The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Morris County (FY 2022)

CCSJ: 0610-04-039

District:ATLANTALet Date:Jan 2022
Highway:IH 30Let Status:Tentative
Project ID:CSJ:0610-04-039
Description:REPAIR ROADWAYHandling
Code:
 
Limits From:US 259Fund Cat:1
Limits To:MORRIS C/LESTIMATE:$725,478
Length:2.5Actual$0
 
District:ATLANTALet Date:Jan 2022
Highway:IH 30Let Status:Tentative
Project ID:CSJ:0610-05-059
Description:REPAIR ROADWAYHandling
Code:
 
Limits From:MORRIS C/LFund Cat:1
Limits To:0.3 MI. E. OF SH 98ESTIMATE:$2,711,748
Length:17.4Actual$0
 
District:ATLANTALet Date:Jan 2022
Highway:IH 30Let Status:Tentative
Project ID:CSJ:0610-06-093
Description:REPAIR ROADWAYHandling
Code:
 
Limits From:0.3 MI. E. OF SH 98Fund Cat:1
Limits To:SS 74ESTIMATE:$2,818,582
Length:13.5Actual$0
 
District:ATLANTALet Date:Jan 2022
Highway:IH 30Let Status:Tentative
Project ID:CSJ:0610-07-119
Description:REPAIR ROADWAYHandling
Code:
 
Limits From:SS 74Fund Cat:1
Limits To:FM 989ESTIMATE:$1,725,048
Length:6.2Actual$0
 
Back...
Totals for 0610-04-039
Length:39.6
Estimate:$7,980,856
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract