Detail Letting Schedule for Parmer County (FY 2021)
Bid Tabulations Dashboard
This report will no longer be updated, please access links on the Contract Letting page. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
Parmer County (FY 2021) |
CCSJ: 0052-01-044 |
|||
District: | LUBBOCK | Let Date: | Jan 2021 |
Highway: | US 70 | Let Status: | Actual |
Project ID: | NH 2021(294) | CSJ: | 0052-01-044 |
Description: | HIGHWAY/RAILROAD IMPROVEMENT | Handling Code: | |
Limits From: | 2.06 MILES EAST OF FARWELL CITY LIMITS | Fund Cat: | 1 |
Limits To: | 2.49 MILES EAST OF FARWELL CITY LIMITS | ESTIMATE: | $1,871,127 |
Length: | 0.0 | Actual | $1,937,606 |
District: | LUBBOCK | Let Date: | Jan 2021 |
Highway: | FM 145 | Let Status: | Actual |
Project ID: | STP 2021(295) | CSJ: | 0754-01-009 |
Description: | INTERSECTION IMPROVEMENT | Handling Code: | |
Limits From: | US 84 | Fund Cat: | 1 |
Limits To: | 0.57 MILES EAST OF US 84 | ESTIMATE: | $858,294 |
Length: | 0.0 | Actual | $1,283,128 |
Proposal Request Bid List List Showing Order Bid Tabulations Award Status Back... | Totals for 0052-01-044 | ||
---|---|---|---|
Length: | 0 | ||
Estimate: | $2,729,421 | ||
Actual: | $3,220,734 | ||
CCSJ: 0052-01-045 |
|||
District: | LUBBOCK | Let Date: | Apr 2021 |
Highway: | US 70 | Let Status: | Actual |
Project ID: | STP 2021(667)FRS2 | CSJ: | 0052-01-045 |
Description: | HAZARD ELIMINATION & SAFETY | Handling Code: | XX |
Limits From: | US 70/84 | Fund Cat: | 8 |
Limits To: | AT DOT#014787R | ESTIMATE: | $275,497 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 0052-01-045 | ||
Length: | 0 | ||
Estimate: | $275,497 | ||
Actual: | |||
CCSJ: 3520-01-022 |
|||
District: | LUBBOCK | Let Date: | Apr 2021 |
Highway: | FM 3333 | Let Status: | Actual |
Project ID: | STP 2021(663)FRS2 | CSJ: | 3520-01-022 |
Description: | RAILROAD CROSSING IMPROVEMENTS | Handling Code: | XX |
Limits From: | US 60 AT FM 3333 | Fund Cat: | 8 |
Limits To: | DOT# 014783N BNSF | ESTIMATE: | $457,622 |
Length: | 0.0 | Actual | $0 |
Back... | Totals for 3520-01-022 | ||
Length: | 0 | ||
Estimate: | $457,622 | ||
Actual: |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |