Detail Letting Schedule for Walker County (FY 2018)
| Walker County (FY 2018) |
CCSJ: 0675-06-096 |
|||
| District: | BRYAN | Let Date: | Mar 2018 |
| Highway: | IH 45 | Let Status: | Actual |
| Project ID: | C 675-6-96 | CSJ: | 0675-06-096 |
| Description: | FOR THE CONSTRUCTION OF AN OVERLAY CONSISTING OF MILLING, | Handling Code: | |
| Limits From: | SH 75 ON SBML | Fund Cat: | 1 |
| Limits To: | 0.08 MILES S OF MADISON C/L | ESTIMATE: | $8,437,404 |
| Length: | 14.9 | Actual | $6,333,634 |
| Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0675-06-096 | ||
|---|---|---|---|
| Length: | 14.9 | ||
| Estimate: | $8,437,404 | ||
| Actual: | $6,333,634 | ||
| Handling Code | Definition |
|---|---|
| XX | Project not processed through statewide letting |
| TR | Transfer of funds |
| LC | Project let through local entity |
| LC | Project not charged against district apportionment |
| Let Status | Definition |
|---|---|
| Tentative | Estimated letting date for this project |
| Approved | Project has administrative approval to be let |
| Actual | Project was let to contract |