Monthly Local Let Maintenance Report For Waco District As Of Aug 23, 2019 Page 1 Of 5

Last Update: Friday, August 23, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBOSQUE
HighwaySH0006
FromVARIOUS ROADWAYS IN BELL, CORYELL,
ToHAMILTON AND BOSQUE COUNTIES
CSJ6225-66-001
Proj IDRMC - 622566001
Work TypeMULTI-COUNTY PAVEMENT MARKINGS
 
0.010150375.00147830.1098.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-23-11
Work Began10-07-11
Work Completed
Time Computed10-10-11
Contract Working Days84
Addl Days Granted0
Working Days Charged50
Percent Time Used59
Contractor(s)
DEANGELO BROTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6225-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07110904
Totals150375.000.00147830.1098.3

CountyHILL
HighwaySH0171
FromSTATE MAINTAINED ROADWAYS
ToHILL COUNTY
CSJ6250-54-001
Proj IDRMC - 625054001
Work TypeMOWING ROW & LITTER PICKUP AND DISPOSAL
 
221.740209531.30214580.6099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-10-13
Work Began06-18-13
Work Completed
Time Computed06-18-13
Contract Working Days124
Addl Days Granted0
Working Days Charged68
Percent Time Used54
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6250-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12120904
Totals209531.300.00214580.6099.9

CountyFALLS
HighwaySH0007
FromVARIOUS ROADWAYS IN FALLS, LIMESTONE &
ToHILL COUNTIES
CSJ6288-93-001
Proj IDRMC - 628893001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.01046527.660.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days77
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
H. T. S. CONSTRUCTION ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07150903
Totals46527.660.000.000.0

CountyHAMILTON
HighwaySH0006
FromVARIOUS ROADWAYS IN BOSQUE, CORYELL,
ToAND HAMILTON COUNTIES
CSJ6288-94-001
Proj IDRMC - 628894001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.01047693.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days89
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
H. T. S. CONSTRUCTION ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07150901
Totals47693.000.000.000.0

CountyFALLS
HighwayUS0077
FromVAR ROADWAYS IN FALLS, BOSQUE, HILL,
ToCORYELL, HAMILTON & LIMESTONE COUNTIES
CSJ6292-57-001
Proj IDRMC - 629257001
Work TypeCLEANING AND SWEEING HIGHWAYS
 
0.010144625.8024753.49100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-07-15
Work Began12-09-15
Work Completed04-30-18
Time Computed12-09-15
Contract Working Days220
Addl Days Granted0
Working Days Charged52
Percent Time Used23
Contractor(s)
H. T. S. CONSTRUCTION ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09150902
Totals144625.800.0024753.49100.0

CountyBELL
HighwaySH0036
FromVARIOUS ROADWAYS
ToIN BELL COUNTY
CSJ6295-41-001
Proj IDRMC - 629541001
Work TypeRURAL MOWING
 
0.100190640.00190130.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-11-16
Work Began06-06-16
Work Completed10-31-16
Time Computed06-01-16
Contract Working Days40
Addl Days Granted0
Working Days Charged23
Percent Time Used57
Contractor(s)
LONESTAR HAWK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150905
Totals190640.000.00190130.00100.0

CountyCORYELL
HighwaySH0036
FromVARIOUS ROADWAYS IN
ToCORYELL COUNTY
CSJ6295-42-001
Proj IDRMC - 629542001
Work TypeMOWING AND LITTER REMOVAL
 
0.100242481.24196626.36100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-27-16
Work Began06-13-16
Work Completed11-22-16
Time Computed06-13-16
Contract Working Days135
Addl Days Granted0
Working Days Charged91
Percent Time Used67
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6295-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150901
Totals242481.240.00196626.36100.0

CountyBELL
HighwaySL0363
FromVARIOUS ROADWAYS IN
ToBELL COUNTY
CSJ6295-50-001
Proj IDRMC - 629550001
Work TypeURBAN MOWING
 
0.100206108.04206108.0499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-11-16
Work Began06-06-16
Work Completed
Time Computed06-01-16
Contract Working Days75
Addl Days Granted0
Working Days Charged38
Percent Time Used50
Contractor(s)
LONESTAR HAWK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150903
Totals206108.040.00206108.0499.9

CountyMCLENNAN
HighwaySH0006
FromVAR RDWYS IN BELL, BOSQUE, FALLS, HIILL,
ToCORYELL, HAMILTON, LIMESTONE, MCLENNAN
CSJ6297-29-001
Proj IDRMC - 629729001
Work TypeLARGE SIGN MAINTENANCE (DISTRICT WIDE)
 
