Detail Letting Schedule for Caldwell County (FY 2009)
|
Detail Letting Schedule for Caldwell County (FY 2009) |
|
Last Update: Monday, November 9, 2009 |
Caldwell County (FY 2009) |
CCSJ: 0286-02-028
|
District: |
Austin |
Let Date: |
MAY 2009 |
Highway: |
SH 80 |
Let Status: |
Actual |
Project ID: |
STP 2009(635)ES |
CSJ: |
0286-02-028 |
Description: |
PAVEMENT REPAIR, MILL, SEAL & OVERLAY |
Handling Code: |
|
Limits From: |
0.35 MILES WEST OF HAYS C/L |
Fund Cat: |
1 |
Limits To: |
FM 20 |
Estimate: |
$6,000,009 |
Length: |
11.7 Miles |
Actual: |
$3,794,305 |
|
Back...
|
Totals for 0286-02-028 |
Length: |
11.7 Miles |
Estimate: |
$6,000,009 |
Actual: |
$3,794,305 |
CCSJ: 0571-02-023
|
District: |
Austin |
Let Date: |
SEP 2008 |
Highway: |
FM 86 |
Let Status: |
Actual |
Project ID: |
BR 2009(010) |
CSJ: |
0571-02-023 |
Description: |
REPLACE BRIDGE & APPROACHES |
Handling Code: |
|
Limits From: |
AT PLUM CREEK |
Fund Cat: |
6 |
Limits To: |
. |
Estimate: |
$1,940,369 |
Length: |
0.3 Miles |
Actual: |
$1,999,591 |
|
Back...
|
Totals for 0571-02-023 |
Length: |
0.3 Miles |
Estimate: |
$1,940,369 |
Actual: |
$1,999,591 |
Handling Code |
Definition |
XX |
Project not processed through statewide letting |
TR |
Transfer of funds |
LC |
Project let through local entity |
NC |
Project not charged against district apportionment |
Let Status |
Definition |
Tentative |
Estimated letting date for this project |
Approved |
Project has administrative approval to be let |
Actual |
Project was let to contract |
|