Detail Letting Schedule for Van Zandt County (FY 2006)
Detail Letting Schedule for Van Zandt County (FY 2006) | ||||
Last Update: Monday, August 28, 2006 |
Van Zandt County (FY 2006) |
CCSJ: 0095-06-057 | |||
District: | Tyler | Let Date: | MAY 2006 |
Highway: | US 80 | Let Status: | Actual |
Project ID: | STP 2006(494) | CSJ: | 0095-06-057 |
Description: | RESURFACE ROADWAY | Handling Code: |
|
Limits From: | 3.2 MI W OF FM 2965 AT KAUFMAN C/L, | Fund Cat: | 1 |
Limits To: | 0.2 MI E OF SH 64 IN WILLS POINT | Estimate: | $2,422,204 |
Length: | 5.5 Miles | Actual: | $2,934,427 |
Back... |
Totals for 0095-06-057 | ||
---|---|---|---|
Length: | 5.5 Miles | ||
Estimate: | $2,422,204 | ||
Actual: | $2,934,427 | ||
CCSJ: 0095-06-060 | |||
District: | Tyler | Let Date: | NOV 2005 |
Highway: | US 80 | Let Status: | Actual |
Project ID: | CPM 95-6-60 | CSJ: | 0095-06-060 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.2 MI EAST OF SH 19, EAST | Fund Cat: | 1 |
Limits To: | 0.8 MILES EAST OF FM 19 | Estimate: | $1,039,309 |
Length: | 0.5 Miles | Actual: | $1,083,423 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | US 80 | Let Status: | Actual |
Project ID: | CPM 95-7-54 | CSJ: | 0095-07-054 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.8 MI EAST OF FM 19, EAST | Fund Cat: | 1 |
Limits To: | 0.25 MI EAST OF FM 857 | Estimate: | $472,362 |
Length: | 7.9 Miles | Actual: | $437,983 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | US 80 | Let Status: | Actual |
Project ID: | CPM 96-2-46 | CSJ: | 0096-02-046 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | FM 778, EAST | Fund Cat: | 1 |
Limits To: | 0.5 MI W OF FM 14 IN HAWKINS (EBL) | Estimate: | $213,899 |
Length: | 6.0 Miles | Actual: | $196,266 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | SH 19 | Let Status: | Actual |
Project ID: | CPM 108-1-26 | CSJ: | 0108-01-026 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | US 80, SOUTH | Fund Cat: | 1 |
Limits To: | IH 20 | Estimate: | $361,383 |
Length: | 7.4 Miles | Actual: | $330,493 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | SH 19 | Let Status: | Actual |
Project ID: | CPM 108-2-27 | CSJ: | 0108-02-027 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | FM 858, SOUTH | Fund Cat: | 1 |
Limits To: | 0.4 MI S OF FM 1861 (HENDERSON C/L) | Estimate: | $214,464 |
Length: | 4.0 Miles | Actual: | $199,891 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | US 84 | Let Status: | Actual |
Project ID: | CPM 109-1-50 | CSJ: | 0109-01-050 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | US 287 (0.35 MI SW OF US 79), E & S | Fund Cat: | 1 |
Limits To: | US 287(0.3 MI S OF SH 19)IN P'STINE | Estimate: | $69,289 |
Length: | 1.4 Miles | Actual: | $64,923 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | US 287 | Let Status: | Actual |
Project ID: | CPM 109-1-51 | CSJ: | 0109-01-051 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | US 84, SOUTHEAST | Fund Cat: | 1 |
Limits To: | 0.8 MI S OF LP 256 IN PALESTINE | Estimate: | $192,436 |
Length: | 2.6 Miles | Actual: | $177,610 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | US 84 | Let Status: | Actual |
Project ID: | CPM 123-1-32 | CSJ: | 0123-01-032 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | SH 19, EAST | Fund Cat: | 1 |
Limits To: | 1.0 MI EAST OF PR 70 | Estimate: | $275,956 |
Length: | 4.5 Miles | Actual: | $254,722 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | US 84 | Let Status: | Actual |
Project ID: | CPM 123-1-33 | CSJ: | 0123-01-033 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 3.0 MI EAST OF FM 3266 (NBL), E | Fund Cat: | 1 |
Limits To: | 1.9 MI W OF FM 747 (NECHES RIVER) | Estimate: | $171,127 |
Length: | 5.6 Miles | Actual: | $160,161 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | US 259 | Let Status: | Actual |
Project ID: | CPM 138-3-43 | CSJ: | 0138-03-043 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.1 MI SOUTH US 79, SOUTH | Fund Cat: | 1 |
Limits To: | 0.1 MI SOUTH OF FM 1798 | Estimate: | $437,666 |
Length: | 10.6 Miles | Actual: | $399,222 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | SH 31 | Let Status: | Actual |
Project ID: | CPM 164-4-153 | CSJ: | 0164-04-153 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | LP 323, EAST | Fund Cat: | 1 |
Limits To: | 0.2 MI W OF US 27171 | Estimate: | $251,811 |
Length: | 2.7 Miles | Actual: | $235,310 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | US 271 | Let Status: | Actual |
Project ID: | CPM 165-1-99 | CSJ: | 0165-01-099 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.1 MI NORTH OF IH 20, SOUTH | Fund Cat: | 1 |
Limits To: | 0.1 MILE SOUTH OF IH 20 | Estimate: | $54,909 |
Length: | 0.3 Miles | Actual: | $51,913 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | US 271 | Let Status: | Actual |
Project ID: | CPM 165-3-30 | CSJ: | 0165-03-030 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.1 MI N OF LP 485 IN GLADEWATER, S | Fund Cat: | 1 |
Limits To: | 1.1 MI S OF SH 135 (SMITH C/L) | Estimate: | $166,716 |
Length: | 2.2 Miles | Actual: | $153,427 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | SH 37 | Let Status: | Actual |
Project ID: | CPM 190-3-73 | CSJ: | 0190-03-073 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | SH 154 W, EAST | Fund Cat: | 1 |
Limits To: | SH 154 E | Estimate: | $41,334 |
Length: | 0.3 Miles | Actual: | $38,133 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | US 69 | Let Status: | Actual |
Project ID: | CPM 191-2-58 | CSJ: | 0191-02-058 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.1 MI S OF US 175, SOUTH | Fund Cat: | 1 |
Limits To: | 0.9 MI N OF LP 456, IN JACKSONVILLE | Estimate: | $190,539 |
Length: | 2.2 Miles | Actual: | $178,346 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | US 175 | Let Status: | Actual |
Project ID: | CPM 198-1-26 | CSJ: | 0198-01-026 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 1.2 MI W OF FM 317, SE | Fund Cat: | 1 |
Limits To: | 4.0 MI W OF FM 2588 | Estimate: | $469,369 |
Length: | 6.7 Miles | Actual: | $431,733 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | US 175 | Let Status: | Actual |
Project ID: | CPM 198-2-31 | CSJ: | 0198-02-031 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 1.4 MI SE OF FM 804, SE | Fund Cat: | 1 |
Limits To: | 1.84 MI E OF FM 315 (ANDERSON C/L) | Estimate: | $355,016 |
Length: | 11.2 Miles | Actual: | $332,426 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | US 175 | Let Status: | Actual |
Project ID: | CPM 198-3-30 | CSJ: | 0198-03-030 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 1.84 MI E OF FM 315(ANDERSON C/L),E | Fund Cat: | 1 |
Limits To: | 0.1 MI WEST OF SH 155, IN FRANKSTON | Estimate: | $194,246 |
Length: | 3.6 Miles | Actual: | $177,894 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | FM 347 | Let Status: | Actual |
Project ID: | CPM 198-4-35 | CSJ: | 0198-04-035 |
Description: | SEAL COAT AND PAVEMEMT MARKINGS | Handling Code: |
|
Limits From: | 0.1 MI S OF US 175 (LINCOLN ST), S | Fund Cat: | 1 |
Limits To: | 0.5 MI S OF US 175 IN JACKSONVILLE | Estimate: | $44,496 |
Length: | 0.5 Miles | Actual: | $41,113 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | FM 1253 | Let Status: | Actual |
Project ID: | CPM 203-8-13 | CSJ: | 0203-08-013 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | US 80 | Fund Cat: | 1 |
Limits To: | SH 110 | Estimate: | $275,385 |
Length: | 11.7 Miles | Actual: | $253,949 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | US 84 | Let Status: | Actual |
Project ID: | CPM 205-14-6 | CSJ: | 0205-14-006 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | US 79, EAST | Fund Cat: | 1 |
Limits To: | US 287 | Estimate: | $87,018 |
Length: | 1.0 Miles | Actual: | $80,020 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | SH 43 | Let Status: | Actual |
Project ID: | CPM 207-1-17 | CSJ: | 0207-01-017 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | FM 1251, SW | Fund Cat: | 1 |
Limits To: | 0.1 MI NE OF US 259 IN HENDERSON | Estimate: | $238,795 |
Length: | 3.9 Miles | Actual: | $219,554 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | SH 43 | Let Status: | Actual |
Project ID: | CPM 207-2-23 | CSJ: | 0207-02-023 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 2.0 MI W OF FM 2658, SW | Fund Cat: | 1 |
Limits To: | FM 1251 | Estimate: | $452,653 |
Length: | 8.0 Miles | Actual: | $416,550 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | SH 64 | Let Status: | Actual |
Project ID: | CPM 245-5-45 | CSJ: | 0245-05-045 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 2.2 MI W OF FM 279 (VAN ZANDT C/L) | Fund Cat: | 1 |
Limits To: | 2.9 MI W LP 323 | Estimate: | $238,966 |
Length: | 5.0 Miles | Actual: | $221,137 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | SH 64 | Let Status: | Actual |
Project ID: | CPM 245-6-73 | CSJ: | 0245-06-073 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.1 MILE EAST OF LP 323 | Fund Cat: | 1 |
Limits To: | US 69 (GLENWOOD) | Estimate: | $96,720 |
Length: | 1.2 Miles | Actual: | $89,035 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | SH 64 | Let Status: | Actual |
Project ID: | CPM 245-8-42 | CSJ: | 0245-08-042 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.8 MI E OF SH 323 IN HENDERSON, E | Fund Cat: | 1 |
Limits To: | 0.1 MI W OF SH 43 (TRAFFIC STAR) | Estimate: | $43,257 |
Length: | 0.4 Miles | Actual: | $41,875 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | SH 64 | Let Status: | Actual |
Project ID: | CPM 245-19-21 | CSJ: | 0245-19-021 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 5.4 MI E OF FM 314 | Fund Cat: | 1 |
Limits To: | 2.2 MI W OF FM 279 (SMITH C/L) | Estimate: | $67,238 |
Length: | 2.2 Miles | Actual: | $62,465 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | US 271 | Let Status: | Actual |
Project ID: | CPM 248-6-13 | CSJ: | 0248-06-013 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.1 MI N OF FM 2275, EAST | Fund Cat: | 1 |
Limits To: | US 80 | Estimate: | $149,403 |
Length: | 1.2 Miles | Actual: | $135,120 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | SH 110 | Let Status: | Actual |
Project ID: | CPM 345-1-53 | CSJ: | 0345-01-053 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.1 MI N OF LP 323, SOUTH | Fund Cat: | 1 |
Limits To: | 0.1 MI N OF FM 346 | Estimate: | $565,461 |
Length: | 6.9 Miles | Actual: | $523,080 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | FM 347 | Let Status: | Actual |