0.010176300.00591674.05100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-13-16
Work Began10-05-16
Work Completed09-01-18
Time Computed05-23-16
Contract Working Days365
Addl Days Granted335
Working Days Charged700
Percent Time Used100
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03160903
Totals176300.000.00591674.05100.0

CountyCORYELL
HighwaySH0009
FromINTERSECTION OF SH 9 AND
ToFM 116
CSJ6300-02-001
Proj IDRMC - 630002001
Work TypeTRAFFIC SIGNAL INSTALLATION
 
0.100196235.20200754.0499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-07-16
Work Began09-08-16
Work Completed
Time Computed05-31-16
Contract Working Days50
Addl Days Granted0
Working Days Charged46
Percent Time Used92
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04160902
Totals196235.200.00200754.0499.9

CountyFALLS
HighwaySH0007
FromVARIOUS ROADWAYS IN FALLS, HILL AND
ToLIMESTONE COUNTIES
CSJ6306-36-001
Proj IDRMC - 630636001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.01046343.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-05-18
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170902
Totals46343.100.000.000.0

CountyHAMILTON
HighwaySH0036
FromVARIOUS ROADWAYS IN BOSQUE,CORYELL,
To& HAMILTON COUNTIES
CSJ6306-37-001
Proj IDRMC - 630637001
Work TypeCLEANING & SWEEPING
 
0.01085083.680.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days148
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170903
Totals85083.680.000.000.0

CountyHILL
HighwaySH0081
FromVARIOUS
ToVARIOUS
CSJ6307-04-001
Proj IDSUP - 630704001
Work TypeLAWN AND GROUNDS MAINTENANCE
 
0.0109890.006150.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-16
Work Began09-01-16
Work Completed08-31-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160935
Totals9890.000.006150.00100.0

CountyCORYELL
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6307-12-001
Proj IDSUP - 630712001
Work TypePICNIC AREA MAINTENANCE
 
0.01047770.0039845.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-16
Work Began09-01-16
Work Completed08-31-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160942
Totals47770.000.0039845.00100.0

CountyHAMILTON
HighwayUS0281
FromVARIOUS
ToVARIOUS
CSJ6307-13-001
Proj IDSUP - 630713001
Work TypePICNIC AREA MAINTENANCE
 
0.01044370.0032375.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-16
Work Began09-01-16
Work Completed08-31-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160943
Totals44370.000.0032375.00100.0

CountyHILL
HighwaySH0081
FromVARIOUS
ToVARIOUS
CSJ6307-14-001
Proj IDSUP - 630714001
Work TypePICNIC AREA MAINTENANCE
 
0.01044300.0035905.0081.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160944
Totals44300.000.0035905.0081.0

CountyBELL
HighwaySL0121
FromVARIOUS ROADWAYS IN
ToBELL COUNTY
CSJ6307-19-001
Proj IDSUP - 630719001
Work TypeLITTER PICK UP AND DISPOSAL
 
0.01094581.0488125.0593.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160949
Totals94581.040.0088125.0593.1

CountyBELL
HighwaySL0121
FromVARIOUS
ToVARIOUS
CSJ6307-20-001
Proj IDSUP - 630720001
Work TypePICNIC AREA MAINTENANCE
 
0.01016550.0012320.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-16
Work Began09-01-16
Work Completed08-31-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160950
Totals16550.000.0012320.00100.0

CountyBELL
HighwayFM0438
FromBELL, BOSQUE AND
ToMCLENNAN COUNTIES
CSJ6319-13-001
Proj IDRMC - 631913001
Work TypeCRACK SEAL - COLD APPLICATION
 
0.010139694.80123623.09100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-11-17
Work Began12-21-17
Work Completed01-16-18
Time Computed12-18-17
Contract Working Days28
Addl Days Granted0
Working Days Charged8
Percent Time Used28
Contractor(s)
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6319-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170901
Totals139694.800.00123623.09100.0

CountyMCLENNAN
HighwaySS0299
FromSWEEP PORCHES/CLEAN HANDRAILS AT
ToTHE WACO DISTRICT COMPLEX
CSJ6322-05-001
Proj IDSUP - 632205001
Work TypeSWEEP PORCHES/CLEAN HANDRAILS
 
0.0105616.005238.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed08-31-18
Time Computed09-01-17
Contract Working Days104
Addl Days Granted0
Working Days Charged97
Percent Time Used93
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6322-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170950
Totals5616.000.005238.00100.0

page 1 | page 2 | page 3 | page 4 | page 5