Letting Schedule for August, 2010 (FY 2010)
Letting Schedule for August, 2010 (FY 2010) | ||||
Last Update: Tuesday, November 2, 2010 |
August, 2010 (FY 2010) | (see Links) |
SEP 2009 | OCT 2009 | NOV 2009 | DEC 2009 | JAN 2010 | FEB 2010 | MAR 2010 | APR 2010 | MAY 2010 | JUN 2010 | JUL 2010 | AUG 2010 | ||||||
CCSJ | County/ District |
Highway | Let Status | Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0354-05-014 | Andrews/ Odessa |
SH 115 | Actual | $5,099,239 | 8 | CONSTRUCTION OF NEW INTERCHANGE |
0911-38-065 | Angelina/ Lufkin |
VA | Actual | $651,825 | 8 | CONSTRUCT SIDE WALKS AND ADA RAMPS |
1675-01-017 | Angelina/ Lufkin |
FM 1669 | Actual | $833,373 | 11 | REPLACE BRIDGE AND APPROACHES |
2607-01-009 | Aransas/ Corpus Christi |
SH 188 | Actual | $137,732 | 8 | INSTALL LEFT TURN LANE OR TWCTL |
0914-18-074 | Bastrop/ Austin |
CR | Actual | $462,904 | 6 | REPLACE BRIDGE AND APPROACHES |
1149-02-023 | Bastrop/ Austin |
FM 812 | Actual | $3,787,648 | 8 | ADDITIONAL PAVED SURFACE WIDTH |
0814-01-033 | Baylor/ Wichita Falls |
FM 422 | Actual | $264,974 | 6 | REPLACE BRIDGE AND APPROACHES |
1117-01-013 | Bee/ Corpus Christi |
FM 798 | Actual | $2,458,329 | 1 | REHAB ROADWAY AND WIDEN |
0320-02-032 | Bell/ Waco |
SH 95 | Actual | $1,182,113 | 1 | IMPROVE DRAINAGE AND ADD CURB AND GUTTER |
0836-03-054 | Bell/ Waco |
FM 439 | Actual | $414,206 | 1 | INTERSECTION IMPROVEMENT BY INSTALLING TRAFFIC SIGNAL, NIGHT |
0017-10-244 | Bexar/ San Antonio |
IH 35 | Actual | $589,660 | 1 | HIGH MAST ILLUMINATION |
0017-10-250 | Bexar/ San Antonio |
IH 35 | Actual | $2,240,645 | 1 | INSTALL CONCRETE MEDIAN BARRIER & ILLUMINATION |
0072-08-121 | Bexar/ San Antonio |
IH 10 | Actual | $673,765 | 6 | REHAB BRIDGE & APPROACHES |
0915-12-224 | Bexar/ San Antonio |
MH | Actual | $26,448,884 | 2 | CONSTRUCT 4 LANE DIVIDED ROADWAY ON NEW LOCATION |
0915-12-440 | Bexar/ San Antonio |
CS | Actual | $4,185,032 | 7 | RECONSTRUCT EXIST ROADWAY, ADD SIDEWALKS, BIKE LANES AND |
0915-12-473 | Bexar/ San Antonio |
VA | Actual | $267,000 | 7 | ALAMO AREA COMMUTE SOLUTION PGM - FY 2010 |
8000-15-012 | Bexar/ San Antonio |
PS | Actual | $24,018,439 | 2 | CONSTRUCT 4 LANE DIVIDED ROADWAY_ON NEW LOCATION |
0398-01-038 | Bosque/ Waco |
FM 56 | Actual | $2,036,618 | 1 | REHABILITATE AND WIDEN PAVEMENT TO ADD SHOULDERS, UPGRADE |
0398-05-011 | Bosque/ Waco |
FM 56 | Actual | $4,277,617 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
0724-03-011 | Bosque/ Waco |
FM 2602 | Actual | $935,027 | 6 | REPLACE BRIDGE AND APPROACHES |
2869-01-007 | Bosque/ Waco |
FM 2841 | Actual | $205,541 | 1 | REPLACE CULVERT |
0061-01-022 | Bowie/ Atlanta |
SH 8 | Actual | $2,041,219 | 1 | RESURFACE EXISTING 2 - LANE HIGHWAY WITH ASPHALTIC CONCRETE |
0610-06-076 | Bowie/ Atlanta |
IH 30 | Actual | $15,994,500 | 12 | CONSTRUCT INTERCHANGE AT WEST HOOKS COUNTY ROAD & CONSTRUCT |
0945-01-037 | Bowie/ Atlanta |
FM 1397 | Actual | $118,433 | 11 | UPGRADE EXISTING TRAFFIC SIGNALS |
0598-02-050 | Brazoria/ Houston |
SH 288 | Actual | $5,828,815 | 1 | SEAL COAT & ACP OVERLAY |
0598-03-024 | Brazoria/ Houston |
SH 288 | Actual | $287,234 | 11 | INSTALL BOX CULVERT |
0912-31-130 | Brazoria/ Houston |
CS | Actual | $389,891 | 6 | REPLACE BRIDGE AND APPROACHES |
0912-31-165 | Brazoria/ Houston |
CR | Actual | $974,312 | 6 | REPLACE BRIDGE |
0912-31-169 | Brazoria/ Houston |
CR | Actual | $1,076,463 | 6 | REPLACE BRIDGE (NBI# 12020AA0652002) |
0912-31-193 | Brazoria/ Houston |
PW | Actual | $252,700 | 10 | PAVE LEVEES AROUND 36 ONE - ACRE PONDS |
0912-31-235 | Brazoria/ Houston |
VA | Actual | $208,478 | 1 | STRUCTURAL REPAIR |
0049-12-079 | Brazos/ Bryan |
SH 6 | Actual | $5,113,465 | 1 | OVERLAY CONSISTING OF MILLING, SURFACE TREATMENT, HMA |
1560-01-031 | Brazos/ Bryan |
FM 1687 | Actual | $749,588 | 1 | UPGRDING NON - FREEWAY FACILITY CONSISTING OF SCARIFYING |
0541-01-026 | Briscoe/ Childress |
SH 256 | Actual | $1,460,038 | 1 | ACP, UTBWC AND STRUCTURES |
0923-06-059 | Brown/ Brownwood |
PW | Actual | $365,761 | 10 | CONST 0.7 MI ROAD ACCESS TO CHECK STATION & SUPPORT FAC. AND |
0252-01-069 | Burnet/ Austin |
US 281 | Actual | $4,671,558 | 1 | REHAB RDWY |
0152-03-054 | Caldwell/ Austin |
US 183 | Actual | $256,546 | 1 | CENTERLINE RUMBLE STRIPS |
0914-22-050 | Caldwell/ Austin |
CR | Actual | $261,621 | 6 | REPLACE BRIDGE AND APPROACHES |
0220-03-029 | Cameron/ Pharr |
US 281 | Actual | $371,691 | 8 | RUMBLE STRIPS |
0921-06-186 | Cameron/ Pharr |
CS | Actual | $5,494,083 | 3 | EXTEND & CONSTRUCT TO 4 LANES |
2717-01-022 | Cameron/ Pharr |
FM 3248 | Actual | $6,815,298 | 1 | IMPROVE TRAFFIC SIGNAL AND SAFETY LIGHTING AT INTERSECTION |
0508-03-091 | Chambers/ Beaumont |
IH 10 | Actual | $2,502,871 | 1 | CONSTRUCT A TRUCK WEIGH STATION |
0047-05-043 | Collin/ Dallas |
SH 5 | Actual | $6,209,528 | 1 | REPLACE BRIDGE AND APPROACHES |
0918-24-163 | Collin/ Dallas |
VA | Actual | $196,000 | 7 | CITYWIDE SIGNAL DATA COLLECTION FOR SIGNAL RETIMING |
1012-02-023 | Collin/ Dallas |
FM 545 | Actual | $1,874,000 | 1 | REPLACE BRIDGE |
1013-01-025 | Collin/ Dallas |
FM 546 | Actual | $3,276,548 | 1 | RECONSTRUCT EXISTING 6 LANE UNDIVIDED URBAN TO 4 LANE |
0857-01-027 | Comal/ San Antonio |
FM 306 | Actual | $1,199,052 | 1 | REHAB AND WIDEN RDWY TO PROVIDE TURN LANES |
0915-17-019 | Comal/ San Antonio |
CR | Actual | $534,942 | 6 | REPLACING BRIDGE AND APPROACHES |
3106-01-010 | Comal/ San Antonio |
FM 306 | Actual | $4,111,989 | 1 | WIDEN NARROW ROADWAY TO ADD SHOULDERS AND PASSING LANES |
1357-01-021 | Cooke/ Wichita Falls |
FM 678 | Actual | $3,585,763 | 8 | CONSTRUCT GRADE SEPARATION |
0867-02-013 | Coryell/ Waco |
FM 932 | Actual | $1,410,931 | 1 | REPLACE BRIDGE AND APPROACHES |
0909-39-121 | Coryell/ Waco |
CR | Actual | $489,397 | 6 | REPLACE BRIDGE AND APPROACHES |
0925-14-006 | Cottle/ Childress |
PW | Actual | $260,477 | 10 | BASE AND STRUCTURES |
0141-01-045 | Crockett/ San Angelo |
IH 10 | Actual | $2,104,661 | 1 | OVERLAY |
1817-02-008 | Crockett/ Odessa |
FM 1901 | Actual | $760,287 | 6 | REPLACE BRIDGE |
0002-11-056 | Culberson/ El Paso |
IH 10 | Actual | $1,094,962 | 1 | MILL AND INLAY |
0066-01-017 | Dallam/ Amarillo |
US 287 | Actual | $7,331,416 | 1 | SUPER 2 - REHAB RDWY / ADD PASS LANES |
0009-11-220 | Dallas/ Dallas |
IH 30 | Actual | $2,559,068 | 10 | CONSTRUCT PERMANENT CONTRAFLOW HOV LANES |
0092-02-116 | Dallas/ Dallas |
IH 45 | Actual | $3,832,239 | 10 | UPGRADE INTERCHANGE FOR EXPANDED MULTIMODAL TRAFFIC |
0094-03-105 | Dallas/ Dallas |
SH 183 | Actual | $7,111,157 | 10 | CONSTRUCT EASTBOUND FRONTAGE ROAD |
0261-03-053 | Dallas/ Dallas |
US 67 | Actual | $3,685,288 | 1 | CONSTRUCT NB AUXILIARY LANE, WIDEN NBML BRIDGE, CHANNEL WORK |
0918-00-159 | Dallas/ Dallas |
VA | Actual | $1,986,666 | 7 | TRAVEL SURVEY AND DATA COLLECTION EFFORT FOR PROJECTS IN MPO |
0918-00-167 | Dallas/ Dallas |
VA | Actual | $3,369,962 | 7 | PROVIDE ASSISTANCE TO STRANDED MOTORISTS OR NON INJURY |
0918-45-760 | Dallas/ Dallas |
CS | Actual | $681,031 | 6 | REPLACE BRIDGE AND APPROACHES |
0918-45-857 | Dallas/ Dallas |
VA | Actual | $714,000 | 7 | UPGRADE TRINITY RAILWAY EXPRESS (TRE) CROSSINGS; INSTALL |
0918-45-881 | Dallas/ Dallas |
VA | Actual | $609,208 | 1 | REFURBISH BRIDGE PROTECTION ASSEMBLY SIGNS |
0918-45-894 | Dallas/ Dallas |
VA | Actual | $19,276,725 | 5 | TRINITY RAILWAY EXPRESS DOUBLE TRACK AND GRADE SEPARATIONS; |
1068-04-140 | Dallas/ Dallas |
IH 30 | Actual | $138,137 | 5 | INSTALLATION OF 2 DYNAMIC MESSAGE SIGNS |
2374-02-132 | Dallas/ Dallas |
IH 635 | Actual | $60,998 | 5 | UPGRADE EXISTING ISDN TO A WIRELESS ITS SYSTEM |
2964-01-043 | Dallas/ Dallas |
SH 161 | Actual | $1,241,668 | 7 | COG CORRIDOR PEAK PRICING BEFORE AND AFTER SURVEY; ANALYZE |
0918-46-242 | Denton/ Dallas |
CS | Actual | $190,000 | 7 | INSTALL DUAL GATES AND ADD PAVEMENT MARKINGS |
2980-01-011 | Denton/ Dallas |
FM 2934 | Actual | $277,725 | 10 | LANDSCAPE DEVELOPMENT INCLUDING TREES AND SHRUBS |
0154-03-027 | Dewitt/ Yoakum |
US 183 | Actual | $2,887,423 | 1 | REPLACE BRIDGE AND APPROACHES |
0005-13-053 | Ector/ Odessa |
IH 20 | Actual | $6,438,933 | 1 | PAVEMENT OVERLAY |
0002-01-083 | El Paso/ El Paso |
SH 20 | Actual | $2,477,913 | 1 | MILL AND INLAY |
0167-01-104 | El Paso/ El Paso |
US 54 | Actual | $1,770,274 | 1 | OVERLAY |
0167-02-046 | El Paso/ El Paso |
BU 54-A | Actual | $919,682 | 1 | MILL AND INLAY |
0374-02-093 | El Paso/ El Paso |
US 62 | Actual | $3,196,379 | 1 | 2" MILL AND INLAY |
0924-06-310 | El Paso/ El Paso |
VA | Actual | $1,562,223 | 7 | TRAFFIC SIGNAL UPGRADES AT 9 INTERSECTIONS TO CURRENT |
0924-06-365 | El Paso/ El Paso |
CS | Actual | $300,000 | 5 | BUS ACQUISITION_#12 |
2121-02-123 | El Paso/ El Paso |
IH 10 | Actual | $7,727,685 | 10 | CONSTRUCT INTERCHANGE IMPROVEMENTS |
2121-02-133 | El Paso/ El Paso |
IH 10 | Actual | $1,063,173 | 1 | MILL AND INLAY |
2121-07-013 | El Paso/ El Paso |
US 85 | Actual | $1,113,636 | 1 | MILL AND INLAY ASP PAVEMENT; REPAIR PAVEMENT, BRIDGE JOINTS, |
2552-04-035 | El Paso/ El Paso |
LP 375 | Actual | $12,125,093 | 9 | LP 375 ENHANCEMENT PROJECT, BRIDGE CANOPIES_PHASE 3 |
1159-02-033 | Ellis/ Dallas |
FM 879 | Actual | $129,809 | 1 | INSTALL CENTERLINE RUMBLE STRIPS |
0250-03-042 | Erath/ Fort Worth |
US 281 | Actual | $220,071 | 8 | CONSTRUCT CENTERLINE RUMBLE STRIPES / INSTALL PAVEMENT STRIPES |
0902-49-062 | Erath/ Fort Worth |
CR | Actual | $237,679 | 6 | REPLACE BRIDGE AND APPROACHES |
1990-01-015 | Erath/ Fort Worth |
FM 205 | Actual | $1,132,996 | 8 | PROVIDE ADDITIONAL PAVED SURFACE BY WIDENING TRAVEL LANE BY |
0908-23-021 | Fisher/ Abilene |
CR | Actual | $548,436 | 6 | REPLACE BRIDGE AND APPROACHES |
0027-08-167 | Fort Bend/ Houston |
US 90A | Actual | $204,937 | 11 | CONTINUOUS SAFETY LIGHTING |
0912-34-120 | Fort Bend/ Houston |
CS | Actual | $94,732 | 5 | INSTALL TRAFFIC SIGNALS AT INTERSECTION |
0912-34-164 | Fort Bend/ Houston |
CS | Actual | $596,183 | 7 | REHABILITATE ROAD |
0051-04-060 | Galveston/ Houston |
SH 87 | Actual | $2,959,684 | 1 | BASE REPAIR AND OVERLAY |
0367-02-076 | Galveston/ Houston |
SH 87 | Actual | $6,850,974 | 1 | RAISE ROAD AND ASPHALT CONCRETE PAVEMENT OVERLAY |
0912-73-121 | Galveston/ Houston |
CS | Actual | $371,894 | 6 | REPLACE BRIDGE |
0912-73-137 | Galveston/ Houston |
VA | Actual | $633,856 | 5 | UPGRADE TRAFFIC SIGNALS & SYNCHRONIZATION (GALVESTON COUNTY) |
0912-73-170 | Galveston/ Houston |
CS | Actual | $385,396 | 10 | RESURFACE ROAD |
0912-73-177 | Galveston/ Houston |
VA | Actual | $88,486 | 10 | REMOVE DEBRIS FROM ROADWAY AFTER HURRICANE IKE |
3595-01-013 | Galveston/ Houston |
SH 275 | Actual | $639,288 | 1 | BASE REPAIRS, MILLING & 1.5" ASPHALT OVERLAY |
3595-01-014 | Galveston/ Houston |
SH 275 | Actual | $154,362 | 10 | 2004 ITS DEPLOYMENT PROGRAM (ITS EQUIPMENT AND ROUTE |
