Detail Letting Schedule for Coryell County (FY 2022)

Last Update: Tuesday, November 30, 2021

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Coryell County (FY 2022)

CCSJ: 0184-01-065

District:WACOLet Date:Mar 2022
Highway:SH 36Let Status:Approved
Project ID:STP ()HESCSJ:0184-01-065
Description:HAZARD ELIMINATION & SAFETYHandling
Code:
 
Limits From:AT FM 107Fund Cat:8
Limits To:.ESTIMATE:$47,667
Length:0.2Actual$0
 
Back...
Totals for 0184-01-065
Length:0.2
Estimate:$47,667
Actual:

CCSJ: 0184-05-005

District:WACOLet Date:Jun 2022
Highway:BS 36-ELet Status:Tentative
Project ID:F ()CSJ:0184-05-005
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:US 84Fund Cat:1
Limits To:SH 36ESTIMATE:$1,200,000
Length:0.0Actual$0
 
Back...
Totals for 0184-05-005
Length:0
Estimate:$1,200,000
Actual:

CCSJ: 0724-01-056

District:WACOLet Date:Dec 2021
Highway:FM 116Let Status:Approved
Project ID:STP 2022(156)HESCSJ:0724-01-056
Description:HAZARD ELIMINATION & SAFETYHandling
Code:
 
Limits From:AT SH 9Fund Cat:8
Limits To:.ESTIMATE:$12,373,652
Length:1.0Actual$0
 
Proposal Request
List Showing Order
Bid List
Back...
Totals for 0724-01-056
Length:1
Estimate:$12,373,652
Actual:

CCSJ: 0909-39-134

District:WACOLet Date:Jun 2022
Highway:CRLet Status:Tentative
Project ID:BR 2019(328)CSJ:0909-39-134
Description:BRIDGE REPLACEMENTHandling
Code:
 
Limits From:CR 274 @ CLEAR CREEKFund Cat:6
Limits To:(MAP #029)ESTIMATE:$575,000
Length:0.0Actual$0
 
Back...
Totals for 0909-39-134
Length:0
Estimate:$575,000
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract