Detail Letting Schedule for Hopkins County (FY 2006)
| Detail Letting Schedule for Hopkins County (FY 2006) | ||||
| Last Update: Monday, August 28, 2006 | 
| Hopkins County (FY 2006) | 
| CCSJ: 0009-09-083 | |||
| District: | Paris | Let Date: | MAR 2006 | 
| Highway: | IH 30 | Let Status: | Actual | 
| Project ID: | STP 2001(108)TE | CSJ: | 0009-09-083 | 
| Description: | RIGHT OF WAY ACQUISITION AND RELOCATION ASSISTANCE AND | Handling Code: | XX | 
| Limits From: | ON IH 30, 1 MILE EAST OF CUMBY | Fund Cat: | 9 | 
| Limits To: | . | Estimate: | |
| Length: | 0.0 Miles | Actual: | $750,000 | 
| Back... | Totals for 0009-09-083 | ||
|---|---|---|---|
| Length: | 0.0 Miles | ||
| Estimate: | |||
| Actual: | $750,000 | ||
| CCSJ: 0009-09-090 | |||
| District: | Paris | Let Date: | JAN 2006 | 
| Highway: | IH 30 | Let Status: | Actual | 
| Project ID: | CPM 9-9-90 | CSJ: | 0009-09-090 | 
| Description: | SEAL COAT | Handling Code: | |
| Limits From: | HUNT COUNTY LINE | Fund Cat: | 1 | 
| Limits To: | 0.25 MILES E OF FM 499 | Estimate: | $429,808 | 
| Length: | 3.4 Miles | Actual: | $356,496 | 
| District: | Paris | Let Date: | JAN 2006 | 
| Highway: | IH 30 | Let Status: | Actual | 
| Project ID: | CPM 9-13-140 | CSJ: | 0009-13-140 | 
| Description: | SEAL COAT | Handling Code: | |
| Limits From: | ROCKWALL COUNTY LINE | Fund Cat: | 1 | 
| Limits To: | HOPKINS COUNTY LINE | Estimate: | $1,542,223 | 
| Length: | 29.8 Miles | Actual: | $1,555,526 | 
| District: | Paris | Let Date: | JAN 2006 | 
| Highway: | IH 30 | Let Status: | Actual | 
| Project ID: | CPM 610-2-46 | CSJ: | 0610-02-046 | 
| Description: | SEAL COAT | Handling Code: | |
| Limits From: | HOPKINS COUNTY LINE | Fund Cat: | 1 | 
| Limits To: | TITUS COUNTY LINE | Estimate: | $548,852 | 
| Length: | 10.7 Miles | Actual: | $554,486 | 
| Back... | Totals for 0009-09-090 | ||
| Length: | 43.9 Miles | ||
| Estimate: | $2,520,883 | ||
| Actual: | $2,466,508 | ||
| CCSJ: 0009-09-091 | |||
| District: | Paris | Let Date: | NOV 2005 | 
| Highway: | IH 30 | Let Status: | Actual | 
| Project ID: | CPM 9-9-91 | CSJ: | 0009-09-091 | 
| Description: | SEAL COAT | Handling Code: | |
| Limits From: | HUNT COUNTY LINE (NORTH FR) | Fund Cat: | 1 | 
| Limits To: | 0.314 MILES W OF SH 19 | Estimate: | $314,718 | 
| Length: | 13.1 Miles | Actual: | $314,177 | 
| District: | Paris | Let Date: | NOV 2005 | 
| Highway: | IH 30 | Let Status: | Actual | 
| Project ID: | CPM 9-9-92 | CSJ: | 0009-09-092 | 
| Description: | SEAL COAT | Handling Code: | |
| Limits From: | HUNT COUNTY LINE (SOUTH FR) | Fund Cat: | 1 | 
| Limits To: | 0.314 MILES W OF SH 19 | Estimate: | $261,484 | 
| Length: | 13.1 Miles | Actual: | $294,259 | 
| District: | Paris | Let Date: | NOV 2005 | 
| Highway: | SH 37 | Let Status: | Actual | 
| Project ID: | CPM 189-5-42 | CSJ: | 0189-05-042 | 
| Description: | SEAL COAT | Handling Code: | |
| Limits From: | RED RIVER COUNTY LINE | Fund Cat: | 1 | 
| Limits To: | BS 37E | Estimate: | $378,804 | 
| Length: | 11.2 Miles | Actual: | $430,024 | 
| District: | Paris | Let Date: | NOV 2005 | 
| Highway: | SH 154 | Let Status: | Actual | 
| Project ID: | CPM 401-1-21 | CSJ: | 0401-01-021 | 
| Description: | SEAL COAT | Handling Code: | |
| Limits From: | 0.27 MILES S OF TCR 363 | Fund Cat: | 1 | 
| Limits To: | WOOD COUNTY LINE | Estimate: | $150,513 | 
| Length: | 7.9 Miles | Actual: | $171,579 | 
| Back... | Totals for 0009-09-091 | ||
| Length: | 45.3 Miles | ||
| Estimate: | $1,105,519 | ||
| Actual: | $1,210,039 | ||
| CCSJ: 0083-03-043 | |||
| District: | Paris | Let Date: | MAY 2006 | 
| Highway: | SH 11 | Let Status: | Actual | 
| Project ID: | STP 2006(522) | CSJ: | 0083-03-043 | 
| Description: | REHAB EXISTING ROAD | Handling Code: | |
| Limits From: | 0.087 MILES EAST OF SH 154 | Fund Cat: | 1 | 
| Limits To: | 0.537 MILES WEST OF FM 1870 | Estimate: | $5,523,855 | 
| Length: | 4.7 Miles | Actual: | $6,515,212 | 
| Back... | Totals for 0083-03-043 | ||
| Length: | 4.7 Miles | ||
| Estimate: | $5,523,855 | ||
| Actual: | $6,515,212 | ||
| 
 
 | 
|  |