Monthly State Let Construction Report For Abilene District As Of May 10, 2016 Page 2 Of 2

Last Update: Tuesday, May 10, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTAYLOR
Highway VA
From VARIOUS LOCATIONS IN KENT,SCURRY,
To STONEWALL,AND HASKELL COUNTIES
CSJ 0908-00-080
Proj ID NH 2016(677)
Work Type INSTALL HIGH MAST ILLUMINATION
 
1.000 448260.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-14-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0908-00-080
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163037
Totals 448260.50 0.00 0.00 0.0

CountyHOWARD
Highway VA
From RM 33
To IH 20
CSJ 0908-12-019
Proj ID BOR 2004(670)
Work Type CONSTRUCT NEW RELIEF ROUTE
 
8.456 44837998.95 1523041.56 46480126.43 99.9
Work Order 03-12-14
Work Began 07-21-14
Work Completed  
Time Computed 05-05-14
Contract Working Days 679
Addl Days Granted 0
Working Days Charged 472
Percent Time Used 69
Contractor(s)
SUNDT CONSTRUCTION, INC.
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0908-12-019
MJE, LLC (2.01%)
HARDY HOLE DRILLING(1.14%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.25%)
CMT ENGINEERING, INC.(0.11%)
MCL CONTRACTING, LLC (1.29%)
DUSTROL, INC.(0.95%)
OTTO TRUCKING, INC.(4.17%)
PENHALL COMPANY(0.03%)
DUSTIN ALLEN, INC. (0.27%)
WILLIS ELECTRIC CO., LP(0.61%)
DYNAMIC VISION CO., INC. (0.18%)
DIVERSIFIED HIGHWAY PRODUCTS AND SERVICES(0.06%)
ENERGY ELECTRIC SUPPLY, INC. (0.28%)
DOUBLE A CONTRACTING, L.P. (0.37%)
CRANE SERVICES, INC. (0.18%)
LONE STAR HIGHWAY PRODUCTS, INC. (4.86%)
SILVIO LOPEZ TRUCKING(0.49%)
VULCAN MATERIAL COMPANY_(ABILENE)(1.23%)
ROBERTO MENDOZA TRUCKING (0.39%)
MAX TRUCKING (0.19%)
P & S TRUCKING (0.09%)
LAREDO PAVING, INC.(0.11%)
CMT ENGINEERING, INC.(0.12%)
AARON CONCRETE CONTRACTORS, L.P. (0.10%)
GESCH CONTRACTING, INC.(0.00%)
INSTA TURF LAWNS (0.28%)
TEXOP CONSTRUCTION (0.02%)
Contract # 12133201
Totals 44837998.95 1523041.56 46480126.43 99.9

CountyFISHER
Highway CR
From ON CR 183
To AT ROUGH CREEK (PSN 1)
CSJ 0908-23-037
Proj ID BR 2013(724)
Work Type REHABILITATE BRIDGE AND APPROACHES
 
0.086 1781426.00 235029.60 1100372.94 100.0
Work Order 10-30-15
Work Began 01-04-16
Work Completed 05-05-16
Time Computed 12-30-15
Contract Working Days 152
Addl Days Granted 0
Working Days Charged 77
Percent Time Used 50
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-23-037
S&S BRIDGE PAINTING( 15.41%)
CONTRACTORS SERVICE COMPANY(0.35%)
MORRIS COUNTY CONTRACTORS, L.L.C.(4.20%)
Contract # 08153022
Totals 1781426.00 235029.60 1100372.94 100.0

CountyHOWARD
Highway FM 821
From FM 2183
To IH 20
CSJ 1156-02-021
Proj ID STP 2015(794)
Work Type SUBGR WIDN, FL BS, 2CST, STRS, SET, MBGF
 
11.542 9379399.55 491919.07 4439520.36 47.3
Work Order 05-19-15
Work Began 06-29-15
Work Completed  
Time Computed 06-19-15
Contract Working Days 256
Addl Days Granted 0
Working Days Charged 189
Percent Time Used 73
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1156-02-021
J.V. CONCRETE CONSTRUCTION (2.36%)
CONTRACTORS SERVICE COMPANY(0.28%)
HJC FARMS, INC.(2.54%)
BARRICADES UNLIMITED (2.68%)
Contract # 04153002
Totals 9379399.55 491919.07 4439520.36 47.3