0153-02-037 | Gonzales/ Yoakum |
US 183 | Actual | $415,933 | 8 | CONSTRUCT CENTERLINE RUMBLE STRIPS |
0913-22-031 | Gonzales/ Yoakum |
CR | Actual | $228,128 | 6 | REPLACE BRIDGE AND APPROACHES |
0045-19-044 | Grayson/ Paris |
US 82 | Actual | $3,606,776 | 8 | GRADE SEPARATION |
0047-03-071 | Grayson/ Paris |
US 75 | Actual | $2,144,890 | 1 | REHABILITATE PAVEMENT |
0047-18-065 | Grayson/ Paris |
US 75 | Actual | $1,385,000 | 11 | REVERSE EXISTING RAMP CONFIGURATION |
0316-02-023 | Grayson/ Paris |
FM 84 | Actual | $193,680 | 8 | INSTALL LEFT TURN LANE |
0436-01-008 | Guadalupe/ San Antonio |
FM 464 | Actual | $1,059,110 | 1 | REHAB EXISTING RAODWAY AND ADD SHOULDERS |
1543-01-006 | Guadalupe/ San Antonio |
FM 1620 | Actual | $963,159 | 1 | REHAB AND WIDEN NARROW ROADWAY |
1096-01-055 | Hardin/ Beaumont |
FM 770 | Actual | $1,832,808 | 1 | RESTORE EXISTING ROADWAY |
0027-10-064 | Harris/ Houston |
US 90A | Actual | $3,356,584 | 6 | REPLACE BRIDGE (NBI# 12102002710064 SB) |
0271-07-292 | Harris/ Houston |
IH 10 | Actual | $3,594,471 | 7 | CONSTRUCT DRAINAGE AND DETENTION FACILITIES |
0271-07-294 | Harris/ Houston |
IH 10 | Actual | $346,000 | 10 | LANDSCAPE DEVELOPMENT |
0271-17-155 | Harris/ Houston |
IH 610 | Actual | $354,224 | 1 | PAVEMENT MARKINGS |
0508-01-323 | Harris/ Houston |
IH 10 | Actual | $855,313 | 10 | LANDSCAPE DEVELOPMENT |
0508-01-324 | Harris/ Houston |
IH 10 | Actual | $650,522 | 10 | LANDSCAPE DEVELOPMENT |
0912-00-362 | Harris/ Houston |
VA | Actual | $10,000,000 | 5 | CLEAN CITIES / CLEAN VEHICLES PROGRAM (FY 2011) |
0912-00-365 | Harris/ Houston |
VA | Actual | $1,890,000 | 5 | HGAC STAFF MARKETING, PUBLIC OUTREACH AND CONSULTANT TECHNIC |
0912-00-367 | Harris/ Houston |
VA | Actual | $5,000,000 | 5 | COMMUTE SOLUTIONS PROGRAM (FY 2010) |
0912-00-372 | Harris/ Houston |
VA | Actual | $4,000,000 | 5 | REGIONAL VANPOOL PROGRAM (FY 2010) CMAQ |
0912-00-374 | Harris/ Houston |
VA | Actual | $1,181,648 | 5 | SIGNAL IMPROVEMENTS AT INTERSECTIONS |
0912-00-395 | Harris/ Houston |
VA | Actual | $5,250,000 | 7 | ACCESS MANAGEMENT STUDIES ALONG SIGNIFICANT CORRIDORS IN THE |
0912-00-449 | Harris/ Houston |
VA | Actual | $469,298 | 5 | VOLUNTARY MOBILE EMISSIONS REDUCTION ACTIVITIES (ADDING |
0912-00-450 | Harris/ Houston |
VA | Actual | $768,500 | 5 | CLEAN AIR ACTION PROGRAM FY 2009, FY 2010, FY 2011 (ADDING |
0912-70-002 | Harris/ Houston |
CS | Actual | $1,509,343 | 6 | REPLACE BRIDGE |
0912-70-020 | Harris/ Houston |
CS | Actual | $2,900,406 | 7 | REHAB AND OVERLAY |
0912-70-036 | Harris/ Houston |
CS | Actual | $928,362 | 7 | MILL AND ACP OVERLAY |
0912-70-040 | Harris/ Houston |
CS | Actual | $308,982 | 7 | ASPHALT OVERLAY |
0912-70-041 | Harris/ Houston |
CS | Actual | $712,114 | 7 | ASPHALT OVERLAY |
0912-70-045 | Harris/ Houston |
PW | Actual | $305,460 | 10 | CONSTRUCT PARKING LOT AND DRIVEWAY |
0912-70-070 | Harris/ Houston |
VA | Actual | $2,147,808 | 5 | PURCHASE EQUIPMENT FOR SYSTEM INTEGRATION AND ACCOMPLISH |
0912-70-071 | Harris/ Houston |
VA | Actual | $1,665,294 | 5 | PURCHASE EQUIPMENT FOR SYSTEM INTEGRATION AND ACCOMPLISH |
0912-70-072 | Harris/ Houston |
VA | Actual | $2,049,020 | 5 | PURCHASE EQUIPMENT FOR SYSTEM INTEGRATION AND ACCOMPLISH |
0912-71-076 | Harris/ Houston |
CS | Actual | $1,160,230 | ROW | REPLACE BRIDGE AND APPROACHES |
0912-71-406 | Harris/ Houston |
CS | Actual | $409,320 | 6 | REPLACE BRIDGE |
0912-71-793 | Harris/ Houston |
CS | Actual | $1,165,917 | 9 | VINCE BAYOU PEDESTRIAN AND BICYCLE TRAIL IN PASADENA |
0912-72-001 | Harris/ Houston |
CS | Actual | $951,006 | 6 | REPLACE BRIDGE AND APPROACHES |
