cat: | 1 |
| Limits To: | SH 359 | Estimate: | $240,857 |
| Length: | 17.4 Miles | Actual: | $223,186 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 3199 | Let Status: | Actual |
| Project ID: | CPM 3299-1-5 | CSJ: | 3299-01-005 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2005) | Handling Code: |
|
| Limits From: | END OF PAVEMENT | Fund Cat: | 1 |
| Limits To: | RM 334 | Estimate: | $65,816 |
| Length: | 6.8 Miles | Actual: | $58,863 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 3249 | Let Status: | Actual |
| Project ID: | CPM 3341-1-1 | CSJ: | 3341-01-001 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY 2004) | Handling Code: |
|
| Limits From: | END OF PAVEMENT | Fund Cat: | 1 |
| Limits To: | SH 339 | Estimate: | $78,799 |
| Length: | 6.5 Miles | Actual: | $71,812 |
| District: | Laredo | Let Date: | JAN 2004 |
| Highway: | FM 3252 | Let Status: | Actual |
| Project ID: | CPM 3353-1-7 | CSJ: | 3353-01-007 |
| Description: | FOR THE CONSTRUCTION OF SEALCOAT TYPE OF WORK (FY2004) | Handling Code: |
|
| Limits From: | FM 186 | Fund Cat: | 1 |
| Limits To: | END OF PAVEMENT | Estimate: | $39,054 |
| Length: | 3.7 Miles | Actual: | $35,495 |
|
Back... |
Totals for 0022-09-046 | ||
| Length: | 333.0 Miles | ||
| Estimate: | $5,789,223 | ||
| Actual: | $4,897,901 | ||
CCSJ: 0022-09-047 | |||
| District: | Laredo | Let Date: | AUG 2004 |
| Highway: | US 90 | Let Status: | Approved |
| Project ID: | CPM 22-5-20 | CSJ: | 0022-05-020 |
| Description: | FOR THE REPAIR, CLEANING AND PAINTING OF A STRUCTURAL STEEL | Handling Code: |
|
| Limits From: | AT EAGLE NEST CANYON IN DEL RIO | Fund Cat: | 1 |
| Limits To: | . | Estimate: | $218,790 |
| Length: | 0.1 Miles | Actual: | |
| District: | Laredo | Let Date: | AUG 2004 |
| Highway: | US 90 | Let Status: | Approved |
| Project ID: | CPM 22-6-45 | CSJ: | 0022-06-045 |
| Description: | FOR THE CLEANING AND PAINTING OF A STRUCTURAL STEEL BRIDGE | Handling Code: |
|
| Limits From: | AT PECOS RIVER IN VAL VERDE | Fund Cat: | 11 |
| Limits To: | . | Estimate: | $1,154,158 |
| Length: | 0.2 Miles | Actual: | |
| District: | Laredo | Let Date: | AUG 2004 |
| Highway: | US 90 | Let Status: | Approved |
| Project ID: | C 22-9-47 | CSJ: | 0022-09-047 |
| Description: | CLEANING AND PAINTING OF A STRUCTURAL STEEL BRIDGE | Handling Code: |
|
| Limits From: | AT DEVIL RIVER/AMISTAD RESEVOIR | Fund Cat: | 11 |
| Limits To: | & SP RR BRIDGE | Estimate: | $4,060,074 |
| Length: | 1.0 Miles | Actual: | |
|
List Showing Order Bidders List Bid Tabulations Proposal Req Form Back... |
Totals for 0022-09-047 | ||
| Length: | 1.3 Miles | ||
| Estimate: | $5,433,022 | ||
| Actual: | |||
CCSJ: 0022-10-047 | |||
| District: | Laredo | Let Date: | DEC 2003 |
| Highway: | US 90 | Let Status: | Actual |
