Monthly State Let Construction Report For Fort Worth District As Of Aug 23, 2019 Page 1 Of 6

Last Update: Friday, August 23, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyZERO COUNTIES
Highway
From
To
CSJ0000-00-001
Proj ID
Work Type
 
0.0050.000.0
CountyTARRANT
HighwayVA
FromDISTRICTWIDE
ToVARIOUS LOCATIONS
CSJ0902-00-147
Proj IDSTP 2018(454)
Work TypeTRAFFIC SIGNALS
 
0.1001292000.001040290.6780.5
Work Order02-14-18
Work Began06-20-18
Work Completed
Time Computed06-14-18
Contract Working Days300
Addl Days Granted0
Working Days Charged150
Percent Time Used50
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0000-00-001
ROAD MASTER STRIPING LLC (2.02)
Contract #01183030
Totals1292000.007703.001040340.6780.5

CountyPARKER
HighwayIH 20
From450 FT WEST OF FM 5
To550 FT EAST OF FM 5
CSJ0008-03-089
Proj IDNH 1702(087)
Work TypeGRADING, PAVEMENT, STRIPING, & SIGN
 
0.1893921685.611679132.9642.8
Work Order09-21-17
Work Began01-07-19
Work Completed
Time Computed10-22-17
Contract Working Days192
Addl Days Granted63
Working Days Charged142
Percent Time Used55
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0008-03-089
BOWMAN ENGINEERING & CONSULTING, INC. (2.64)
RAMBO CONTRACTING, INC. (3.04)
MARCOM"S MOWING SERVICE, LLC (0.20)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.47)
FARR FOUNDATION, INC. (6.15)
DK CONTRACTING, LLC (0.65)
NORTHEASTERN PAVERS, INC. (7.16)
MICA CORPORATION (10.05)
TRP CONSTRUCTION GROUP, LLC (1.37)
DURABLE SPECIALTIES, INC. (5.60)
AAA DRILLING FOUNDATION CO., INC. (0.09)
Contract #08173237
Totals3921685.61162518.561679132.9642.8

CountyTARRANT
HighwaySH 180
FromWEST OF RIVERSIDE DRIVE
ToTIERNEY ROAD
CSJ0008-05-027
Proj IDC 8-5-27
Work TypeBASE RPR, MILL, OVERLAY, PAVMT MARK
 
3.5354223908.264683690.2499.9
CountyTARRANT
HighwaySH 180
FromTIERNEY RD
ToLOUISE ST
CSJ0008-06-051
Proj IDC 8-6-51
Work TypeBASE RPR, MILL, OVERLAY, PAVMT MARK
 
1.3681609857.101273731.5279.1
Work Order06-14-18
Work Began08-06-18
Work Completed
Time Computed07-15-18
Contract Working Days150
Addl Days Granted0
Working Days Charged156
Percent Time Used104
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-05-027
O. TREVINO CONSTRUCTION, LLC (17.09)
ALTUS TRAFFIC MANAGEMENT LLC (0.44)
DUSTROL, INC. (6.83)
TRP CONSTRUCTION GROUP, LLC (4.00)
BRENDA PRICE TRUCKING (0.49)
W.O.E. CONSTRUCTION (0.93)
PRIMATE CONSTRUCTION, INC. (1.00)
PEOPLEREADY, INC. (0.04)
CACTUS ENVIRONMENTAL SERVICES (0.03)
VANN/ELLI, INC. (1.08)
JUNIOR CONSTRUCTION COMPANY, INC. (0.25)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.13)
Contract #05183247
Totals5833765.3674140.845957421.7699.9

CountyTARRANT
HighwaySH 180
FromFIELDER RD
ToWEST 23RD ST
CSJ0008-07-035
Proj IDC 8-7-35
Work TypeBASE RPR, MILL, OVERLAY, PAVMT MARK
 
5.7246444576.452601088.3440.3
Work Order02-22-19
Work Began04-02-19
Work Completed
Time Computed03-24-19
Contract Working Days96
Addl Days Granted0
Working Days Charged79
Percent Time Used82
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0008-07-035
ALTUS TRAFFIC MANAGEMENT LLC (0.38)
MELS ELECTRIC, L.P. (8.31)
STRIPING TECHNOLOGY, L.P. (2.13)
O. TREVINO CONSTRUCTION, LLC (2.63)
W.O.E. CONSTRUCTION (14.21)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.65)
ALLIED DRILLING COMPANY (0.28)
BRENDA PRICE TRUCKING (0.00)
W.O.E. CONSTRUCTION (0.05)
SOUTHWEST CONSTRUCTION SERVICES (1.18)
SUPERIOR SERVICES (0.28)
Contract #01193250
Totals6444576.45428065.102601088.3440.3

CountyPARKER
HighwayFM 5
From6 MILES WEST OF FM 1187
ToNORTH OF FM 1187
CSJ0008-09-036
Proj IDC 8-9-36
Work TypeBASE RPR, OVERLAY, PAVMENT MARK
 
6.1652939418.334467333.8299.9
CountyPARKER
HighwayFM 5
FromIH 20
To4.8 MILES SOUTH OF IH 20
CSJ1469-01-019
Proj IDC 1469-1-19
Work TypeBASE RPR, OVERLAY, PAVMT MARK
 
4.8592072892.832398679.7799.9
Work Order07-31-18
Work Began11-19-18
Work Completed
Time Computed08-31-18
Contract Working Days192
Addl Days Granted0
Working Days Charged166
Percent Time Used86
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-09-036
TOTAL HIGHWAY MAINTENANCE, LLC (0.58)
VANN/ELLI, INC. (4.04)
JOSE SANTOS CONSTRUCTION COMPANY, INC. (1.33)
TRP CONSTRUCTION GROUP, LLC (3.92)
Contract #05183242
Totals5012311.161006445.516866013.5999.9

CountyTARRANT
HighwayIH 820 ETC
FromSH 121/SH 183 INTERCHANGE
ToRANDOL MILL ROAD
CSJ0008-13-221
Proj IDNH 2018(321)
Work TypeGR,DR,BS,STR,PAV,ITS,SGNL,ILLUM&SGN
 
8.944173724094.7467199999.3438.6
Work Order02-05-18
Work Began07-23-18
Work Completed
Time Computed06-06-18
Contract Working Days1,126
Addl Days Granted0
Working Days Charged303
Percent Time Used26
Contractor(s)
FLATIRON CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-13-221
VENUS CONSTRUCTION (3.22)
ATS DRILLING, L.P. (2.65)
DUSTROL, INC. (0.32)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09)
SOUTH TEXAS PAINTING CONTRACTORS (0.26)
STRUCTURAL TECHNOLOGIES, LLC (0.15)
TOTAL HIGHWAY MAINTENANCE, LLC (0.46)
STORM WATER MANAGEMENT, INC. (0.14)
ADF EXCAVATION, LLC (0.13)
ANTIGO CONSTRUCTION, INC. (0.02)
PANIOLO CONSTRUCTION SERVICES, LLC (0.62)
MICA CORPORATION (5.07)
PREMIER PAVING, LTD. (9.90)
ALTUS TRAFFIC MANAGEMENT LLC (0.12)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.26)
OSCAR ORDUNO, INC. (2.38)
(INACTIVE)AR DANIEL CONSTRUCTION SERVICES, INC. (0.69)
EPCS ENVIRONMENTAL, LLC (0.53)
JE CASEY, LLC (0.24)
ROYAL REBAR (0.81)
LINDAMOOD DEMOLITION, INC. (0.02)
BREDA COMPANY, INC. (0.01)
DURABLE SPECIALTIES, INC. (0.41)
LAWN PATROL SERVICE INC. (0.19)
PROTEX EROSION CONTROL, LLC (0.14)
Contract #12173001
Totals173724094.743682738.9367199999.3438.6

CountyTARRANT
HighwayIH 20
From.62 MI W OF BU 287P
To.01 M N OF IH 820
CSJ0008-13-231
Proj IDSTP 2016(994)HES
Work TypeCONVERT MEDIAN BARRIER
 
0.7951187693.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-07-17
Work Began00-00-00
Work Completed
Time Computed03-10-17
Contract Working Days159
Addl Days Granted0
Working Days Charged67
Percent Time Used42
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-13-231
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08163044
Totals1187693.000.000.000.0

CountyTARRANT
HighwayIH 20
From.62 MI W OF BU 287P
To.01 MI N OF IH 820
CSJ0008-13-238
Proj IDSTP 2016(994)HES
Work TypeCONVERT MEDIAN BARRIER
 
0.6951033324.180.000.0
CountyTARRANT
HighwayVA
FromVARIOUS LOCATIONS ALONG IH 20,
ToIH 35W, US 287, IH 820
CSJ0902-90-115
Proj IDC 902-90-115
Work TypeSSCB INSTALLATION
 
0.4891062719.060.000.0
Work Order05-31-19
Work Began07-26-19
Work Completed
Time Computed06-30-19
Contract Working Days89
Addl Days Granted0
Working Days Charged9
Percent Time Used10
Contractor(s)
ALTUS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0008-13-238
ROAD SOLUTIONS L.L.C. (7.29)
Contract #04193022
Totals2096043.240.000.000.0

CountyTARRANT
HighwayIH 820
From.3 MILES N OF TEAM RANCH ROAD
To1.3 MILES S OF TEAM RANCH ROAD
CSJ0008-15-050
Proj IDC 8-15-50
Work TypeREPLACE WIRE/CONDUIT
 
2.900485156.99620056.55100.0
Work Order09-21-17
Work Began11-13-18
Work Completed08-19-19
Time Computed10-22-17
Contract Working Days120
Addl Days Granted0
Working Days Charged118
Percent Time Used98
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0008-15-050
TCB FOUNDATION DRILLERS, INC. (0.61)
Contract #08173219
Totals485156.990.00620056.55100.0

CountyTARRANT
HighwayIH 20
FromLUDE TEAM RANCH ROAD
ToALEDO ROAD
CSJ0008-16-046
Proj IDNH 1902(223)
Work TypeTCD
 
1.5181511128.670.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-13-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days171
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MICA CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0008-16-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193245
Totals1511128.670.000.000.0

CountyWISE
HighwayUS 81
FromUS 380
ToFM 730
CSJ0013-08-135
Proj IDNH 1902(224)
Work TypeOV
 
1170226.870.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-13-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0013-08-135
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193038
Totals1170226.870.000.000.0

CountyTARRANT
HighwayBU 287P
FromMINTON RD
ToPALOMINO DR
CSJ0013-10-086
Proj IDSTP 1902(225)
Work TypeLSE
 
1.245433943.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-16-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days95
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0013-10-086
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193054
Totals433943.750.000.000.0

CountyTARRANT
HighwayIH 35W
FromON MCPHERSON
ToAT IH 35W
CSJ0014-02-049
Proj IDSTP 1602(429)MM
Work TypeGR, DR, STRUC, AND PAVEMENT
 
0.1006093665.756551611.75100.0
Work Order11-22-16
Work Began01-19-17
Work Completed08-19-19
Time Computed12-23-16
Contract Working Days278
Addl Days Granted98
Working Days Charged393
Percent Time Used104
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0014-02-049
BUYERS BARRICADES, INC. (0.63)
COWBOY TRUCKING (1.20)
FORTSON CONTRACTING, INC. (0.82)
GJ SEEDING, LLC (0.54)
NORTH TEXAS CONTRACTING, INC. (22.97)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (2.36)
STAR OPERATIONS, INC. (7.81)
STRIPE-A-ZONE, INC. (0.46)
WOLFE CONSTRUCTION GROUP, INC. (0.60)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.18)
W.O.E. CONSTRUCTION (0.08)
CIP CONCRETE, LLC (0.22)
MCL CONTRACTING, LLC (0.27)
V.C. HUFF, L.L.C. (4.01)
TEXAS HIGHWAY PRODUCTS CORPORATION (0.06)
INTEGRATED ROADWAY SERVICES, INC. (0.08)
Contract #08163039
Totals6093665.752804.076551611.75100.0

CountyTARRANT
HighwayIH 35W
FromIH 20
ToSH 174
CSJ0014-02-051
Proj IDCM 2018(453)
Work TypeITS FIBER AND EQUIPMENT
 
7.8311657422.771415364.0885.3
CountyJOHNSON
HighwaySH 174
FromIH 35W
ToWICKER HILL DRIVE
CSJ0019-01-145
Proj IDNH 2018(498)
Work TypeINSTALL ITS FIBER & EQUIPMENT
 
4.211377160.98376083.7399.7
Work Order09-05-18
Work Began12-03-18
Work Completed
Time Computed12-05-18
Contract Working Days171
Addl Days Granted66
Working Days Charged158
Percent Time Used66
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0014-02-051
COLLIER SERVICES LLC (21.65)
DALLAS LITE AND BARRICADE, INC. (0.90)
DOUBLE S CONSTRUCTION (7.37)
TX DOWN UNDER CONSTRUCTION LLC (0.91)
BADGER DAYLIGHTING CORP. (0.56)
Contract #01183009
Totals2034583.754608.851791447.8188.0

CountyJOHNSON
HighwayIH 35W
FromCR 604
ToTARRANT C/L
CSJ0014-03-095
Proj IDNH 2018(892)
Work TypeCONC PAV RPR, MILL, OVERLAY, PAVMT
 
9.35110321476.863425636.0833.1
Work Order06-14-18
Work Began00-00-00
Work Completed
Time Computed07-16-18
Contract Working Days235
Addl Days Granted0
Working Days Charged76
Percent Time Used32
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0014-03-095
AREA WIDE PROTECTIVE, INC. (0.13)
ODUM SERVICES, LLC (4.18)
O. TREVINO CONSTRUCTION, LLC (7.72)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.15)
J & M CONTRACTING COMPANY (2.46)
DUSTROL, INC. (4.85)
STRIPING TECHNOLOGY, L.P. (3.17)
STRAIGHT LINE SAWING & SEALING, INC. (0.08)
JM YANEZ CONSTRUCTION, INC. (0.15)
W.O.E. CONSTRUCTION (0.32)
EAST TEXAS R&D SERVICES, INC. (2.24)
TRP CONSTRUCTION GROUP, LLC (0.10)
Contract #05183232
Totals10321476.861487498.343425636.0833.1

CountyJOHNSON
HighwayIH 35W
From0.501 MI. N OF BI 35V
To2.187 MI. S OF FM 3391
CSJ0014-03-100
Proj IDSTP 2019(934)HES
Work TypeIOI
 
4345364.380.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days192
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0014-03-100
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08193218
Totals4345364.380.000.000.0

CountyTARRANT
HighwayIH 35W
From@ HATTIE STREET
To.
CSJ0014-16-276
Proj IDBR 1802(187)
Work TypeUPGRADE BRIDGE & APPROACH RAILING
 
0.2141213542.001280375.1999.9
Work Order07-17-18
Work Began01-07-19
Work Completed
Time Computed08-17-18
Contract Working Days278
Addl Days Granted5
Working Days Charged225
Percent Time Used79
Contractor(s)
IOWA BRIDGE & CULVERT, LC
SUBCONTRACTOR(S) FOR CCSJ: 0014-16-276
SYNERGY SIGNS & SERVICES LLC (6.87)
BUYERS BARRICADES, INC. (3.64)
BEAN ELECTRICAL, INC. (0.37)
UNIVERSAL FENCE COMPANY, INC. (1.77)
(INACTIVE)COMEN ENTERPRISES LLC (0.56)
Contract #06183041
Totals1213542.0025327.051280375.1999.9

CountyTARRANT
HighwayUS 377
FromCOOK RANCH ROAD
ToUS 377 (BENBROOK BLVD)
CSJ0080-07-097
Proj IDC 80-7-97
Work TypeTRAFFIC SIGN INSTALLATION
 
0.001188385.20156396.4183.0
Work Order09-26-18
Work Began01-22-19
Work Completed
Time Computed12-26-18
Contract Working Days30
Addl Days Granted7
Working Days Charged35
Percent Time Used94
Contractor(s)
NEW WORLD CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0080-07-097
WG ENGINEERING & CONSTRUCTION, LLC (55.99)
STRIPING TECHNOLOGY, L.P. (4.67)
DALLAS LITE AND BARRICADE, INC. (2.51)
PRIME UTILITY CONSTRUCTION, L.L.C. (2.65)
Contract #08183218
Totals188385.2077411.41156396.4183.0

CountyHOOD
HighwayUS 377
FromAPPROX. 1.4 MI SOUTH OF SH 171
ToJOHNSON COUNTY LINE
CSJ0080-11-001
Proj IDNH 1802(546)
Work TypeGR, DR, STR, BS AND PAVEMENT
 
1.70046969449.35317736.000.6
CountyJOHNSON
HighwayUS 377
FromHOOD COUNTY LINE
ToAPPROX. 1.1 MI NORTH OF SH 171
CSJ0080-12-001
Proj IDSTP 1802(547)
Work TypeGR, DR, STR, BS AND PAVEMENT
 
1.80613744380.850.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-16-19
Work Began00-00-00
Work Completed
Time Computed08-14-19
Contract Working Days756
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0080-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08183002
Totals60713830.200.00317736.000.5

CountyTARRANT
HighwayUS 377
FromSH 183
ToNORTH OF ADAMS DR
CSJ0081-01-051
Proj IDNH 1902(356)
Work TypeOVERLAY
 
1311735.330.000.0
CountyTARRANT
HighwaySH 183
FromDECATUR AVE
ToUS 377
CSJ0094-01-040
Proj IDC 94-1-40
Work TypeOV
 
3.2152973743.040.000.0
CountyTARRANT
HighwaySH 183
FromSH 199
ToBU 287P
CSJ0094-05-066
Proj IDC 94-5-66
Work TypeOVERLAY
 
2151173.210.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days278
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0081-01-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08193049
Totals6436651.580.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6