House District 4 Construction Report

Last Update: Sunday, November 10, 2024
 

View Report for Senate District Number:

View Report for House District Number:


 

Projects Under Construction

 
TxDOT DistrictCountyCCSJProject IDObligated AmountOther Sharing Districts
HoustonMontgomery140004040STP 2022(697)HES$1,870,035.50003
HoustonMontgomery274401032C 2744-1-32$10,866,955.64003, 016
HoustonMontgomery191201022C 1912-1-22$7,041,940.21003, 016, 018
HoustonMontgomery017705112C 177-5-112$3,716,482.69003, 018
HoustonMontgomery011004219C 110-4-219$2,579,830.79003, 015, 016, 150, 012, 141, 140, 139, 134
HoustonMontgomery052310047STP 2022(307)HES$10,225,881.20003, 015
HoustonMontgomery353801055F 2021(547)$30,991,507.54003
HoustonMontgomery052309009C 523-9-9$48,285,563.88003
HoustonMontgomery017714045STP 2B24(343)HES$573,846.14003
HoustonMontgomery353801045STP 2018(858)$23,483,270.27003
HoustonMontgomery017714010STP 1802(602)$14,347,428.72003
HoustonMontgomery052308007C 523-8-7$29,787,407.89003
HoustonMontgomery353801035STP 2019(952)$36,793,630.18003, 015
HoustonMontgomery353801036STP 2019(797)$65,322,056.94003, 018
HoustonMontgomery198601070STP 2B23(073)HES$2,022,486.20003
HoustonMontgomery091237237STP 2024(139)TP$4,077,635.10003, 016
HoustonMontgomery141603018C 1416-3-18$4,541,531.81003, 016
HoustonMontgomery353801060C 3538-1-60$8,197,532.35003, 015, 018
HoustonMontgomery351007015C 3510-7-15$12,409,870.43003, 015, 130, 132, 135, 126
HoustonMontgomery198601064C 1986-1-64$31,355,904.72003
HoustonMontgomery011004209C 110-4-209$1,297,846.95003, 015, 016
HoustonWaller005005067STP 2020(593)$5,433,536.70003
HoustonWaller011411082NH 2B20(183)$4,591,144.05003
HoustonWaller027104071NH 1702(007)$141,496,478.10003
 

 
Total number of projects under construction: 24
Total obligated amount: $ 501,309,804.00