| Project ID: | STP 2004(72)HES | CSJ: | 0022-10-047 |
| Description: | IMPROVE TRAFFIC SIGNAL AND SAFETY LIGHTING AT INTERSECTION | Handling Code: |
|
| Limits From: | AT US 277 AND SH SP 297 | Fund Cat: | 1 |
| Limits To: | . | Estimate: | $149,093 |
| Length: | 0.1 Miles | Actual: | $135,779 |
| District: | Laredo | Let Date: | DEC 2003 |
| Highway: | US 90 | Let Status: | Actual |
| Project ID: | STP 2004(72)HES | CSJ: | 0023-01-070 |
| Description: | IMPROVE TRAFFIC SIGNAL AND SAFETY LIGHTING AT INTERSECTION | Handling Code: |
|
| Limits From: | AT BEDELL ST | Fund Cat: | 1 |
| Limits To: | . | Estimate: | $118,813 |
| Length: | 0.1 Miles | Actual: | $115,025 |
| District: | Laredo | Let Date: | DEC 2003 |
| Highway: | FM 375 | Let Status: | Actual |
| Project ID: | STP 2004(72)HES | CSJ: | 1229-04-008 |
| Description: | UPGRADE TRAFFIC SIGNAL | Handling Code: |
|
| Limits From: | FM 1021 | Fund Cat: | 1 |
| Limits To: | AT THE INTERSECTION OF FM 375 | Estimate: | $105,566 |
| Length: | 0.1 Miles | Actual: | $96,378 |
|
Back... |
Totals for 0022-10-047 | ||
| Length: | 0.3 Miles | ||
| Estimate: | $373,472 | ||
| Actual: | $347,182 | ||
CCSJ: 0022-10-048 | |||
| District: | Laredo | Let Date: | FEB 2004 |
| Highway: | US 90 | Let Status: | Actual |
| Project ID: | MG 2004(244) | CSJ: | 0022-10-048 |
| Description: | FOR THE CONSTRUCTION OF ASPHALTIC CONCRETE PAVEMENT OVERLAY | Handling Code: |
|
| Limits From: | 17TH ST (DEL RIO) | Fund Cat: | 1 |
| Limits To: | US 277/US 90 Y INTERSECTION | Estimate: | $1,178,215 |
| Length: | 3.0 Miles | Actual: | $1,242,509 |
|
Back... |
Totals for 0022-10-048 | ||
| Length: | 3.0 Miles | ||
| Estimate: | $1,178,215 | ||
| Actual: | $1,242,509 | ||
CCSJ: 0299-01-058 | |||
| District: | Laredo | Let Date: | AUG 2004 |
| Highway: | US 277 | Let Status: | Approved |
| Project ID: | MG 2004(645) | CSJ: | 0299-01-058 |
| Description: | REHABILITATION OF EXISTING ROADWAY | Handling Code: |
|
| Limits From: | SAN FELIPE CREEK IN DEL RIO | Fund Cat: | 4 |
| Limits To: | KINNEY COUNTY LINE | Estimate: | $4,935,000 |
| Length: | 11.6 Miles | Actual: | |
|
List Showing Order Bidders List Bid Tabulations Proposal Req Form Back... |
Totals for 0299-01-058 | ||
| Length: | 11.6 Miles | ||
| Estimate: | $4,935,000 | ||
| Actual: | |||
CCSJ: 0922-11-017 | |||
| District: | Laredo | Let Date: | JUL 2004 |
| Highway: | VA | Let Status: | Actual |
| Project ID: | ITS 99(709) | CSJ: | 0922-11-017 |
| Description: | INTEGRATION / DEPLOYMENT | Handling Code: |
NC |
| Limits From: | VARIOUS LOCATIONS IN | Fund Cat: | 10 |
| Limits To: | DEL RIO | Estimate: | $649,150 |
| Length: | 0.1 Miles | Actual: | $685,020 |
|
Award Status Bid Tabulations Back... |
Totals for 0922-11-017 | ||
| Length: | 0.1 Miles | ||
| Estimate: | $649,150 | ||
| Actual: | $685,020 | ||
|
| |