Detail Letting Schedule for Bowie County (FY 2006)
Detail Letting Schedule for Bowie County (FY 2006) | ||||
Last Update: Monday, August 28, 2006 |
Bowie County (FY 2006) |
CCSJ: 0010-19-008 | |||
District: | Atlanta | Let Date: | JAN 2006 |
Highway: | FM 991 | Let Status: | Actual |
Project ID: | SFT 10-19-8 | CSJ: | 0010-19-008 |
Description: | WIDEN LANES ON EXISTING ROADWAY | Handling Code: |
|
Limits From: | US 67 (S) | Fund Cat: | 8 |
Limits To: | US 67 (N) | Estimate: | $868,155 |
Length: | 6.8 Miles | Actual: | $906,293 |
District: | Atlanta | Let Date: | JAN 2006 |
Highway: | FM 44 | Let Status: | Actual |
Project ID: | SFT 330-2-13 | CSJ: | 0330-02-013 |
Description: | WIDEN LANES ON EXISTING ROADWAY | Handling Code: |
|
Limits From: | US 259 | Fund Cat: | 8 |
Limits To: | RED RIVER COUNTY LINE | Estimate: | $442,199 |
Length: | 7.7 Miles | Actual: | $474,895 |
District: | Atlanta | Let Date: | JAN 2006 |
Highway: | FM 44 | Let Status: | Actual |
Project ID: | SFT 330-3-25 | CSJ: | 0330-03-025 |
Description: | WIDEN LANES ON EXISTING ROADWAY | Handling Code: |
|
Limits From: | CR 4247 | Fund Cat: | 8 |
Limits To: | FM 992 | Estimate: | $318,735 |
Length: | 3.4 Miles | Actual: | $338,068 |
District: | Atlanta | Let Date: | JAN 2006 |
Highway: | FM 1397 | Let Status: | Actual |
Project ID: | SFT 945-1-31 | CSJ: | 0945-01-031 |
Description: | WIDEN LANES ON EXISTING ROADWAY | Handling Code: |
|
Limits From: | 6.0 MI N OF FM 2240 | Fund Cat: | 8 |
Limits To: | 0.2 MI N OF MCKINNEY BAYOU | Estimate: | $281,391 |
Length: | 3.8 Miles | Actual: | $303,290 |
District: | Atlanta | Let Date: | JAN 2006 |
Highway: | FM 559 | Let Status: | Actual |
Project ID: | SFT 1020-1-48 | CSJ: | 1020-01-048 |
Description: | WIDEN LANES ON EXISTING ROADWAY | Handling Code: |
|
Limits From: | 1.1 MI N OF FM 2253 | Fund Cat: | 8 |
Limits To: | 0.1 MI N OF FM 989 | Estimate: | $979,466 |
Length: | 7.0 Miles | Actual: | $873,715 |
District: | Atlanta | Let Date: | JAN 2006 |
Highway: | FM 990 | Let Status: | Actual |
Project ID: | SFT 1213-1-11 | CSJ: | 1213-01-011 |
Description: | WIDEN LANES ON EXISTING ROADWAY | Handling Code: |
|
Limits From: | FM 561 | Fund Cat: | 8 |
Limits To: | US 67 | Estimate: | $312,742 |
Length: | 3.4 Miles | Actual: | $330,802 |
District: | Atlanta | Let Date: | JAN 2006 |
Highway: | FM 1397 | Let Status: | Actual |
Project ID: | SFT 1231-2-9 | CSJ: | 1231-02-009 |
Description: | WIDEN LANES ON EXISTING ROADWAY | Handling Code: |
|
Limits From: | 5.0 MI. N. OF FM 559 | Fund Cat: | 8 |
Limits To: | FM 559 | Estimate: | $652,972 |
Length: | 5.0 Miles | Actual: | $596,978 |
District: | Atlanta | Let Date: | JAN 2006 |
Highway: | FM 2253 | Let Status: | Actual |
Project ID: | SFT 2048-1-13 | CSJ: | 2048-01-013 |
Description: | WIDEN LANES ON EXISTING ROADWAY | Handling Code: |
|
Limits From: | FM 559 | Fund Cat: | 8 |
Limits To: | 0.1 MI S OF IH 30 | Estimate: | $519,112 |
Length: | 6.0 Miles | Actual: | $548,399 |
District: | Atlanta | Let Date: | JAN 2006 |
Highway: | FM 990 | Let Status: | Actual |
Project ID: | SFT 2527-1-11 | CSJ: | 2527-01-011 |
Description: | WIDEN LANES ON EXISTING ROADWAY | Handling Code: |
|
Limits From: | FM 1840 | Fund Cat: | 8 |
Limits To: | FM 561 | Estimate: | $902,793 |
Length: | 10.7 Miles | Actual: | $952,130 |
District: | Atlanta | Let Date: | JAN 2006 |
Highway: | FM 2624 | Let Status: | Actual |
Project ID: | SFT 2575-1-6 | CSJ: | 2575-01-006 |
Description: | WIDEN LANES ON EXISTING ROADWAY | Handling Code: |
