Detail Letting Schedule for Bandera County (FY 2005)
| Detail Letting Schedule for Bandera County (FY 2005) | ||||
| Last Update: Monday, August 15, 2005 |
| Bandera County (FY 2005) |
CCSJ: 0421-06-016 | |||
| District: | San Antonio | Let Date: | OCT 2004 |
| Highway: | SH 173 | Let Status: | Actual |
| Project ID: | STP 2004(739) | CSJ: | 0421-06-016 |
| Description: | REHAB ROADWAY | Handling Code: |
|
| Limits From: | KERR COUNTY LINE | Fund Cat: | 1 |
| Limits To: | 0.24 MI SOUTH OF FM 2828 | Estimate: | $781,455 |
| Length: | 1.0 Miles | Actual: | $984,120 |
|
Back... |
Totals for 0421-06-016 | ||
|---|---|---|---|
| Length: | 1.0 Miles | ||
| Estimate: | $781,455 | ||
| Actual: | $984,120 | ||
CCSJ: 0792-04-036 | |||
| District: | San Antonio | Let Date: | JUL 2005 |
| Highway: | FM 470 | Let Status: | Actual |
| Project ID: | ER 2005(63) | CSJ: | 0792-04-036 |
| Description: | REMOVE & REPLACE RIPRAP & DEBRIS REMOVAL | Handling Code: |
NC |
| Limits From: | AT SECO CREEK | Fund Cat: | 10 |
| Limits To: | . | Estimate: | $215,451 |
| Length: | 0.0 Miles | Actual: | $227,960 |
|
Award Status Bid Tabulations Back... |
Totals for 0792-04-036 | ||
| Length: | 0.0 Miles | ||
| Estimate: | $215,451 | ||
| Actual: | $227,960 | ||
|
| |