Detail Letting Schedule for Clay County (FY 2021)
Bid Tabulations Dashboard
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Clay County (FY 2021) |
CCSJ: 0224-02-045 |
|||
District: | WICHITA FALLS | Let Date: | Oct 2019 |
Highway: | US 287 | Let Status: | Tentative |
Project ID: | NH ( ) | CSJ: | 0224-02-045 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: | |
Limits From: | AT EAST FORK LITTLE WICHITA | Fund Cat: | 6 |
Limits To: | RIVER (NB) | ESTIMATE: | $500,000 |
Length: | 0.1 | Actual | $0 |
District: | WICHITA FALLS | Let Date: | Oct 2019 |
Highway: | US 287 | Let Status: | Tentative |
Project ID: | NH ( ) | CSJ: | 0224-02-046 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: | |
Limits From: | AT EAST FORK LITTLE WICHITA RIVER | Fund Cat: | 6 |
Limits To: | RELIEF (NB) | ESTIMATE: | $500,000 |
Length: | 0.1 | Actual | $0 |
Award Status Back... | Totals for 0224-02-045 | ||
---|---|---|---|
Length: | 0.2 | ||
Estimate: | $1,000,000 | ||
Actual: |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |