Monthly State Let Construction Report For Houston District As Of Jan 10, 2023 Page 1 Of 12

Last Update: Tuesday, January 10, 2023
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyFORT BEND
HighwayUS 90A
From0.21 MILES WEST OF LANE DRIVE
ToFM 3155
CSJ0027-07-032
Proj IDC 27-7-32
Work TypeREPLACE EXISTING RAILROAD UNDERPASS
 
0.59518405189.024493714.1524.4
Work Order05-30-17
Work Began02-19-18
Work Completed
Time Computed06-30-17
Contract Working Days541
Addl Days Granted0
Working Days Charged35
Percent Time Used6
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0027-07-032
TRAFFIC SYSTEMS CONSTRUCTION, INC. (3.93)
GEORGE MEEKS LANDPRO, INC. (0.47)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.80)
RDI FOUNDATION DRILLING (4.63)
PRIMATE CONSTRUCTION, INC. (0.23)
MESA ROD BUSTERS, INC. (0.78)
BORTUNCO (2.87)
PROFESSIONAL TRAFFIC CONTROL LLC (0.55)
SEMARCK LANDSCAPE SERVICES, INC. (0.12)
Contract #01173003
Totals18405189.022500.004493714.1524.4

CountyHARRIS
HighwayUS 90A
FromFORT BEND COUNTY LINE
ToIH 610S
CSJ0027-09-104
Proj IDCM 2022(106)
Work TypeCORRIDOR TRAFFIC MANAGEMENT
 
6.8955773289.684521004.9478.3
Work Order01-12-22
Work Began00-00-00
Work Completed
Time Computed02-11-22
Contract Working Days270
Addl Days Granted0
Working Days Charged90
Percent Time Used33
Contractor(s)
SICE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0027-09-104
BUYERS BARRICADES HOUSTON, LLC (0.69)
PROFESSIONAL SERVICE INDUSTRIES, INC. (0.24)
MCA COMMUNICATIONS, INC. (2.53)
JH CONTRACT FIELD SERVICES, LLC (0.83)
AZTECA UTILITY RR SERVICES INC (9.49)
APTUS GROUP USA, LLC (18.23)
DORAN STEEL, INC. (0.04)
Contract #11213205
Totals5773289.68845276.514521004.9478.3

CountyFORT BEND
HighwayIH 69
FromW OF FM 762
To0.31 MI W OF FM 2759
CSJ0027-12-097
Proj IDNH 1402(081)
Work TypeGR, STRS, BASE, PAVE & HOV LNS
 
4.271155200552.60162397409.5099.9
CountyFORT BEND
HighwayIH 69
FromFM 762 EAST
ToFM 762 WEST
CSJ0027-12-137
Proj IDSTP 2011(256)TE
Work TypeENHANCEMENT PROJECT
 
0.001535282.30138381.0025.8
CountyFORT BEND
HighwayIH 69
FromAT FM 762
To.
CSJ0027-12-144
Proj IDNH 1402(081)
Work TypeINTERSECTION IMPROVEMENTS
 
0.001293400.00426995.0399.9
Work Order09-23-14
Work Began09-23-14
Work Completed
Time Computed10-09-14
Contract Working Days1,045
Addl Days Granted0
Working Days Charged1,045
Percent Time Used100
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0027-12-097
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.71)
PROFESSIONAL TRAFFIC CONTROL, LLC (0.48)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (3.63)
INDUS CONSTRUCTION, L.P. (12.04)
BUILDER SERVICES CO. (0.10)
QUALITY TURF GRASS (1.46)
WASTE PARTNERS OF TEXAS, INC (0.05)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.24)
BASE CONSTRUCTION (0.45)
BORTUNCO (0.18)
BAY CITY TRAFFIC (0.10)
BATTEN DRILLING, INC. (0.10)
RAY"S THREADING AND FAB SHOP (0.58)
SCOTT DERR PAINTING CO, LLC (0.02)
YELLOWSTONE LANDSCAPE - CENTRAL, INC. (0.08)
WEST TEXAS ROCK RESOURCES, LLC (0.02)
ESSARY, HART & MACWILLIAM, INC. (0.00)
PINNACLE GRINDING AND GROOVING LLC (0.00)
Contract #08143201
Totals156029234.90107981.37162962785.5399.9

CountyFORT BEND
HighwayUS 59
FromW OF SH 36
ToW OF FM 762
CSJ0027-12-105
Proj IDNH 2014(211)
Work TypeWIDEN TO 6 LN RURAL FW, GRD SEP, IT
 
7.350133473457.87147536824.6099.9
CountyFORT BEND
HighwayUS 59
FromW OF SH 36
ToW OF FM 762
CSJ0027-12-126
Proj IDRW 27-12-126
Work TypeROW ACQUISITION
 
0.0011758017.201668692.6694.9
CountyFORT BEND
HighwayUS 59
FromSP 10
ToW OF SH 36
CSJ0027-12-127
Proj IDRW 27-12-127
Work TypeROW ACQUISITION
 
0.001637063.65718758.9599.9
Work Order02-27-14
Work Began04-17-14
Work Completed
Time Computed04-17-14
Contract Working Days1,079
Addl Days Granted880
Working Days Charged1,814
Percent Time Used92
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0027-12-105
BATTERSON,LLP (0.99)
CREACOM, INC. (5.17)
BASE CONSTRUCTION, L.L.P. (7.01)
WILLOW CITY SIGN & RAIL, INC. (1.04)
ESSARY, HART & MACWILIAM,INC. (11.23)
QUALITY TURF GRASS (1.47)
CPAVE, INC. (0.29)
TEXAS HIGHWAY WALLS (3.69)
HOUSTON SAWING & DRILLING (0.03)
SCOTT DERR PAINTING CO, LLC (0.01)
BUILDER SERVICES CO. (0.46)
BORTUNCO (0.82)
WASTE PARTNERS OF TEXAS, INC (0.02)
DRILL TECH DRILLING & SHORING, INC. (5.87)
RAY"S THREADING AND FAB SHOP (0.98)
TEXAS CUTTING & CORING GP, INC. (0.02)
WEST TEXAS ROCK RESOURCES, LLC (0.06)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.00)
PINNACLE GRINDING AND GROOVING LLC (0.00)
MESA ROD BUSTERS, INC. (0.11)
Contract #01143001
Totals135868538.72950623.71149924276.2199.9

CountyFORT BEND
HighwayIH 69
FromEAST OF SS 529
ToSH 99
CSJ0027-12-152
Proj IDC 27-12-152
Work TypeCORRIDOR TRAFFIC MANAGEMENT
 
22.5463151614.40388895.0012.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-14-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days450
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0027-12-152
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12203204
Totals3151614.400.00388895.0012.3

CountyFORT BEND
HighwayIH 69
FromAT OYSTER CREEK
To.
CSJ0027-12-158
Proj IDC 27-12-158
Work TypeBRIDGE REPLACEMENT
 
0.0535893966.50547270.059.2
Work Order10-11-22
Work Began00-00-00
Work Completed
Time Computed12-10-22
Contract Working Days367
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NBG CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0027-12-158
PRIMATE CONSTRUCTION, LP (0.12)
ARCOSA LWS, LLC (1.46)
BATTERSON, LLP (2.38)
SCOTT DERR PAINTING CO, LLC (0.36)
THIRD COAST SERVICES LLC (2.62)
LONESTAR TRAFFIC SAFETY, LLC (0.21)
MESA ROD BUSTERS, INC. (0.41)
HOUSTON SAWING & DRILLING (0.82)
Contract #09223211
Totals5893966.50547270.05547270.059.2

CountyFORT BEND
HighwayIH 69
FromBRAZOS CANYON DIVE
ToWRIGHT ROAD
CSJ0027-12-159
Proj IDC 27-12-159
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
8.2571099756.21980854.6289.1
Work Order09-29-21
Work Began11-05-21
Work Completed
Time Computed10-29-21
Contract Working Days90
Addl Days Granted30
Working Days Charged120
Percent Time Used100
Contractor(s)
GREEN SAGE SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0027-12-159
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213045
Totals1099756.2124190.30980854.6289.1

CountyFORT BEND
HighwayIH 69
From0.094 MILES WEST OF READING ROAD
ToGREATWOOD PARKWAY
CSJ0027-12-166
Proj IDC 27-12-166
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
5.560800573.420.000.0
Work Order10-19-22
Work Began00-00-00
Work Completed
Time Computed11-18-22
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0027-12-166
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09223018
Totals800573.420.000.000.0

CountyHARRIS
HighwayIH 69
FromFORT BEND C/L
ToSOUTH OF BISSONNET
CSJ0027-13-212
Proj IDNH 2019(365)
Work TypeUPGRADE HIGH MAST & UNDERPASS LIGHT
 
4.5224728767.667336832.7899.9
Work Order03-19-19
Work Began07-31-19
Work Completed
Time Computed07-17-19
Contract Working Days220
Addl Days Granted229
Working Days Charged337
Percent Time Used75
Contractor(s)
SICE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0027-13-212
SPECIALTY DRILLING, LTD. (9.42)
JMHP, INC. (1.15)
DORAN STEEL, INC. (0.48)
SIGNAL SERVICES GROUP INC. (9.40)
VACA UNDERGROUND UTILITIES INC (3.85)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (1.19)
POWER LINE SOLUTIONS, INC. (2.14)
ALTUS CONSTRUCTION LLC (2.79)
SPECIALTY DRILLING, LLC (9.42)
Contract #02193009
Totals4728767.660.007336832.7899.9

CountyHARRIS
HighwayUS 90
FromIH 610 E
ToBW 8
CSJ0028-02-092
Proj IDNH 2018(415)
Work TypeINSTALL ITS EQUIPMENT & INFRASTRUC
 
6.4731782760.651629965.7691.4
Work Order05-29-18
Work Began06-28-18
Work Completed
Time Computed06-28-18
Contract Working Days375
Addl Days Granted0
Working Days Charged349
Percent Time Used93
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0028-02-092
SPECIALTY DRILLING, LLC (1.67)
Contract #04183016
Totals1782760.654209.601629965.7691.4

CountyHARRIS
HighwayUS 90
FromHUNTING BAYOU
ToLINDSTROM ROAD
CSJ0028-02-100
Proj IDC 28-2-100
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
32.5751486713.951742469.6899.9
Work Order07-20-20
Work Began09-09-20
Work Completed
Time Computed08-19-20
Contract Working Days135
Addl Days Granted0
Working Days Charged89
Percent Time Used65
Contractor(s)
TEXAS WALL & LANDSCAPE
SUBCONTRACTOR(S) FOR CCSJ: 0028-02-100
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06203011
Totals1486713.950.001742469.6899.9

CountyWALLER
HighwaySH 6
FromGRIMES COUNTY LINE
ToUS 290
CSJ0050-04-027
Proj IDC 50-4-27
Work TypeOVERLAY
 
8.0345294013.775845497.9499.9
Work Order03-12-21
Work Began07-26-21
Work Completed
Time Computed05-11-21
Contract Working Days138
Addl Days Granted0
Working Days Charged195
Percent Time Used141
Contractor(s)
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0050-04-027
WILLOW CITY SIGN & RAIL, INC. (3.22)
F. N. PLOCH CONSTRUCTION COMPANY, INC. (16.74)
PINNACLE GRINDING AND GROOVING LLC (0.19)
ASE CONTRACTORS LLC (2.34)
HIGHWAY 1 LLC (8.26)
MPB, INC. (0.40)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (2.45)
J & M CONTRACTING, COMPANY (1.38)
Contract #02213207
Totals5294013.772587.205845497.9499.9

CountyWALLER
HighwayBU 290H
FromSH 6
ToHARRIS COUNTY LINE
CSJ0050-05-067
Proj IDSTP 2020(593)
Work TypeOVERLAY
 
10.9995433536.706170674.4099.9
Work Order04-28-20
Work Began09-09-20
Work Completed
Time Computed06-29-20
Contract Working Days135
Addl Days Granted20
Working Days Charged155
Percent Time Used100
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0050-05-067
TOTAL HIGHWAY MAINTENANCE, LLC (6.25)
LONESTAR TRAFFIC SAFETY, LLC (0.26)
BATTERSON, LLP (0.30)
THIRD COAST SERVICES LLC (4.05)
WILLOW CITY SIGN & RAIL, INC. (6.06)
TEXOP CONSTRUCTION (3.36)
R & A TRANSPORT, INC. (2.13)
AVILES CONSTRUCTION SERVICE, INC (1.23)
Contract #02203007
Totals5433536.700.006170674.4099.9

CountyHARRIS
HighwayUS 290
FromWEST OF BADTKE
ToMUESCHKE
CSJ0050-06-089
Proj IDC 50-6-89
Work TypeCORRIDOR TRAFFIC MANAGEMENT
 
1371760.050.000.0
CountyHARRIS
HighwayUS 290
FromWALLER COUNTY LINE
ToWEST OF BADTKE RD
CSJ0114-12-014
Proj IDC 114-12-14
Work TypeCORRIDOR TRAFFIC MANAGEMENT
 
935785.260.000.0
Work Order09-15-22
Work Began00-00-00
Work Completed
Time Computed10-15-22
Contract Working Days270
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0050-06-089
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08223211
Totals2307545.310.000.000.0

CountyHARRIS
HighwayBU 290H
From0.25 MI NW OF KICKAPOO RD
To0.25 MI SE OF KICKAPOO RD
CSJ0050-06-094
Proj IDSTP 2021(331)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.50078734.4073464.0093.3
Work Order06-17-21
Work Began06-06-22
Work Completed
Time Computed07-17-21
Contract Working Days90
Addl Days Granted0
Working Days Charged38
Percent Time Used42
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0050-06-094
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05213236
Totals78734.400.0073464.0093.3

CountyHARRIS
HighwayUS 290
FromFM 529
ToWEST OF IH 610
CSJ0050-09-095
Proj IDNH 1902(173)
Work TypeLSE
 
7.1191648298.342651742.9699.9
Work Order08-13-19
Work Began03-16-20
Work Completed
Time Computed09-12-19
Contract Working Days135
Addl Days Granted0
Working Days Charged135
Percent Time Used100
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0050-09-095
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193025
Totals1648298.3417437.232651742.9699.9

CountyHARRIS
HighwaySH 3
FromRICHEY ST S
ToGALVESTON C/L
CSJ0051-02-101
Proj IDSTP 2019(765)TAP
Work TypeADD BIKES LNS
 
13.26613218969.8613575500.3899.9
CountyGALVESTON
HighwaySH 3
FromHARRIS C/L
ToFM 518
CSJ0051-03-109
Proj IDSTP 2019(765)TAP
Work TypeADD BIKE LANES
 
1.072732989.74621296.8484.7
Work Order05-14-19
Work Began07-22-19
Work Completed
Time Computed06-13-19
Contract Working Days600
Addl Days Granted0
Working Days Charged626
Percent Time Used104
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0051-02-101
PROFESSIONAL TRAFFIC CONTROL LLC (6.69)
WILLOW CITY SIGN & RAIL, INC. (1.56)
GREEN SAGE SERVICES LLC (4.37)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (4.72)
Contract #04193218
Totals13951959.600.0014196797.2299.9

CountyHARRIS
HighwaySH 3
FromSOUTH RICHEY STREET
ToGALVESTON COUNTY LINE
CSJ0051-02-108
Proj IDSTP 2022(405)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
14.5865450259.59279991.255.1
Work Order04-19-22
Work Began08-03-22
Work Completed
Time Computed05-19-22
Contract Working Days223
Addl Days Granted0
Working Days Charged149
Percent Time Used66
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0051-02-108
GMJ PAVING CO. (17.46)
TRAFFIC SIGNS & LINES, LLC (14.02)
SOUTHERN EROSION, LLC (2.54)
Contract #03223204
Totals5450259.592500.00279991.255.1

CountyGALVESTON
HighwaySH 3
FromN OF FM 1765
ToSH 146
CSJ0051-03-117
Proj IDC 51-3-117
Work TypeOVERLAY
 
2.9804384915.813468132.4079.0
Work Order03-24-22
Work Began05-14-22
Work Completed
Time Computed05-14-22
Contract Working Days150
Addl Days Granted0
Working Days Charged109
Percent Time Used72
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0051-03-117
QUALITY TURF FARMS, L.C. (0.26)
STRIPE LINES, INC. (4.27)
TRAF-TEX, INC. (11.28)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (0.87)
Contract #02223210
Totals4384915.81162532.573468132.4079.0

CountyGALVESTON
HighwaySH 3
FromHARRIS C/L
ToFM 646
CSJ0051-03-119
Proj IDSTP 2022(919)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.7001131153.800.000.0
Work Order09-20-22
Work Began10-20-22
Work Completed
Time Computed10-20-22
Contract Working Days357
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0051-03-119
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08223023
Totals1131153.800.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12