Detail Letting Schedule for Delta County (FY 2009)

 
 
Last Update: Monday, November 9, 2009
Delta County (FY 2009)

CCSJ: 2003-03-005

District: Paris Let Date: MAY 2009
Highway: FM 2675 Let Status: Actual
Project ID: BR 2009(451) CSJ: 2003-03-005
Description: REPLACE BRIDGE AND APPROACHES Handling
Code:
 
Limits From: @ N. SULPHUR RIVER Fund Cat: 6
Limits To: . Estimate: $1,467,789
Length: 0.2 Miles Actual: $1,157,838
 
Back...

Totals for 2003-03-005
Length: 0.2 Miles
Estimate: $1,467,789
Actual: $1,157,838


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract