Monthly Local Let Maintenance Report For El Paso District As Of Nov 22, 2017 Page 4 Of 4

Last Update: Wednesday, November 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6317-16-001
Proj IDRMC - 631716001
Work TypeCULVERT CLEANING
 
200.000191988.5014752.307.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-02-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged31
Percent Time Used8
Contractor(s)
KEGLEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172403
Totals191988.5014752.3014752.307.6

CountyEL PASO
HighwayIH0010
FromEL PASO DISTRICT COMPLEX
ToEL PASO DISTRICT COMPLEX
CSJ6317-48-001
Proj IDSUP - 631748001
Work TypeJANITORIAL SERVICES
 
0.001346469.2814436.224.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-17
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged31
Percent Time Used4
Contractor(s)
TIBH INDUSTRIES, INC.
PCSI, INC
SUBCONTRACTOR(S) FOR CCSJ: 6317-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172432
Totals346469.2814436.2214436.224.1

CountyEL PASO
HighwayIH0010
FromEL PASO DISTRICT COMPLEX
ToEL PASO DISTRICT COMPLEX
CSJ6318-07-001
Proj IDSUP - 631807001
Work TypeLANDSCAPE MAINTENANCE SERVICES DHQ
 
1.00099600.0020750.0020.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-24-17
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged153
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL INDUSTRIES OF EL PASO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05172431
Totals99600.004150.0020750.0020.8

CountyHUDSPETH
HighwayUS0062
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6319-69-001
Proj IDRMC - 631969001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
215.00054651.00119389.8299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-18-17
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted48
Working Days Charged33
Percent Time Used30
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6319-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07172401
Totals54651.0082835.00119389.8299.9

CountyCULBERSON
HighwayUS0062
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6319-98-001
Proj IDRMC - 631998001
Work TypeMAINTENANCE PICNIC AREAS
 
93.00029406.751647.455.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-09-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged23
Percent Time Used6
Contractor(s)
A CUT ABOVE LAWN MAINTENANCE & SPRINKLER CO.
SUBCONTRACTOR(S) FOR CCSJ: 6319-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07172402
Totals29406.751647.451647.455.6

CountyPRESIDIO
HighwayUS0067
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6320-09-001
Proj IDRMC - 632009001
Work TypePICNIC AREA LITTER BARREL
 
300.00046979.080.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-17
Work Began10-01-17
Work Completed
Time Computed10-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MESA D CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6320-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07172403
Totals46979.080.000.000.0

CountyEL PASO
HighwaySL0375
FromSL 0375_TRANSMOUNTAIN
ToSL 0375_TRANSMOUNTAIN
CSJ6320-44-001
Proj IDRMC - 632044001
Work TypePICNIC AREA MAINTENANCE
 
6.00030000.083625.0012.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged44
Percent Time Used12
Contractor(s)
MESA D CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6320-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172404
Totals30000.082500.003625.0012.0

CountyBREWSTER
HighwayUS0067
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6320-61-001
Proj IDRMC - 632061001
Work TypePICNIC LITTER BARREL MAINTENANCE
 
300.00057317.504484.007.8
Work Order09-26-17
Work Began10-01-17
Work Completed
Time Computed10-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged31
Percent Time Used8
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6320-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172405
Totals57317.504484.004484.007.8

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6320-66-001
Proj IDRMC - 632066001
Work TypeCULVERT CLEANING
 
80.000230784.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KEGLEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6320-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172403
Totals230784.150.000.000.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6321-48-001
Proj IDRMC - 632148001
Work TypeCRACK SEALING
 
450.000268129.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged2
Percent Time Used2
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6321-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172416
Totals268129.800.000.000.0

CountyCULBERSON
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6321-61-001
Proj IDRMC - 632161001
Work TypeCRACK SEALING
 
260.000160531.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6321-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172411
Totals160531.200.000.000.0

CountyJEFF DAVIS
HighwayUS0090
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6321-62-001
Proj IDRMC - 632162001
Work TypeCRACK SEALING
 
290.000170928.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-23-17
Work Began00-00-00
Work Completed
Time Computed12-04-17
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6321-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172412
Totals170928.400.000.000.0

page 1 | page 2 | page 3 | page 4