0912-72-084 | Harris/ Houston |
VA | Actual | $1,924,707 | 5 | HARRIS COUNTY SIGNAL INTERCONNECT PHASE 2 |
0912-72-089 | Harris/ Houston |
VA | Actual | $4,497,941 | 5 | HARRIS COUNTY SIGNAL INTERCONNECT PHASE 2 |
0912-72-194 | Harris/ Houston |
VA | Actual | $2,315,250 | 5 | INSTALL TRAFFIC MANAGEMENT OPERATIONS EQUIPMENT PHASE 2 |
1006-01-061 | Harris/ Houston |
FM 529 | Actual | $411,110 | 1 | 2 DETENTION PONDS |
1685-01-099 | Harris/ Houston |
FM 1960 | Actual | $2,933 | 10 | PROVIDE TEMPORARY POWER SOURCE FOR TRAFFIC SIGNALS AFTER |
3510-05-011 | Harris/ Houston |
SH 99 | Actual | $315,482 | 1 | NOISE WALL CONTRACT 1 |
0016-02-122 | Hays/ Austin |
IH 35 | Actual | $866,875 | 11 | IH 35 RIVER RIDGE ENTRANCE & EXIT RAMP PROJECT WILL CONST |
0471-02-062 | Hays/ Austin |
SH 21 | Actual | $671,309 | 7 | ADD LEFT TURN LANE & SHOULDERS |
0914-33-054 | Hays/ Austin |
CS | Actual | $367,417 | 7 | CONST BIKE / PED TRAIL |
1429-01-025 | Hidalgo/ Pharr |
FM 2557 | Actual | $5,495,563 | 1 | REHABILITATE PAVEMENT AND ADD SHOULDERS |
1190-01-040 | Hill/ Waco |
FM 933 | Actual | $4,037,030 | 1 | SAFETY TREAT FIXED OBJECTS, WIDEN LANES, CONSTRUCT PAVED |
1513-01-015 | Hood/ Fort Worth |
FM 167 | Actual | $51,261 | 1 | EXTEND MULTIPLE BOX CULVERT UPSTREAM TO ACCOMMODATE TURNING |
0083-04-023 | Hopkins/ Paris |
SH 11 | Actual | $4,638,238 | 1 | REHAB EXISTING ROAD |
0735-04-016 | Hopkins/ Paris |
FM 2285 | Actual | $3,286,604 | 1 | REHABILITATION OF EXISTING ROADWAY |
0635-03-021 | Houston/ Lufkin |
FM 228 | Actual | $278,552 | 8 | SAFETY TREAT FIXED OBJECTS |
1017-03-029 | Hunt/ Paris |
SH 276 | Actual | $3,428,604 | 1 | 2 1 / 2" TYPE D OVERLAY WITH 1" LEVEL - UP |
2799-01-005 | Hunt/ Paris |
FM 2737 | Actual | $1,625,649 | 1 | REHAB EXISTING ROADWAY |
2367-01-049 | Jefferson/ Beaumont |
SH 82 | Actual | $9,987,560 | 6 | CLEAN AND PAINT STEEL BRIDGE |
0172-03-017 | Johnson/ Fort Worth |
BU 287P | Actual | $7,112 | 10 | INSTALLATION OF SCHOOL ZONE FLASHERS |
0365-03-042 | Johnson/ Fort Worth |
SH 171 | Actual | $71,548 | 1 | INSTALLATION OF A FULL TRAFFIC ACTUATED TRAFFIC SIGNAL |
0365-03-044 | Johnson/ Fort Worth |
SH 171 | Actual | $3,399,210 | 1 | CEMENT TREAT BASE; ADD 4" NEW BASE AND 2" HMAC OVERLAY |
0519-01-027 | Johnson/ Fort Worth |
SH 174 | Actual | $2,084,452 | 1 | CEMENT STABILIZE BASE AND HMAC OVERLAY |
0366-06-037 | Karnes/ Corpus Christi |
SH 123 | Actual | $289,815 | 8 | INSTALL LEFT TURN LANE OR TWCTL |
0751-01-034 | Kaufman/ Dallas |
FM 148 | Actual | $9,184,740 | 6 | REPLACE BRIDGE AND APPROACHES |
3212-03-017 | Kendall/ San Antonio |
FM 3351 | Actual | $1,238,085 | 8 | SAFETY TREAT FIXED OBJECTS |
1135-02-019 | Kerr/ San Antonio |
RM 783 | Actual | $1,492,945 | 1 | STORM SEWER |
1446-02-017 | Kleberg/ Corpus Christi |
FM 1356 | Actual | $273,180 | 8 | INSTALL LEFT TURN LANE OR TWCTL |
0922-20-012 | La Salle/ Laredo |
CS | Actual | $355,243 | 10 | REHABILITATION OF AN EXISTING ROADWAY |
0045-09-093 | Lamar/ Paris |
US 82 | Actual | $937,024 | 8 | INSTALL CONTINUOUS 2 WAY LEFT TURN LANE |
0563-03-011 | Lamb/ Lubbock |
FM 54 | Actual | $1,528,665 | 8 | HAZARD ELIMINATION SAFETY |
1291-02-012 | Lamb/ Lubbock |
FM 1055 | Actual | $1,350,742 | 1 | REHABILITATION OF EXISTING ROAD |
0251-06-026 | Lampasas/ Brownwood |
US 183 | Actual | $6,626,140 | 1 | REHABILITATION, CURB, SIDEWALK, DRAINAGE IMPROVEMENTS, |
0028-04-071 | Liberty/ Beaumont |
US 90 | Actual | $495,450 | 8 | CENTERLINE TEXTURING |
0920-02-085 | Liberty/ Beaumont |
CS | Actual | $59,944 | 7 | OVERLAY EXISTING ROADWAY |
0355-01-045 | Lipscomb/ Amarillo |
