Detail Letting Schedule for Bowie County (FY 2011)
Detail Letting Schedule for Bowie County (FY 2011) | ||||
Last Update: Tuesday, September 6, 2011 |
Bowie County (FY 2011) |
CCSJ: 0010-13-085 | |||
District: | Atlanta | Let Date: | MAY 2011 |
Highway: | US 67 | Let Status: | Actual |
Project ID: | STP 2011(945)SB | CSJ: | 0010-13-085 |
Description: | INSTALL LEFT TURN LANE | Handling Code: |
|
Limits From: | AT INTERSECTION OF FM 2148 | Fund Cat: | 8 |
Limits To: | . | Estimate: | $241,332 |
Length: | 0.4 Miles | Actual: | $255,644 |
District: | Atlanta | Let Date: | MAY 2011 |
Highway: | US 82 | Let Status: | Actual |
Project ID: | STP 2011(945)SB | CSJ: | 0046-03-037 |
Description: | INSTALL LEFT TURN LANE | Handling Code: |
|
Limits From: | AT INTERSECTION OF CR 3215 | Fund Cat: | 8 |
Limits To: | . | Estimate: | $91,174 |
Length: | 0.3 Miles | Actual: | $120,333 |
Back... |
Totals for 0010-13-085 | ||
---|---|---|---|
Length: | 0.7 Miles | ||
Estimate: | $332,506 | ||
Actual: | $375,977 | ||
CCSJ: 0085-04-039 | |||
District: | Atlanta | Let Date: | MAY 2011 |
Highway: | US 259 | Let Status: | Actual |
Project ID: | STP 2011(947)HES | CSJ: | 0084-01-021 |
Description: | TTEXTURIZE SHOULDERS & CENTERLINE TEXTURING | Handling Code: |
|
Limits From: | US 67 | Fund Cat: | 8 |
Limits To: | SH 49 | Estimate: | $84,684 |
Length: | 10.2 Miles | Actual: | $58,606 |
District: | Atlanta | Let Date: | MAY 2011 |
Highway: | US 259 | Let Status: | Actual |
Project ID: | STP 2011(947)HES | CSJ: | 0085-01-042 |
Description: | TEXTURIZE SHOULDERS & CENTERLINE TEXTURING | Handling Code: |
|
Limits From: | BOWIE COUNTY LINE | Fund Cat: | 8 |
Limits To: | US 67 | Estimate: | $310,618 |
Length: | 9.0 Miles | Actual: | $275,153 |
District: | Atlanta | Let Date: | MAY 2011 |
Highway: | US 259 | Let Status: | Actual |
Project ID: | STP 2011(947)HES | CSJ: | 0085-02-047 |
Description: | TEXTURIZE SHOULDERS & CENTERLINE TEXTURING | Handling Code: |
|
Limits From: | 0.3 MI. SOUTH OF FM 44 | Fund Cat: | 8 |
Limits To: | MORRIS COUNTY LINE | Estimate: | $546,912 |
Length: | 12.2 Miles | Actual: | $598,306 |
District: | Atlanta | Let Date: | MAY 2011 |
Highway: | US 259 | Let Status: | Actual |
Project ID: | STP 2011(947)HES | CSJ: | 0085-04-039 |
Description: | TEXTURIZE SHOULDERS & CENTERLINE TEXTURING | Handling Code: |
|
Limits From: | OKLAHOMA STATE LINE | Fund Cat: | 8 |
Limits To: | 0.3 MI. SOUTH OF FM 44 | Estimate: | $436,484 |
Length: | 14.8 Miles | Actual: | $567,560 |
District: | Atlanta | Let Date: | MAY 2011 |
Highway: | US 259 | Let Status: | Actual |
Project ID: | STP 2011(947)HES | CSJ: | 0392-01-068 |
Description: | TEXTURIZE SHOULDERS & CENTERLINE TEXTURING | Handling Code: |
|
Limits From: | SH 49 | Fund Cat: | 8 |
Limits To: | UPSHUR COUNTY LINE | Estimate: | $145,040 |
Length: | 9.0 Miles | Actual: | $121,253 |
District: | Atlanta | Let Date: | MAY 2011 |
Highway: | US 259 | Let Status: | Actual |
Project ID: | STP 2011(947)HES | CSJ: | 0392-02-084 |
Description: | TEXTURIZE SHOULDERS & CENTERLINE TEXTURING | Handling Code: |
|
Limits From: | MORRIS COUNTY LINE | Fund Cat: | 8 |
Limits To: | GREGG COUNTY LINE | Estimate: | $589,099 |
Length: | 17.8 Miles | Actual: | $488,917 |
Back... |
Totals for 0085-04-039 | ||
Length: | 73.0 Miles | ||
Estimate: | $2,112,837 | ||
Actual: | $2,109,795 | ||
CCSJ: 0217-01-027 | |||
District: | Atlanta | Let Date: | NOV 2010 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | NH 2009(645) | CSJ: | 0217-01-027 |
Description: | CONSTRUCT NEW LOCATION LOOP NORTHEAST OF TEXARKANA | Handling Code: |
LC |
Limits From: | AT TEXARKANA NORTHERN LOOP | Fund Cat: | 11 |