|
Limits From: | SH 8 | Fund Cat: | 8 |
Limits To: | 5.4 MI E OF SH 8 | Estimate: | $443,813 |
Length: | 5.4 Miles | Actual: | $442,456 |
District: | Atlanta | Let Date: | JAN 2006 |
Highway: | FM 991 | Let Status: | Actual |
Project ID: | SFT 2776-1-11 | CSJ: | 2776-01-011 |
Description: | WIDEN LANES ON EXISTING ROADWAY | Handling Code: |
|
Limits From: | US 67 | Fund Cat: | 8 |
Limits To: | 1.8 MI S OF US 67 | Estimate: | $215,766 |
Length: | 1.8 Miles | Actual: | $196,852 |
Back... |
Totals for 0010-19-008 | ||
---|---|---|---|
Length: | 61.0 Miles | ||
Estimate: | $5,937,144 | ||
Actual: | $5,963,878 | ||
CCSJ: 0046-06-063 | |||
District: | Atlanta | Let Date: | JUL 2006 |
Highway: | US 82 | Let Status: | Actual |
Project ID: | SFT 46-6-63 | CSJ: | 0046-06-063 |
Description: | SAFETY TREAT FIXED OBJECTS, INSTALL PROTECTION & MODERNIZE | Handling Code: |
|
Limits From: | FM 989 | Fund Cat: | 8 |
Limits To: | FM 1398 (W) | Estimate: | $510,595 |
Length: | 7.6 Miles | Actual: | $539,383 |
Bid Tabulations Back... |
Totals for 0046-06-063 | ||
Length: | 7.6 Miles | ||
Estimate: | $510,595 | ||
Actual: | $539,383 | ||
CCSJ: 0330-03-020 | |||
District: | Atlanta | Let Date: | DEC 2005 |
Highway: | FM 561 | Let Status: | Actual |
Project ID: | BR 2006(109) | CSJ: | 0330-03-020 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | AT WEAVER CREEK | Fund Cat: | 6 |
Limits To: | . | Estimate: | $1,212,747 |
Length: | 0.4 Miles | Actual: | $1,023,555 |
Back... |
Totals for 0330-03-020 | ||
Length: | 0.4 Miles | ||
Estimate: | $1,212,747 | ||
Actual: | $1,023,555 | ||
CCSJ: 0610-07-085 | |||
District: | Atlanta | Let Date: | JUL 2006 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | SFT 218-2-34 | CSJ: | 0218-02-034 |
Description: | CONSTRUCT TURNAROUNDS | Handling Code: |
|
Limits From: | AT INTERSECTION OF US 82 | Fund Cat: | 1 |
Limits To: | . | Estimate: | $882,959 |
Length: | 0.1 Miles | Actual: | $1,627,524 |
District: | Atlanta | Let Date: | JUL 2006 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | SFT 218-2-35 | CSJ: | 0218-02-035 |
Description: | SAFETY TREAT FIXED OBJECTS, ETC. | Handling Code: |
|
Limits From: | 0.3 MI S OF IH 30 | Fund Cat: | 1 |
Limits To: | 0.3 MI S OF US 82 | Estimate: | $3,088,264 |
Length: | 0.6 Miles | Actual: | $3,974,333 |
District: | Atlanta | Let Date: | JUL 2006 |
Highway: | IH 30 | Let Status: | Actual |
Project ID: | IMD 0303(120) | CSJ: | 0610-07-085 |
Description: | CONVERT FRONTAGE ROADS TO ONE - WAY OPERATIONS, RELOCATE RAMPS | Handling Code: |
|
Limits From: | 0.6 MI W OF FM 989 | Fund Cat: | 10 |
Limits To: | ARKANSAS STATE LINE | Estimate: | $91,561,904 |
Length: | 5.9 Miles | Actual: | 112,675,353 |
District: | Atlanta | Let Date: | JUL 2006 |
Highway: | IH 30 | Let Status: | Actual |
Project ID: | BR 2006(661) | CSJ: | 0610-07-092 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | AT US 59 UNDERPASS NB & SB | Fund Cat: | 1 |
Limits To: | . | Estimate: | $18,820,372 |
Length: | 1.6 Miles | Actual: | $23,595,564 |
District: | Atlanta | Let Date: | JUL 2006 |
Highway: | IH 30 | Let Status: | Actual |
Project ID: | BR 2006(661) | CSJ: | 0610-07-093 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | AT US 59/71 (STATELINE) INTERCHANGE | Fund Cat: | 1 |
Limits To: | . | Estimate: | $6,393,472 |
Length: | 0.9 Miles | Actual: | $8,366,679 |
Bid Tabulations Back... |
Totals for 0610-07-085 | ||
Length: | 9.1 Miles | ||
Estimate: | 120,746,971 | ||
Actual: | 150,239,453 |
|
|