SH 15 | Actual | $2,460,186 | 11 | REHAB AND 2 COURSE SURFACE TREATMENT |
1550-01-011 | Live Oak/ Corpus Christi |
FM 534 | Actual | $1,166,011 | 8 | WIDEN ROADWAY |
1553-01-012 | Live Oak/ Corpus Christi |
FM 1042 | Actual | $670,407 | 8 | WIDEN ROADWAY |
1553-02-007 | Live Oak/ Corpus Christi |
FM 1545 | Actual | $396,138 | 8 | WIDEN ROADWAY |
3245-01-006 | Live Oak/ Corpus Christi |
FM 3162 | Actual | $3,145,702 | 1 | REAHB ROADWAY AND WIDEN |
0150-04-042 | Llano/ Austin |
SH 29 | Actual | $661,749 | 8 | CENTERLINE RUMBLE STRIPS |
1344-02-021 | Lubbock/ Lubbock |
FM 1730 | Actual | $1,325,000 | 1 | REHABILITATION OF EXISTING ROADWAY |
2184-01-008 | Lynn/ Lubbock |
FM 179 | Actual | $1,096,474 | 1 | REHABILITATION OF EXISTING ROAD |
2697-01-032 | Matagorda/ Yoakum |
FM 2668 | Actual | $459,500 | 8 | SAFFETY TREAT FIXED OBJECTS |
0055-07-058 | McLennan/ Waco |
US 84 | Actual | $387,089 | 8 | ADD CENTERLINE RUMBLE STRIP |
0909-22-154 | McLennan/ Waco |
CS | Actual | $226,884 | 8 | CONSTRUCT ALTERNATE TRANSPORTATION ROUTE CONSISTING OF |
0054-09-032 | Mills/ Brownwood |
US 84 | Actual | $199,822 | 8 | CONSTRUCT A LEFT TURN LANE |
0908-21-021 | Mitchell/ Abilene |
VA | Actual | $134,708 | 11 | ADA IMPROVEMENTS |
0013-05-051 | Montague/ Wichita Falls |
US 81 | Actual | $4,911,504 | 6 | REPLACEMENT OF EXISTING RAILROAD UNDERPASS |
0044-06-069 | Montague/ Wichita Falls |
US 82 | Actual | $98,000 | 1 | INSTALL TRAFFIC SIGNAL |
0110-02-023 | Montgomery/ Lufkin |
SH 75 | Actual | $878,374 | 1 | CENTERLINE RUMBLE STRIPS |
0338-04-075 | Montgomery/ Houston |
SH 105 | Actual | $158,055 | 8 | SAFETY TREATMENT, FIX OBJECTS, INSTALL CONTINUOUS LEFT TURN |
0675-08-103 | Montgomery/ Houston |
IH 45 | Actual | $24,972,837 | 7 | WIDEN TO 6 MAIN LANES, BRIDGE AND INTERSECTION AT SHEPHARD |
0912-37-184 | Montgomery/ Houston |
CR | Actual | $498,910 | 6 | REPLACE BRIDGE AND APPROACHES |
0912-37-210 | Montgomery/ Houston |
CS | Actual | $562,504 | 7 | FULL DEPTH REHABILITATION |
0912-37-211 | Montgomery/ Houston |
CS | Actual | $494,830 | 7 | FULL DEPTH REHABILITATION |
0162-04-047 | Navarro/ Dallas |
SH 31 | Actual | $9,138,953 | 1 | UPGRADE DRAINAGE, REPAIR PAVEMENT AND MEET ADA STANDARDS |
0995-01-023 | Navarro/ Dallas |
FM 637 | Actual | $776,254 | 8 | MODERNIZE BRIDGE RAIL & APPROACH GUARDRAIL; SAFETY TREAT |
0304-05-032 | Newton/ Beaumont |
SH 87 | Actual | $160,440 | 8 | SAFETY TREAT FIXED OBJECTS |
0006-02-104 | Nolan/ Abilene |
IH 20 | Actual | $1,038,393 | 1 | REPAIR BASE FAILURES AND MICROSURFACING FOR IMPROVED SKID |
0006-02-106 | Nolan/ Abilene |
IH 20 | Actual | $589,050 | 8 | INSTALL MEDIAN BARRIER |
0101-06-104 | Nueces/ Corpus Christi |
US 181 | Actual | $4,291,131 | 6 | REHABILITATION OF EXISTING BRIDGE STRUCTURE |
0102-02-094 | Nueces/ Corpus Christi |
US 77 | Actual | $103,217 | 11 | SIGN REPLACEMENT |
0373-01-096 | Nueces/ Corpus Christi |
BU 77-U | Actual | $1,456,661 | 8 | CONSTRUCT LEFT TURN LANE AND ADD SHLDRS |
1052-01-063 | Nueces/ Corpus Christi |
FM 666 | Actual | $963,877 | 6 | BRIDGE REPLACEMENT |
1052-01-072 | Nueces/ Corpus Christi |
FM 666 | Actual | $2,398,623 | 1 | REHAB. ROADWAY, WIDEN AND ADD SHLDRS. |
1052-02-077 | Nueces/ Corpus Christi |
FM 665 | Actual | $1,130,886 | 8 | INSTALL LEFT TURN LANE OR TWCTL |
3176-01-009 | Nueces/ Corpus Christi |
FM 3088 | Actual | $871,428 | 8 | RESURFACING OF ROADWAY |
0028-11-198 | Orange/ Beaumont |
IH 10 | Actual | $355,855 | 10 | INSTALL LANDSCAPING |
2562-01-018 | Orange/ Beaumont |
FM 1442 | Actual | $410,052 | 1 | ADD SIGNAL AND RIGHT TURN LANE |
0007-10-054 | Palo Pinto/ Fort Worth |
US 180 | Actual | $1,517,352 | 1 | OVERLAY |
0902-39-031 | Palo Pinto/ Fort Worth |
PW | Actual | $3,516 | 10 | PURCHASE OF MATERIALS FOR HMAC OVERLAY BY MAINTENANCE FORCES |
0314-01-074 | Parker/ Fort Worth |
IH 20 | Actual | $23,651,493 | 1 | REHABILITATE PAVEMENT WITH 2" HMAC OVERLAY AND 12" |
0388-06-004 | Polk/ Lufkin |
SH 146 | Actual | $1,178,551 | 11 | REHAB EXISTING PAVEMENT |
0924-07-010 | Presidio/ El Paso |
VA | Actual | $1,600,000 | 10 | PRESIDENTIAL PERMIT PREPARATION_PRESIDIO COUNTY |
0534-01-016 | Randall/ Amarillo |
PR 5 | Actual | $722,421 | 10 | EMBANKMENT & DRAINAGE |
0155-05-035 | Refugio/ Corpus Christi |
US 183 | Actual | $68,003 | 8 | INSTALL SAFETY LIGHTING |
0447-05-065 | Refugio/ Corpus Christi |
FM 774 | Actual | $272,202 | 8 | WIDEN ROADWAY |
3075-02-009 | Refugio/ Corpus Christi |
SH 239 | Actual | $2,485,166 | 1 | REHAB ROADWAY |
0049-07-057 | Robertson/ Bryan |
US 79 | Actual | $1,056,111 | 1 | REHABILITATE EXISTING ROAD CONSISTING OF MILLING, SURFACE |
0049-08-061 | Robertson/ Bryan |
US 190 | Actual | $710,768 | 8 | SAFETY WORK CONSISTING OF CENTERLINE RUMBLE STRIPS |
2337-01-020 | Robertson/ Bryan |
FM 1644 | Actual | $530,856 | 10 | MISCELLANEOUS WORK CONSISTING OF CONSTRUCTION OF CONCRETE |
0245-08-045 | Rusk/ Tyler |
US 79 | Actual | $73,310 | 10 | BEAUTIFY SIGNAL ISLANDS W / PLANTINGS & RELAY EXISTING PAVERS |
1940-02-009 | Rusk/ Tyler |
FM 1716 | Actual | $3,500,000 | 10 | RELOCATE ROADWAY FOR STRIP MINING |
0911-29-027 | Sabine/ Lufkin |
CR | Actual | $424,066 | 6 | REPLACE BRIDGE AND APPROACHES |
0180-06-089 | San Patricio/ Corpus Christi |
BS 35-L | Actual | $517,890 | 8 | INSTALL SAFETY LIGHTING |
0507-01-018 | San Patricio/ Corpus Christi |
SH 234 | Actual | $543,843 | 8 | INSTALL LEFT TURN LANE OR TWCTL |
1209-02-016 | San Patricio/ Corpus Christi |
FM 631 | Actual | $552,249 | 8 | WIDEN ROADWAY |
1559-01-023 | San Patricio/ Corpus Christi |
FM 1074 | Actual | $971,976 | 1 | REHAB ROADWAY |
0053-07-036 | Scurry/ Abilene |
US 84 | Actual | $4,340,252 | 1 | PLANING, ACP OVERLAY, GUARD FENCE, AND PAVEMENT MARKINGS |
0053-07-037 | Scurry/ Abilene |
US 84 | Actual | $5,966,872 | 1 | STRUCTURE WIDENING, PLANING, ASPHALT CONCRETE PAVEMENT |
0296-01-032 | Scurry/ Abilene |
US 180 | Actual | $1,918,648 | 1 | MICROSURFACING |
0495-04-063 | Smith/ Tyler |
IH 20 | Actual | $1,237,963 | 11 | REPAIR & RESURFACE WEST BOUND LANES AND SHOULDER |
0927-01-024 | Smith/ Tyler |
FM 344 | Actual | $2,280,270 | 1 | ADD SHOULDERS & RESURFACE ROADWAY |
0008-06-048 | Tarrant/ Fort Worth |
SH 180 | Actual | $1,447,722 | 1 | REPLACE BRIDGE AND APPROACHES |
0014-15-040 | Tarrant/ Fort Worth |
US 287 | Actual | $3,658,595 | 1 | FULL DEPTH PAVEMENT REPAIR AT VARIOUS LOCATIONS AND 2" HMAC |
0747-04-060 | Tarrant/ Fort Worth |
FM 157 | Actual | $126,223 | 1 | CONSTRUCT RADII WIDENING, SIDEWALK RAMPS, SIGNING, PAVEMENT |
0902-48-497 | Tarrant/ Fort Worth |
CS | Actual | $546,147 | 6 | REPLACE BRIDGE |
0902-48-698 | Tarrant/ Fort Worth |
VA | Actual | $2,403,180 | 7 | PEDESTRIAN TRAIL CONNECTION OF BRIDGE ACROSS TRINITY RIVER |
0902-48-723 | Tarrant/ Fort Worth |
CR | Actual | $674,569 | 6 | REPLACE BRIDGE AND APPROACHES |
0902-48-725 | Tarrant/ Fort Worth |
CS | Actual | $740,111 | 8 | 2007 SRTS INFRASTRUCTURE PROJECT; SIDEWALKS, PEDESTRIAN |
0902-48-761 | Tarrant/ Fort Worth |
VA | Actual | $2,375,000 | 5 | DEVELOP AND IMPLEMENT TRAFFIC SIGNAL COORDINATION IN 9 |
0902-48-762 | Tarrant/ Fort Worth |
VA | Actual | $1,333,334 | 7 | STREAMLINED PROJECT DELIVERY / PASSENGER RAIL & RDWY PLANNING; |
0902-48-763 | Tarrant/ Fort Worth |
VA | Actual | $750,000 | 7 | DEVELOP & IMPLEMENT REG. PROJECT TRACK, MONITOR & ASSESSMENT |
0902-48-764 | Tarrant/ Fort Worth |
VA | Actual | $1,100,000 | 7 | PLANNING / OVERSIGHT / ADMINSTRATION OF ITS, MOBILITY ASSISTANCE |
0902-48-785 | Tarrant/ Fort Worth |
VA | Actual | $1,358,549 | 7 | VANPOOL PROGRAM OPERATION FOR FY 2008 |
0902-48-786 | Tarrant/ Fort Worth |
VA | Actual | $1,358,549 | 7 | VANPOOL PROGRAM FY 2009 |
0033-06-101 | Taylor/ Abilene |
US 83 | Actual | $1,056,812 | 1 | REHABILITATION |
0034-01-122 | Taylor/ Abilene |
US 83 | Actual | $252,956 | 1 | DRAINAGE IMPROVEMENTS |
0248-09-003 | Titus/ Atlanta |
US 271 | Actual | $778,145 | 12 | PREPARING ROW |
0919-30-051 | Titus/ Atlanta |
CR | Actual | $521,575 | 6 | REPLACE BRIDGE AND APPROACHES_ON CR 3120 AT HORSE CREEK |
0555-05-023 | Tom Green/ San Angelo |
RM 853 | Actual | $245,164 | 11 | MICROSURFACING |
2574-01-043 | Tom Green/ San Angelo |
RM 584 | Actual | $1,036,944 | 1 | ACP OVERLAY |
0113-13-148 | Travis/ Austin |
SH 71 | Actual | $519,515 | 10 | TREE / SHRUB PLANTING AND IRRIGATION |
0440-06-009 | Travis/ Austin |
SH 130 | Actual | $1,469,668 | 1 | ADD NB EXIT RAMP & SB ENTRANCE RAMP |
0440-06-012 | Travis/ Austin |
SH 130 | Actual | $2,296,000 | 1 | TOLL INTEGRATION |
0914-00-295 | Travis/ Austin |
VA | Actual | $140,874 | 1 | FY 2010 SIGNING |
0914-00-307 | Travis/ Austin |
VA | Actual | $623,579 | 1 | FURNISH & INSTALL DYNAMIC MESSAGE SIGN |
0914-00-325 | Travis/ Austin |
VA | Actual | $1,433,000 | 7 | INSTL UNINTERUPTED PWR SUPPLY AT 300 INTERSECTIONS |
0914-04-253 | Travis/ Austin |
VA | Actual | $354,550 | 8 | SIDEWALKS & CROSSWALK |
1200-03-050 | Travis/ Austin |
FM 973 | Actual | $312,197 | 8 | CENTERLINE RUMBLE STRIPS |
1237-01-029 | Tyler/ Beaumont |
FM 1013 | Actual | $632,993 | 8 | SAFETY TREAT FIXED OBJECTS |
0505-01-043 | Van Zandt/ Tyler |
SH 110 | Actual | $778,510 | 1 | CONSTRUCT TURN LANE AT NEW SCHOOL SPORTS COMPLEX |
2350-01-047 | Victoria/ Yoakum |
US 77 | Actual | $1,415,661 | 1 | PAVEMENT REPAIR AND ACP SURFACING |
0004-04-076 | Ward/ Odessa |
IH 20 | Actual | $14,473,729 | 9 | CONSTRUCTION OF TOURIST AND VISITOR CENTER |
0542-01-074 | Webb/ Laredo |
US 59 | Actual | $1,476,418 | 1 | RESURFACE OF EXISTING HIGHWAY |
0922-00-058 | Webb/ Laredo |
VA | Actual | $981,827 | 11 | UPGRADE BRIDGE RAIL AND MBGF |
1235-02-018 | Wheeler/ Childress |
FM 1046 | Actual | $5,270,932 | 1 | REHABILITATION OF EXISTING ROADWAY |
0044-01-093 | Wichita/ Wichita Falls |
US 82 | Actual | $459,075 | 8 | INSTALL MEDIAN BARRIER |
0043-06-080 | Wilbarger/ Wichita Falls |
US 287 | Actual | $1,524,919 | 1 | PLANNING, HOT MIX, AND PERMEABLE FRICTION COURSE |
0043-20-017 | Wilbarger/ Wichita Falls |
BU 287F | Actual | $734,479 | 1 | DIAMOND GRINDING OF CONCRETE PAVEMENT, SEAL COAT, 2" HMAC |
0124-03-052 | Wilbarger/ Wichita Falls |
US 283 | Actual | $7,586,089 | 6 | WIDEN PAVEMENT AND STRUCTURES |
0015-16-019 | Williamson/ Austin |
BI 35-L | Actual | $1,990,487 | 1 | MILL, SEAL & THIN OVERLAY |
0204-02-027 | Williamson/ Austin |
US 79 | Actual | $11,500,548 | 12 | UPGRADE TO 4 - LANE DIVIDED ROADWAY |
0914-05-141 | Williamson/ Austin |
CR | Actual | $2,247,003 | 6 | REPLACE BRIDGE AND APPROACHES |
0914-05-147 | Williamson/ Austin |
CS | Actual | $7,556,013 | 7 | WIDEN TO MAD 4 W / CONTINUOUS TURN LANE |
0915-14-028 | Wilson/ San Antonio |
CR | Actual | $331,984 | 6 | REPLACE BRIDGE AND APPROACHES |
0902-20-091 | Wise/ Fort Worth |
CR | Actual | $810,773 | 6 | REPLACE BRIDGE AND APPROACHES |
0134-02-054 | Young/ Wichita Falls |
US 380 | Actual | $195,327 | 1 | CENTERLINE RUMBLE STRIPS |
|
|