Project ID: | CPM 378-7-24 | CSJ: | 0378-07-024 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.5 MI S US 175 (CHEROKEE ST), S | Fund Cat: | 1 |
Limits To: | 0.1 MI N OF LP 456 IN JACKSONVILLE | Estimate: | $165,938 |
Length: | 2.4 Miles | Actual: | $151,218 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | SH 154 | Let Status: | Actual |
Project ID: | CPM 401-2-29 | CSJ: | 0401-02-029 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.2 MI W OF SH 37, EAST | Fund Cat: | 1 |
Limits To: | SH 37 | Estimate: | $20,693 |
Length: | 0.2 Miles | Actual: | $18,902 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | FM 2710 | Let Status: | Actual |
Project ID: | CPM 429-4-2 | CSJ: | 0429-04-002 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | FM 16, EAST | Fund Cat: | 1 |
Limits To: | 5.3 MI W OF FM 14 | Estimate: | $99,371 |
Length: | 4.0 Miles | Actual: | $90,759 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | FM 756 | Let Status: | Actual |
Project ID: | CPM 492-4-29 | CSJ: | 0492-04-029 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.1 MI S LP 323, SOUTH | Fund Cat: | 1 |
Limits To: | 2.8 MI OF LP 323 | Estimate: | $170,334 |
Length: | 2.4 Miles | Actual: | $157,279 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | SH 110 | Let Status: | Actual |
Project ID: | CPM 505-2-38 | CSJ: | 0505-02-038 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | IH 20 (S FRONTAGE RD), E | Fund Cat: | 1 |
Limits To: | 0.2 MI W OF FM 849 | Estimate: | $147,144 |
Length: | 4.2 Miles | Actual: | $138,780 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | SH 155 | Let Status: | Actual |
Project ID: | CPM 520-6-39 | CSJ: | 0520-06-039 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | BECKHAM ST FROM SH 31 (FRONT ST), S | Fund Cat: | 1 |
Limits To: | SH 64 (5TH ST) IN TYLER | Estimate: | $128,552 |
Length: | 1.0 Miles | Actual: | $118,866 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | FM 16 | Let Status: | Actual |
Project ID: | CPM 522-3-22 | CSJ: | 0522-03-022 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | IH 20 (SERVICE ROAD), EAST | Fund Cat: | 1 |
Limits To: | FM 314, IN VAN | Estimate: | $90,021 |
Length: | 3.0 Miles | Actual: | $82,553 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | FM 13 | Let Status: | Actual |
Project ID: | CPM 591-1-6 | CSJ: | 0591-01-006 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | SH 135 IN TROUP, S | Fund Cat: | 1 |
Limits To: | O.1 MI S OF FM 1089 (CHEROKEE C/L) | Estimate: | $41,435 |
Length: | 1.1 Miles | Actual: | $38,142 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | FM 13 | Let Status: | Actual |
Project ID: | CPM 591-2-16 | CSJ: | 0591-02-016 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 3.4 MI E OF FM 856 (CHEROKEE C/L),E | Fund Cat: | 1 |
Limits To: | SH 42 | Estimate: | $81,626 |
Length: | 3.0 Miles | Actual: | $74,439 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | FM 13 | Let Status: | Actual |
Project ID: | CPM 591-2-17 | CSJ: | 0591-02-017 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.1 MI E OF LP 571, EAST | Fund Cat: | 1 |
Limits To: | 0.1 MI W OF BU 79 IN HENDERSON | Estimate: | $123,311 |
Length: | 2.4 Miles | Actual: | $112,555 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | FM 13 | Let Status: | Actual |
Project ID: | CPM 591-3-8 | CSJ: | 0591-03-008 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.1 MI S OF FM 1089 (SMITH C/L), E | Fund Cat: | 1 |
Limits To: | 3.0 MI W OF SH 42 (RUSK C/L) | Estimate: | $210,543 |
Length: | 7.6 Miles | Actual: | $192,520 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | FM 47 | Let Status: | Actual |
Project ID: | CPM 646-3-11 | CSJ: | 0646-03-011 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | SH 243, S | Fund Cat: | 1 |
Limits To: | SH 198 | Estimate: | $244,220 |
Length: | 9.3 Miles | Actual: | $229,144 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | FM 316 | Let Status: | Actual |
Project ID: | CPM 646-7-7 | CSJ: | 0646-07-007 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | FM 1861 (VAN ZANDT C/L), S | Fund Cat: | 1 |
Limits To: | US 175 | Estimate: | $136,431 |
Length: | 4.5 Miles | Actual: | $127,285 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | FM 241 | Let Status: | Actual |
Project ID: | CPM 1124-3-10 | CSJ: | 1124-03-010 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.1 MI S OF FM 752 IN RUSK, S | Fund Cat: | 1 |
Limits To: | 0.1 MI N OF SH 21 | Estimate: | $305,867 |
Length: | 12.5 Miles | Actual: | $280,928 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | FM 2962 | Let Status: | Actual |
Project ID: | CPM 1150-3-4 | CSJ: | 1150-03-004 |
Description: | SEAL COAT, PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | US 84, SOUTH | Fund Cat: | 1 |
Limits To: | END OF ST. MAINT | Estimate: | $80,209 |
Length: | 3.4 Miles | Actual: | $73,659 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | FM 851 | Let Status: | Actual |
Project ID: | CPM 1150-4-4 | CSJ: | 1150-04-004 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.1 MI S OF FM 343, SOUTH | Fund Cat: | 1 |
Limits To: | 0.1 MI E OF US 69, IN ALTO | Estimate: | $231,310 |
Length: | 9.9 Miles | Actual: | $212,755 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | FM 850 | Let Status: | Actual |
Project ID: | CPM 1163-2-28 | CSJ: | 1163-02-028 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | SH 135 IN OVERTON, EAST | Fund Cat: | 1 |
Limits To: | 0.6 MI EAST OF FM 2276 | Estimate: | $303,745 |
Length: | 10.5 Miles | Actual: | $278,541 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | FM 837 | Let Status: | Actual |
Project ID: | CPM 1666-1-8 | CSJ: | 1666-01-008 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.1 MI E OF FM 315, NE | Fund Cat: | 1 |
Limits To: | SH 155 | Estimate: | $192,205 |
Length: | 8.5 Miles | Actual: | $177,269 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | LP 323 | Let Status: | Actual |
Project ID: | CPM 2075-1-46 | CSJ: | 2075-01-046 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | SH 31 (WEST), NORTH AND EAST | Fund Cat: | 1 |
Limits To: | 0.1 MI WEST OF US 69, IN TYLER | Estimate: | $309,514 |
Length: | 2.8 Miles | Actual: | $281,445 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | LP 323 | Let Status: | Actual |
Project ID: | CPM 2075-2-54 | CSJ: | 2075-02-054 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.1 MI N OF SH 155 (S), NORTH | Fund Cat: | 1 |
Limits To: | 0.1 MI S OF SH 31 (WEST) IN TYLER | Estimate: | $322,941 |
Length: | 2.6 Miles | Actual: | $304,628 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | FM 2908 | Let Status: | Actual |
Project ID: | CPM 2956-1-5 | CSJ: | 2956-01-005 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.1 MI S OF US 271, SOUTH | Fund Cat: | 1 |
Limits To: | 0.1 MI N OF SH 31 | Estimate: | $112,546 |
Length: | 5.0 Miles | Actual: | $103,665 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | FM 2710 | Let Status: | Actual |
Project ID: | CPM 3085-1-2 | CSJ: | 3085-01-002 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 4.2 MI NE OF FM 16 (CR 452), SE | Fund Cat: | 1 |