Limits To: | (JOINT PROJECT W/ARKANSAS) | Estimate: | $500,000 |
Length: | 0.1 Miles | Actual: | $764,873 |
Back... |
Totals for 0217-01-027 | ||
Length: | 0.1 Miles | ||
Estimate: | $500,000 | ||
Actual: | $764,873 | ||
CCSJ: 0217-01-032 | |||
District: | Atlanta | Let Date: | MAR 2011 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | STP 2011(931)HES | CSJ: | 0062-07-083 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 1.3 MI N OF FM 1793 | Fund Cat: | 8 |
Limits To: | 0.1 MI N OF SH 43 N | Estimate: | $398,111 |
Length: | 3.9 Miles | Actual: | $429,898 |
District: | Atlanta | Let Date: | MAR 2011 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | STP 2011(931)HES | CSJ: | 0063-04-055 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | 0.3 MI S OF FM 2517 | Fund Cat: | 8 |
Limits To: | MURVAUL CREEK | Estimate: | $281,797 |
Length: | 2.5 Miles | Actual: | $303,648 |
District: | Atlanta | Let Date: | MAR 2011 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | STP 2011(931)HES | CSJ: | 0063-05-034 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | MURVAUL CREEK | Fund Cat: | 8 |
Limits To: | FM 999 | Estimate: | $125,240 |
Length: | 1.4 Miles | Actual: | $135,320 |
District: | Atlanta | Let Date: | MAR 2011 |
Highway: | SH 43 | Let Status: | Actual |
Project ID: | STP 2011(932) | CSJ: | 0207-04-034 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | HARRISON C/L | Fund Cat: | 1 |
Limits To: | RUSK C/L | Estimate: | $259,339 |
Length: | 5.0 Miles | Actual: | $267,404 |
District: | Atlanta | Let Date: | MAR 2011 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | STP 1102(013)HES | CSJ: | 0217-01-032 |
Description: | SEAL COAT AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | ARKANSAS SL | Fund Cat: | 1 |
Limits To: | 3.9 MI S OF ARKANSAS SL | Estimate: | $417,920 |
Length: | 3.9 Miles | Actual: | $440,048 |
District: | Atlanta | Let Date: | MAR 2011 |
Highway: | US 79 | Let Status: | Actual |
Project ID: | STP 2011(932) | CSJ: | 0247-02-045 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | 0.2 MI S OF MILL CREEK | Fund Cat: | 1 |
Limits To: | SABINE RIVER BRIDGE | Estimate: | $299,136 |
Length: | 3.3 Miles | Actual: | $316,843 |
District: | Atlanta | Let Date: | MAR 2011 |
Highway: | SH 338 | Let Status: | Actual |
Project ID: | STP 2011(932) | CSJ: | 0622-01-013 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | SH 77 | Fund Cat: | 1 |
Limits To: | US 259 | Estimate: | $204,210 |
Length: | 6.5 Miles | Actual: | $210,719 |
District: | Atlanta | Let Date: | MAR 2011 |
Highway: | FM 127 | Let Status: | Actual |
Project ID: | STP 2011(931)HES | CSJ: | 0734-01-040 |
Description: | SEAL COAT AND PAVMENT MARKINGS | Handling Code: |
|
Limits From: | TEXAS UTILITIES RAILROAD | Fund Cat: | 8 |
Limits To: | US 271 | Estimate: | $252,294 |
Length: | 6.2 Miles | Actual: | $265,305 |
District: | Atlanta | Let Date: | MAR 2011 |
Highway: | FM 1402 | Let Status: | Actual |
Project ID: | STP 2011(932) | CSJ: | 1384-01-025 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | FM 71 | Fund Cat: | 1 |
Limits To: | US 67 | Estimate: | $316,541 |
Length: | 12.7 Miles | Actual: | $327,968 |
District: | Atlanta | Let Date: | MAR 2011 |
Highway: | FM 968 | Let Status: | Actual |
Project ID: | STP 2011(932) | CSJ: | 1575-02-033 |
Description: | SEAL COAT | Handling Code: |
|
Limits From: | GREGG C/L | Fund Cat: | 1 |
Limits To: | IH 20 | Estimate: | $86,413 |
Length: | 2.9 Miles | Actual: | $89,505 |
Back... |
Totals for 0217-01-032 | ||
Length: | 48.3 Miles | ||
Estimate: | $2,641,001 | ||
Actual: | $2,786,658 |
|
|