Monthly State Let Construction Report For Houston District As Of Jul 13, 2021 Page 1 Of 11

Last Update: Friday, July 16, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyFORT BEND
HighwayUS 90A
From0.21 MILES WEST OF LANE DRIVE
ToFM 3155
CSJ0027-07-032
Proj IDC 27-7-32
Work TypeREPLACE EXISTING RAILROAD UNDERPASS
 
0.59518405189.024363769.5023.7
Work Order05-30-17
Work Began02-19-18
Work Completed
Time Computed06-29-17
Contract Working Days541
Addl Days Granted0
Working Days Charged35
Percent Time Used6
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0027-07-032
TRAFFIC SYSTEMS CONSTRUCTION, INC. (3.93)
GEORGE MEEKS LANDPRO, INC. (0.47)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.80)
RDI FOUNDATION DRILLING (4.63)
PRIMATE CONSTRUCTION, INC. (0.23)
MESA ROD BUSTERS, INC. (0.78)
BORTUNCO (2.87)
PROFESSIONAL TRAFFIC CONTROL LLC (0.55)
SEMARCK LANDSCAPE SERVICES, INC. (0.12)
Contract #01173003
Totals18405189.022500.004363769.5023.7

CountyHARRIS
HighwayUS 90A
FromUS 90A/S.WAYSIDE @ COUNTRY CLUB BYU
To.
CSJ0027-10-071
Proj IDBR 2018(234)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1263815251.204100104.1899.9
Work Order11-13-17
Work Began06-07-18
Work Completed
Time Computed01-12-18
Contract Working Days137
Addl Days Granted18
Working Days Charged160
Percent Time Used103
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0027-10-071
WEBER-BALKE FOUNDATION COMPANY, INC (7.29)
ENVIRONMENTAL ALLIES, L.P. (0.14)
FOSTER FENCE, LTD. (0.10)
GMJ PAVING CO. (2.05)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (5.28)
BATTERSON,LLP (0.57)
JMHP, INC. (1.33)
A-1 EROSION CONTROL, LLC (0.35)
HIGHWAY 1 LLC (0.40)
SOUTHERN CRUSHED CONCRETE LLC (0.52)
MESA ROD BUSTERS, INC. (1.53)
PRIMATE CONSTRUCTION, INC. (0.27)
SCOTT DERR PAINTING CO, LLC (0.08)
FARR FOUNDATION, INC. (1.65)
MESA ROD BUSTERS, INC. (0.56)
PEREZ CONSTRUCTION CO. (0.06)
DORAN STEEL, INC. (0.41)
Contract #10173218
Totals3815251.200.004100104.1899.9

CountyFORT BEND
HighwayIH 69
FromW OF FM 762
To0.31 MI W OF FM 2759
CSJ0027-12-097
Proj IDNH 1402(081)
Work TypeGR, STRS, BASE, PAVE & HOV LNS
 
4.271155200552.60161266260.1699.9
CountyFORT BEND
HighwayIH 69
FromFM 762 EAST
ToFM 762 WEST
CSJ0027-12-137
Proj IDSTP 2011(256)TE
Work TypeENHANCEMENT PROJECT
 
0.001535282.3096869.4018.0
CountyFORT BEND
HighwayIH 69
FromAT FM 762
To.
CSJ0027-12-144
Proj IDNH 1402(081)
Work TypeINTERSECTION IMPROVEMENTS
 
0.001293400.00426995.0399.9
Work Order09-23-14
Work Began09-23-14
Work Completed
Time Computed10-09-14
Contract Working Days1,045
Addl Days Granted0
Working Days Charged1,045
Percent Time Used100
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0027-12-097
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.71)
PROFESSIONAL TRAFFIC CONTROL, LLC (0.48)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (3.63)
INDUS CONSTRUCTION, L.P. (12.04)
BUILDER SERVICES CO. (0.10)
QUALITY TURF GRASS (1.46)
WASTE PARTNERS OF TEXAS, INC (0.05)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.24)
BASE CONSTRUCTION (0.45)
BORTUNCO (0.18)
BAY CITY TRAFFIC (0.10)
BATTEN DRILLING, INC. (0.10)
RAY"S THREADING AND FAB SHOP (0.58)
SCOTT DERR PAINTING CO, LLC (0.02)
YELLOWSTONE LANDSCAPE - CENTRAL, INC. (0.08)
WEST TEXAS ROCK RESOURCES, LLC (0.02)
ESSARY, HART & MACWILLIAM, INC. (0.00)
Contract #08143201
Totals156029234.90158803.97161790124.5999.9

CountyFORT BEND
HighwayUS 59
FromW OF SH 36
ToW OF FM 762
CSJ0027-12-105
Proj IDNH 2014(211)
Work TypeWIDEN TO 6 LN RURAL FW, GRD SEP, IT
 
7.350133473457.87135072638.3599.9
CountyFORT BEND
HighwayUS 59
FromW OF SH 36
ToW OF FM 762
CSJ0027-12-126
Proj IDRW 27-12-126
Work TypeROW ACQUISITION
 
0.0011758017.201668692.6694.9
CountyFORT BEND
HighwayUS 59
FromSP 10
ToW OF SH 36
CSJ0027-12-127
Proj IDRW 27-12-127
Work TypeROW ACQUISITION
 
0.001637063.65718758.9599.9
Work Order02-27-14
Work Began04-17-14
Work Completed
Time Computed04-17-14
Contract Working Days1,079
Addl Days Granted472
Working Days Charged1,407
Percent Time Used90
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0027-12-105
BATTERSON,LLP (0.99)
CREACOM, INC. (5.17)
BASE CONSTRUCTION, L.L.P. (7.01)
WILLOW CITY SIGN & RAIL, INC. (1.04)
ESSARY, HART & MACWILIAM,INC. (11.23)
QUALITY TURF GRASS (1.47)
CPAVE, INC. (0.29)
TEXAS HIGHWAY WALLS (3.69)
HOUSTON SAWING & DRILLING (0.03)
SCOTT DERR PAINTING CO, LLC (0.01)
BUILDER SERVICES CO. (0.46)
BORTUNCO (0.82)
WASTE PARTNERS OF TEXAS, INC (0.02)
DRILL TECH DRILLING & SHORING, INC. (5.87)
RAY"S THREADING AND FAB SHOP (0.98)
TEXAS CUTTING & CORING GP, INC. (0.02)
WEST TEXAS ROCK RESOURCES, LLC (0.06)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.00)
Contract #01143001
Totals135868538.72583019.24137460089.9699.9

CountyFORT BEND
HighwayIH 69
FromEAST OF SS 529
ToSH 99
CSJ0027-12-152
Proj IDC 27-12-152
Work TypeCORRIDOR TRAFFIC MANAGEMENT
 
22.5463151614.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-14-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days450
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0027-12-152
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12203204
Totals3151614.400.000.000.0

CountyHARRIS
HighwayIH 69
FromFORT BEND C/L
ToSOUTH OF BISSONNET
CSJ0027-13-212
Proj IDNH 2019(365)
Work TypeUPGRADE HIGH MAST & UNDERPASS LIGHT
 
4.5224728767.665768922.0299.9
Work Order03-19-19
Work Began07-31-19
Work Completed
Time Computed07-17-19
Contract Working Days220
Addl Days Granted70
Working Days Charged299
Percent Time Used103
Contractor(s)
SICE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0027-13-212
SPECIALTY DRILLING, LTD. (9.42)
JMHP, INC. (1.15)
DORAN STEEL, INC. (0.48)
SIGNAL SERVICES GROUP INC. (9.40)
VACA UNDERGROUND UTILITIES INC (3.85)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (1.19)
POWER LINE SOLUTIONS, INC. (2.14)
ALTUS CONSTRUCTION LLC (2.79)
SPECIALTY DRILLING, LLC (9.42)
Contract #02193009
Totals4728767.6658208.695768922.0299.9

CountyHARRIS
HighwayIH 69
FromN OF BEECHNUT
ToHILLCROFT
CSJ0027-13-222
Proj IDNH 2019(965)
Work TypeTRAFFIC CONTROL DEVICES
 
