Detail Letting Schedule for Milam County (FY 2010)
| Detail Letting Schedule for Milam County (FY 2010) | ||||
| Last Update: Tuesday, November 2, 2010 |
| Milam County (FY 2010) |
CCSJ: 0204-08-053 | |||
| District: | Bryan | Let Date: | SEP 2009 |
| Highway: | US 79 | Let Status: | Actual |
| Project ID: | STP 2010(027)ES | CSJ: | 0204-08-053 |
| Description: | OVERLAY CONSISTING OF MILLING, HMA OVERLAY, SURFACE | Handling Code: |
|
| Limits From: | 0.4 MILE WEST OF FM 2095 | Fund Cat: | 1 |
| Limits To: | CEDAR PARK | Estimate: | $925,741 |
| Length: | 5.6 Miles | Actual: | $766,187 |
|
Back... |
Totals for 0204-08-053 | ||
|---|---|---|---|
| Length: | 5.6 Miles | ||
| Estimate: | $925,741 | ||
| Actual: | $766,187 | ||
CCSJ: 0204-08-054 | |||
| District: | Bryan | Let Date: | NOV 2009 |
| Highway: | US 79 | Let Status: | Actual |
| Project ID: | STP 2010(223)SB | CSJ: | 0204-08-054 |
| Description: | SAFETY IMPROVEMENT WORK CONSISTING OF SUBGRADE WIDENING, | Handling Code: |
|
| Limits From: | AT THE INTERSECTION OF US 79 | Fund Cat: | 8 |
| Limits To: | AND CR 346 | Estimate: | $249,312 |
| Length: | 0.5 Miles | Actual: | $271,316 |
| District: | Bryan | Let Date: | NOV 2009 |
| Highway: | US 77 | Let Status: | Actual |
| Project ID: | STP 2010(223)SB | CSJ: | 0211-01-028 |
| Description: | SAFETY IMPROVEMENT WORK CONSISTING OF SUBGRADE WIDENING, | Handling Code: |
|
| Limits From: | AT THE INTERSECTION OF US 77 | Fund Cat: | 8 |
| Limits To: | AND FM 487 | Estimate: | $241,735 |
| Length: | 0.5 Miles | Actual: | $270,410 |
| District: | Bryan | Let Date: | NOV 2009 |
| Highway: | US 77 | Let Status: | Actual |
| Project ID: | STP 2010(223)SB | CSJ: | 0211-01-029 |
| Description: | SAFETY IMPROVEMENT WORK CONSISTING OF SUBGRADE WIDENING, | Handling Code: |
|
| Limits From: | AT THE INTERSECTION OF US 77 | Fund Cat: | 8 |
| Limits To: | AND CR 322 | Estimate: | $243,631 |
| Length: | 0.5 Miles | Actual: | $268,690 |
|
Back... |
Totals for 0204-08-054 | ||
| Length: | 1.5 Miles | ||
| Estimate: | $734,678 | ||
| Actual: | $810,416 | ||
CCSJ: 0337-04-008 | |||
| District: | Bryan | Let Date: | NOV 2009 |
| Highway: | FM 1331 | Let Status: | Actual |
| Project ID: | STP 2010(224)SB | CSJ: | 0337-04-008 |
| Description: | SAFETY IMPROVEMENT WORK CONSISTING OF SUBGRADE WIDENING, | Handling Code: |
|
| Limits From: | AT THE INTERSECTION OF FM 1331 | Fund Cat: | 8 |
| Limits To: | AND COUNTY ROAD 439 | Estimate: | $126,970 |
| Length: | 0.4 Miles | Actual: | $165,550 |
| District: | Bryan | Let Date: | NOV 2009 |
| Highway: | FM 486 | Let Status: | Actual |
| Project ID: | STP 2010(224)SB | CSJ: | 0590-05-046 |
| Description: | SAFETY IMPROVEMENT WORK CONSISTING OF SUBGRADE WIDENING, | Handling Code: |
|
| Limits From: | AT THE INTERSECTION OF FM 486 | Fund Cat: | 8 |
| Limits To: | AND FM 1331 | Estimate: | $159,321 |
| Length: | 0.4 Miles | Actual: | $191,071 |
| District: | Bryan | Let Date: | NOV 2009 |
| Highway: | FM 486 | Let Status: | Actual |
| Project ID: | STP 2010(224)SB | CSJ: | 0590-05-047 |
| Description: | SAFETY IMPROVEMENT WORK CONSISTING OF SUBGRADE WIDENING, | Handling Code: |
|
| Limits From: | AT THE INTERSECTION OF FM 486 | Fund Cat: | 8 |
| Limits To: | AND COUNTY ROAD 455 | Estimate: | $118,093 |
| Length: | 0.4 Miles | Actual: | $157,319 |
|
Back... |
Totals for 0337-04-008 | ||
| Length: | 1.2 Miles | ||
| Estimate: | $404,384 | ||
| Actual: | $513,940 | ||
|
| |