Limits To: | FM 14 | Estimate: | $124,740 |
Length: | 5.3 Miles | Actual: | $113,595 |
District: | Tyler | Let Date: | NOV 2005 |
Highway: | FM 3080 | Let Status: | Actual |
Project ID: | CPM 3156-2-5 | CSJ: | 3156-02-005 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | SH 198 (AT KAUFMAN C/L), EAST | Fund Cat: | 1 |
Limits To: | FM 316 | Estimate: | $150,910 |
Length: | 6.7 Miles | Actual: | $137,970 |
Back... |
Totals for 0095-06-060 | ||
Length: | 234.0 Miles | ||
Estimate: | $11,224,829 | ||
Actual: | $10,484,671 | ||
CCSJ: 0095-07-052 | |||
District: | Tyler | Let Date: | MAY 2006 |
Highway: | US 80 | Let Status: | Actual |
Project ID: | BR 2006(495) | CSJ: | 0095-07-052 |
Description: | REPLACE BRIDGES AND APPROACHES | Handling Code: |
|
Limits From: | AT GRAND SALINE CREEK (WEST BOUND) | Fund Cat: | 6 |
Limits To: | STR#046 | Estimate: | $2,292,422 |
Length: | 0.8 Miles | Actual: | $2,477,889 |
Back... |
Totals for 0095-07-052 | ||
Length: | 0.8 Miles | ||
Estimate: | $2,292,422 | ||
Actual: | $2,477,889 | ||
CCSJ: 0245-03-020 | |||
District: | Tyler | Let Date: | JAN 2006 |
Highway: | FM 279 | Let Status: | Actual |
Project ID: | SFT 245-3-20 | CSJ: | 0245-03-020 |
Description: | WIDEN ROADWAY TO 28' | Handling Code: |
|
Limits From: | SH 64, SE | Fund Cat: | 1 |
Limits To: | FM 314 IN EDOM | Estimate: | $1,757,017 |
Length: | 8.8 Miles | Actual: | $2,086,020 |
District: | Tyler | Let Date: | JAN 2006 |
Highway: | FM 279 | Let Status: | Actual |
Project ID: | SFT 245-4-19 | CSJ: | 0245-04-019 |
Description: | WIDEN ROADWAY TO 28' | Handling Code: |
|
Limits From: | FM 314 IN EDOM , SE | Fund Cat: | 1 |
Limits To: | 1 MI W OF SH 64 (BEG NECHES RV BRG) | Estimate: | $2,136,186 |
Length: | 9.6 Miles | Actual: | $2,569,439 |
District: | Tyler | Let Date: | JAN 2006 |
Highway: | SH 110 | Let Status: | Actual |
Project ID: | SFT 505-2-37 | CSJ: | 0505-02-037 |
Description: | ADD LEFT TURN LANE | Handling Code: |
|
Limits From: | AT FM 3271 | Fund Cat: | 8 |
Limits To: | NW OF TYLER | Estimate: | $212,110 |
Length: | 0.2 Miles | Actual: | $249,910 |
District: | Tyler | Let Date: | JAN 2006 |
Highway: | SH 243 | Let Status: | Actual |
Project ID: | SFT 522-2-34 | CSJ: | 0522-02-034 |
Description: | ADD LEFT TURN LANE | Handling Code: |
|
Limits From: | AT CR 2506 | Fund Cat: | 8 |
Limits To: | 3.8 MI E OF FM 47 | Estimate: | $145,224 |
Length: | 0.2 Miles | Actual: | $174,378 |
District: | Tyler | Let Date: | JAN 2006 |
Highway: | FM 316 | Let Status: | Actual |
Project ID: | SFT 646-4-8 | CSJ: | 0646-04-008 |
Description: | WIDEN ROADWAY TO 24' | Handling Code: |
|
Limits From: | SH 198, S | Fund Cat: | 8 |
Limits To: | 1.5 MI S OF FM 3080 (HENDERSON C/L) | Estimate: | $603,738 |
Length: | 5.0 Miles | Actual: | $668,948 |
District: | Tyler | Let Date: | JAN 2006 |
Highway: | FM 773 | Let Status: | Actual |
Project ID: | SFT 1099-1-7 | CSJ: | 1099-01-007 |
Description: | WIDEN ROADWAY TO 28' | Handling Code: |
|
Limits From: | FM 858, S | Fund Cat: | 1 |
Limits To: | 0.2 MI S OF FM 2339 (HENDERSON C/L) | Estimate: | $1,033,544 |
Length: | 5.9 Miles | Actual: | $1,172,578 |
District: | Tyler | Let Date: | JAN 2006 |
Highway: | FM 850 | Let Status: | Actual |
Project ID: | SFT 1163-1-18 | CSJ: | 1163-01-018 |
Description: | WIDEN ROADWAY TO 28' | Handling Code: |
|
Limits From: | SH 31 EAST OF TYLER, S | Fund Cat: | 8 |
Limits To: | 1 MI W OF FM 3053 (OVERTON CTY LIN) | Estimate: | $3,414,497 |
Length: | 15.0 Miles | Actual: | $3,864,751 |
District: | Tyler | Let Date: | JAN 2006 |
Highway: | RM 2909 | Let Status: | Actual |
Project ID: | SFT 2957-1-8 | CSJ: | 2957-01-008 |
Description: | WIDEN ROADWAY TO 28' | Handling Code: |
|
Limits From: | SH 19 S OF CANTON ,S | Fund Cat: | 8 |
Limits To: | FM 858 | Estimate: | $1,888,317 |
Length: | 9.0 Miles | Actual: | $2,168,061 |
District: | Tyler | Let Date: | JAN 2006 |
Highway: | FM 3053 | Let Status: | Actual |
Project ID: | SFT 3082-1-8 | CSJ: | 3082-01-008 |
Description: | WIDEN ROADWAY TO 28' | Handling Code: |
|
Limits From: | 0.2 MI S IF IH 20 | Fund Cat: | 8 |
Limits To: | 0.6 MI S OF SH 31 (RUSK C/L) | Estimate: | $941,935 |
Length: | 4.4 Miles | Actual: | $1,028,829 |
Back... |
Totals for 0245-03-020 | ||
Length: | 58.1 Miles | ||
Estimate: | $12,132,568 | ||
Actual: | $13,982,914 | ||
CCSJ: 0495-03-057 | |||
District: | Tyler | Let Date: | DEC 2005 |
Highway: | IH 20 | Let Status: | Actual |
Project ID: | STP 2005(964)SFT | CSJ: | 0495-03-057 |
Description: | INSTALL MEDIAN BARRIER | Handling Code: |
|
Limits From: | SH 19, EAST | Fund Cat: | 8 |
Limits To: | SMITH C/L | Estimate: | $7,826,697 |
Length: | 16.2 Miles | Actual: | $5,596,184 |
District: | Tyler | Let Date: | DEC 2005 |
Highway: | IH 20 | Let Status: | Actual |
Project ID: | STP 2005(964)SFT | CSJ: | 0495-04-057 |
Description: | INSTALL MEDIAN BARRIER | Handling Code: |
|
Limits From: | VAN ZANDT C/L, EAST | Fund Cat: | 8 |
Limits To: | 0.7 MI EAST OF US 69 | Estimate: | $6,192,652 |
Length: | 13.2 Miles | Actual: | $4,448,083 |
District: | Tyler | Let Date: | DEC 2005 |
Highway: | IH 20 | Let Status: | Actual |
Project ID: | STP 2005(964)SFT | CSJ: | 0495-05-043 |
Description: | INSTALL MEDIAN BARRIER | Handling Code: |
|
Limits From: | 0.9 MI EAST OF US 69, EAST | Fund Cat: | 8 |
Limits To: | 0.3 MI EAST OF US 271 | Estimate: | $5,059,094 |
Length: | 14.7 Miles | Actual: | $3,816,508 |
District: | Tyler | Let Date: | DEC 2005 |
Highway: | IH 20 | Let Status: | Actual |
Project ID: | STP 2005(964)SFT | CSJ: | 0495-06-028 |
Description: | INSTALL MEDIAN BARRIER | Handling Code: |
|
Limits From: | 0.5 MI W OF FM 757, W | Fund Cat: | 8 |
Limits To: | GREGG C/L | Estimate: | $4,255,752 |
Length: | 8.3 Miles | Actual: | $2,931,457 |
District: | Tyler | Let Date: | DEC 2005 |
Highway: | IH 20 | Let Status: | Actual |
Project ID: | STP 2005(964)SFT | CSJ: | 0495-07-063 |
Description: | INSTALL MEDIAN BARRIER | Handling Code: |
|
Limits From: | SMITH C/L, EAST | Fund Cat: | 8 |
Limits To: | HARRISON C/L | Estimate: | $7,924,103 |
Length: | 16.9 Miles | Actual: | $5,654,805 |
Back... |
Totals for 0495-03-057 | ||
Length: | 69.3 Miles | ||
Estimate: | $31,258,298 | ||
Actual: | $22,447,037 | ||
CCSJ: 0910-12-050 | |||
District: | Tyler | Let Date: | MAY 2006 |
Highway: | CR | Let Status: | Actual |
Project ID: | BR 2005(151) | CSJ: | 0910-12-050 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | CR 2702 AT LACY FORK | Fund Cat: | 6 |
Limits To: | STR# AA02-48-002 | Estimate: | $289,299 |
Length: | 0.1 Miles | Actual: | $309,963 |
District: | Tyler | Let Date: | MAY 2006 |
Highway: | CR | Let Status: | Actual |
Project ID: | BR 2005(152) | CSJ: | 0910-12-051 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | CR 3504 AT GILADON CREEK | Fund Cat: | 6 |
Limits To: | STR# AA01-21-003 | Estimate: | $220,701 |
Length: | 0.1 Miles | Actual: | $240,408 |
Back... |
Totals for 0910-12-050 | ||
Length: | 0.2 Miles | ||
Estimate: | $510,000 | ||
Actual: | $550,371 |
|
|