4.0033258510.853156887.7796.8
Work Order07-17-19
Work Began01-06-20
Work Completed
Time Computed11-14-19
Contract Working Days181
Addl Days Granted26
Working Days Charged176
Percent Time Used85
Contractor(s)
MICA CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0027-13-222
M & D FOUNDATION DRILLING INDUSTRIES, INC. (11.84)
BLACKTOP INDUSTRIES LLC (1.36)
SOWELLS ENGINEERS & CONSTRUCTORS, LLC (2.42)
DORAN STEEL, INC. (0.54)
STAR-AMSTON GLOBAL LIMITED (2.75)
Contract #06193018
Totals3258510.8515813.353156887.7796.8

CountyHARRIS
HighwayUA 90
FromIH 10
ToIH 610
CSJ0028-01-099
Proj IDNH 2020(693)
Work TypeOVERLAY
 
1.4781366270.54874607.4864.0
Work Order07-07-20
Work Began09-08-20
Work Completed
Time Computed08-06-20
Contract Working Days64
Addl Days Granted13
Working Days Charged58
Percent Time Used75
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0028-01-099
TRAFFIC SIGNS & LINES, LLC (0.86)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.69)
STRIPE LINES, INC. (5.72)
TEXOP CONSTRUCTION (2.28)
AIMS COMPANIES (2.11)
ASPLUNDH TREE EXPERT, LLC (2.67)
QUICK MATERIALS (1.40)
BUYERS BARRICADES HOUSTON, LLC (1.06)
PROSCAPE DEVELOPMENT LLC (2.75)
Contract #04203227
Totals1366270.5455829.83874607.4864.0

CountyHARRIS
HighwayUS 90
FromIH 610 E
ToBW 8
CSJ0028-02-092
Proj IDNH 2018(415)
Work TypeINSTALL ITS EQUIPMENT & INFRASTRUC
 
6.4731782760.65503113.1328.2
Work Order05-29-18
Work Began06-28-18
Work Completed
Time Computed06-28-18
Contract Working Days375
Addl Days Granted0
Working Days Charged176
Percent Time Used46
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0028-02-092
SPECIALTY DRILLING, LLC (1.67)
Contract #04183016
Totals1782760.6560983.50503113.1328.2

CountyHARRIS
HighwayUS 90
FromHUNTING BAYOU
ToLINDSTROM ROAD
CSJ0028-02-100
Proj IDC 28-2-100
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
32.5751486713.951386197.4593.2
Work Order07-20-20
Work Began09-09-20
Work Completed
Time Computed08-19-20
Contract Working Days135
Addl Days Granted0
Working Days Charged89
Percent Time Used65
Contractor(s)
TEXAS WALL & LANDSCAPE
SUBCONTRACTOR(S) FOR CCSJ: 0028-02-100
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06203011
Totals1486713.9538476.701386197.4593.2

CountyWALLER
HighwaySH 6
FromGRIMES COUNTY LINE
ToUS 290
CSJ0050-04-027
Proj IDC 50-4-27
Work TypeOVERLAY
 
8.0345294013.770.000.0
Work Order03-12-21
Work Began00-00-00
Work Completed
Time Computed05-11-21
Contract Working Days138
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VULCAN CONSTRUCTION TEMP
SUBCONTRACTOR(S) FOR CCSJ: 0050-04-027
WILLOW CITY SIGN & RAIL, INC. (3.22)
F. N. PLOCH CONSTRUCTION COMPANY, INC. (16.74)
PINNACLE GRINDING AND GROOVING LLC (0.19)
ASE CONTRACTORS LLC (2.34)
HIGHWAY 1 LLC (8.26)
Contract #02213207
Totals5294013.770.000.000.0

CountyWALLER
HighwayBU 290H
FromSH 6
ToHARRIS COUNTY LINE
CSJ0050-05-067
Proj IDSTP 2020(593)
Work TypeOVERLAY
 
10.9995433536.705513722.9499.9
Work Order04-28-20
Work Began09-09-20
Work Completed
Time Computed06-29-20
Contract Working Days135
Addl Days Granted3
Working Days Charged140
Percent Time Used101
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0050-05-067
TOTAL HIGHWAY MAINTENANCE, LLC (6.25)
LONESTAR TRAFFIC SAFETY, LLC (0.26)
BATTERSON, LLP (0.30)
THIRD COAST SERVICES LLC (4.05)
WILLOW CITY SIGN & RAIL, INC. (6.06)
TEXOP CONSTRUCTION (3.36)
R & A TRANSPORT, INC. (2.13)
AVILES CONSTRUCTION SERVICE, INC (1.23)
Contract #02203007
Totals5433536.70352925.575513722.9499.9

