Detail Letting Schedule for Wilson County (FY 2010)
Detail Letting Schedule for Wilson County (FY 2010) | ||||
Last Update: Tuesday, November 2, 2010 |
Wilson County (FY 2010) |
CCSJ: 0215-11-020 | |||
District: | San Antonio | Let Date: | NOV 2009 |
Highway: | FM 1681 | Let Status: | Actual |
Project ID: | STP 2009(637)ES | CSJ: | 0215-11-020 |
Description: | WIDEN EXISTING ROADWAY TO ADD SHOULDERS | Handling Code: |
|
Limits From: | UNION AT CR 448 | Fund Cat: | 1 |
Limits To: | GONZALES COUNTY LINE | Estimate: | $1,690,558 |
Length: | 5.0 Miles | Actual: | $1,576,834 |
District: | Yoakum | Let Date: | NOV 2009 |
Highway: | FM 1681 | Let Status: | Actual |
Project ID: | STP 2009(749)ES | CSJ: | 0215-12-008 |
Description: | WIDEN NARROW ROADWAY & ADD SHOULDERS | Handling Code: |
|
Limits From: | WILSON C/L | Fund Cat: | 1 |
Limits To: | SH 80 | Estimate: | $414,413 |
Length: | 1.2 Miles | Actual: | $382,484 |
Back... |
Totals for 0215-11-020 | ||
---|---|---|---|
Length: | 6.2 Miles | ||
Estimate: | $2,104,971 | ||
Actual: | $1,959,318 | ||
CCSJ: 0915-14-028 | |||
District: | San Antonio | Let Date: | AUG 2010 |
Highway: | CR | Let Status: | Actual |
Project ID: | BR 2010(297) | CSJ: | 0915-14-028 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | CR 212 AT DRAW (WEST CROSSING) | Fund Cat: | 6 |
Limits To: | . | Estimate: | $158,784 |
Length: | 0.1 Miles | Actual: | $147,168 |
District: | San Antonio | Let Date: | AUG 2010 |
Highway: | CR | Let Status: | Actual |
Project ID: | BR 2010(298) | CSJ: | 0915-14-044 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | CR 212 AT DRAW (EAST CROSSING) | Fund Cat: | 6 |
Limits To: | . | Estimate: | $195,661 |
Length: | 0.1 Miles | Actual: | $184,816 |
Bid Tabulations Back... |
Totals for 0915-14-028 | ||
Length: | 0.2 Miles | ||
Estimate: | $354,445 | ||
Actual: | $331,984 |
|
|