CountyHARRIS
HighwayUS 290
FromEAST OF MUESCHKE ROAD
ToEAST OF TELGE ROAD (SEGMENT 9)
CSJ0050-06-081
Proj IDNH 2013(983)
Work TypeGR, STRS, BASE AND PAVE
 
4.96285215953.75100610357.7799.9
Work Order12-11-13
Work Began02-11-14
Work Completed
Time Computed02-09-14
Contract Working Days960
Addl Days Granted544
Working Days Charged1,499
Percent Time Used99
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0050-06-081
ALLSTATE SIGNAL & CONSTRUCTION, LLC (6.46)
BASE CONSTRUCTION, L.L.P. (14.87)
BROOKLYN SWEEPS (0.38)
ESSARY, HART & MACWILIAM,INC. (5.59)
HIGHWAY PAVEMENT SPECIALTIES, INC. (2.43)
INTERSTATE BARRICADES & MARKINGS, INC. (0.87)
ROADWAY CONSTRUCTION, LLC (2.24)
SCOTT DERR PAINTING CO, LLC (0.06)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.62)
TEXAS ENVIRONMENTAL MANAGEMENT, INC (0.54)
A R DANIEL CONSTRUCTION SERVICES, INC. (0.71)
BATTEN DRILLING, INC. (0.10)
UNDER CONSTRUCTION INC. (0.33)
SCMU (0.76)
CONSTRUCTION DIVERSITY GROUP, LLC (0.44)
PENHALL COMPANY (6.18)
PROFESSIONAL TRAFFIC CONTROL, LLC (0.00)
ANTIGO CONSTRUCTION, INC. (0.02)
ISI CONTRACTING, INC. (0.05)
PMI PAVEMENT MARKING, LLC (0.11)
Contract #11133002
Totals85215953.750.00100610357.7799.9

CountyHARRIS
HighwayUS 290
FromTELGE ROAD
ToB 290
CSJ0050-06-090
Proj IDNH 1802(600)
Work TypeLANDSCAPE ENHANCEMENTS
 
12.2931140000.001039844.0691.2
Work Order09-26-18
Work Began03-11-19
Work Completed
Time Computed10-26-18
Contract Working Days120
Addl Days Granted0
Working Days Charged120
Percent Time Used100
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0050-06-090
BUYERS BARRICADES, INC. (1.20)
Contract #08183245
Totals1140000.006500.001039844.0691.2

CountyHARRIS
HighwayBU 290H
From0.25 MI NW OF KICKAPOO RD
To0.25 MI SE OF KICKAPOO RD
CSJ0050-06-094
Proj IDSTP 2021(331)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.50078734.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-17-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0050-06-094
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05213236
Totals78734.400.000.000.0

CountyHARRIS
HighwayUS 290
FromEAST OF TELGE ROAD
ToWEST OF ELDRIDGE PKWY (SEGMENT 8)
CSJ0050-08-087
Proj IDCM 2013(740)
Work TypeGR, STRS, BASE AND PAVE
 
3.12594106953.38132657799.7899.9
CountyHARRIS
HighwayFM 1960
FromUS 290
ToNORTH ELDRIDGE PARKWAY
CSJ1685-01-093
Proj IDCM 2013(740)
Work TypeRECST US 290/SH 6 INTERCHANGE
 
0.74016196261.8316152324.3899.7
CountyHARRIS
HighwaySH 6
FromSOUTH OF HEMPSTEAD ROAD
ToUS 290
CSJ1685-05-098
Proj IDCM 2013(740)
Work TypeRECST US 290/SH 6 INTERCHANGE
 
0.67725152540.7723136889.0691.9
Work Order05-16-13
Work Began08-12-13
Work Completed
Time Computed01-06-14
Contract Working Days1,052
Addl Days Granted628
Working Days Charged1,669
Percent Time Used99
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0050-08-087
CPAVE, INC. (0.19)
HOUSTON SAWING & DRILLING (0.03)
SCOTT DERR PAINTING CO (0.08)
Z & L CONCRETE CONTRACTORS, INC. (0.42)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.20)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.60)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (4.82)
BASE CONSTRUCTION, L.L.P. (11.75)
ESSARY, HART & MACWILIAM,INC. (8.84)
INTERSTATE BARRICADES & MARKINGS, INC. (0.70)
ROADWAY CONSTRUCTION, INC. (0.45)
BROOKLYN SWEEPS (0.24)
BATTEN DRILLING, INC. (0.06)
A R DANIEL CONSTRUCTION SERVICES, INC. (0.53)
ANTIGO CONSTRUCTION, INC. (0.03)
PINNACLE GRINDING AND GROOVING LLC (1.43)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.10)
Contract #04133232
Totals135455755.98354069.65171947013.2299.9

CountyHARRIS
HighwayUS 290
FromFM 529
ToWEST OF IH 610
CSJ0050-09-095
Proj IDNH 1902(173)
Work TypeLSE
 
7.1191648298.342325988.7799.9
Work Order08-13-19
Work Began03-16-20
Work Completed
Time Computed09-12-19
Contract Working Days135
Addl Days Granted0
Working Days Charged135
Percent Time Used100
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0050-09-095
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193025
Totals1648298.3411101.292325988.7799.9

CountyHARRIS
HighwaySH 3
FromRICHEY ST S
ToGALVESTON C/L
CSJ0051-02-101
Proj IDSTP 2019(765)TAP
Work TypeADD BIKES LNS
 
13.26613218969.8610812942.0581.7
CountyGALVESTON
HighwaySH 3
FromHARRIS C/L
ToFM 518
CSJ0051-03-109
Proj IDSTP 2019(765)TAP
Work TypeADD BIKE LANES
 
1.072732989.74517382.7570.5
Work Order05-14-19
Work Began07-22-19
Work Completed
Time Computed06-13-19
Contract Working Days600
Addl Days Granted0
Working Days Charged418
Percent Time Used69
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0051-02-101
PROFESSIONAL TRAFFIC CONTROL LLC (6.69)
WILLOW CITY SIGN & RAIL, INC. (1.56)
GREEN SAGE SERVICES LLC (4.37)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (4.72)
Contract #04193218
Totals13951959.60641103.9911330324.8081.2

CountyGALVESTON
HighwaySH 87
From59TH STREET
ToSEAWALL BLVD
CSJ0051-04-067
Proj IDNH 1902(174)
Work TypeOV
 
3.88510994229.675670031.3051.6
Work Order08-13-19
Work Began09-25-19
Work Completed
Time Computed09-12-19
Contract Working Days210
Addl Days Granted0
Working Days Charged219
Percent Time Used104
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0051-04-067
TRAFFIC SIGNS & LINES, LLC (0.40)
PROFESSIONAL TRAFFIC CONTROL LLC (1.99)
KMA CONTRACTORS SERVICES (0.00)
AAA ASPHALT PAVING, INC. (0.18)
Contract #07193218
Totals10994229.67923091.695670031.3051.6

CountyGALVESTON
HighwaySS 342
FromAT HEARDS LANE
To.
CSJ0051-08-019
Proj IDSTP 2021(260)HES
Work TypeTRAFFIC CONTROL DEVICES
 
2.000243649.850.000.0
CountyBRAZORIA
HighwaySH 35
FromAT FM 524
To.
CSJ0179-11-004
Proj IDSTP 2021(260)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200145343.200.000.0
CountyBRAZORIA
HighwaySH 332
FromAT FM 523
To.
CSJ0586-01-068
Proj IDSTP 2021(260)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.20019680.000.000.0
CountyGALVESTON
HighwayFM 2004
From0.5 MI N OF TACQUARD RANCH ROAD
To0.5 MI S OF TACQUARD RANCH ROAD
CSJ2523-01-027
Proj IDSTP 2021(260)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.00049795.000.000.0
Work Order03-01-21
Work Began00-00-00
Work Completed
Time Computed06-29-21
Contract Working Days61
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CITYLYNX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0051-08-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01213222
Totals458468.050.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11