CountySCURRY
Highway FM 1606
From SH 350
To SH 208
CSJ 1526-02-009
Proj ID STP 1502(293)
Work Type SUBGR WIDEN, FL BS, STRS, 2CST, MBGF
 
7.101 6584662.31 1167666.53 4375233.21 66.4
Work Order 08-24-15
Work Began 10-14-15
Work Completed  
Time Computed 10-14-15
Contract Working Days 194
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 62
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1526-02-009
W.S. CONSTRUCTION COMPANY(8.07%)
BARRICADES UNLIMITED (1.33%)
DUSTIN ALLEN, INC. (1.64%)
BLACK JACK ENERGY SERVICES ( 48.00%)
MURRAY CONSTRUCTION(0.68%)
CONTRACTORS SERVICE COMPANY(0.22%)
Contract # 06153058
Totals 6584662.31 1167666.53 4375233.21 66.4

CountySCURRY
Highway FM 1606
From SH 208
To US 84
CSJ 1526-03-015
Proj ID STP 2016(678)
Work Type SUBGR WIDEN, FL BS, STRS, 2CST, MBGF
 
9.330 6876410.35 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-19-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 228
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1526-03-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163233
Totals 6876410.35 0.00 0.00 0.0

CountySCURRY
Highway FM 1610
From BORDEN COUNTY LINE
To FM 1606
CSJ 1531-02-012
Proj ID STP 2016(679)
Work Type RESTORE AND WIDEN EXISTING ROADWAY
 
7.044 5397845.79 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-14-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1531-02-012
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163022
Totals 5397845.79 0.00 0.00 0.0

CountyHOWARD
Highway FM 846
From FM 669
To FM 1205
CSJ 1872-02-017
Proj ID STP 1502(216)
Work Type EMB, EXC, STRS, SET, SURF, MBGF
 
16.092 9519743.52 472537.13 1710271.77 17.9
Work Order 07-30-15
Work Began 11-16-15
Work Completed  
Time Computed 09-28-15
Contract Working Days 311
Addl Days Granted 0
Working Days Charged 86
Percent Time Used 27
Contractor(s)
SBBI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1872-02-017
BARRICADES UNLIMITED (3.62%)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (5.46%)
WEST TEXAS ROCK RESOURCES, LLC ( 10.51%)
Contract # 05153055
Totals 9519743.52 472537.13 1710271.77 17.9

CountySCURRY
Highway FM 1269
From APPROX 1 MILE S. OF GARZA CNTY LINE
To US 180
CSJ 1873-02-022
Proj ID STP 1302(042)
Work Type REHAB & WIDEN
 
16.020 4597730.26 3000.00 4622656.20 99.9
Work Order 02-13-15
Work Began 03-11-15
Work Completed  
Time Computed 03-01-15
Contract Working Days 240
Addl Days Granted 0
Working Days Charged 233
Percent Time Used 97
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1873-02-022
BARRICADES UNLIMITED (1.86%)
TEXAS ALTERNATIVE GRASSER, INC.(0.21%)
HJC FARMS, INC.(1.23%)
W.S. CONSTRUCTION COMPANY(7.93%)
BLACK JACK ENERGY SERVICES ( 39.53%)
Contract # 01153025
Totals 4597730.26 3000.00 4622656.20 99.9

CountyHOWARD
Highway FM 2230
From US 87
To FM 846
CSJ 2149-01-009
Proj ID STP 2013(765)
Work Type EXC, EMB, FL BS, STRS, 2 CRSE SURF TRT
 
10.965 6178220.66 394782.13 4533646.63 73.3
Work Order 04-02-15
Work Began 05-20-15
Work Completed  
Time Computed 06-01-15
Contract Working Days 331
Addl Days Granted 10
Working Days Charged 186
Percent Time Used 54
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2149-01-009
REECE CONSTRUCTION CO., INC. ( 26.62%)
GARY A. CRAIN, INC.(0.05%)
TEXAS SHAFTS, INC. (1.31%)
ALTUS TRAFFIC MANAGEMENT LLC (0.50%)
BARRICADES UNLIMITED (1.44%)
HJC FARMS, INC.(1.06%)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (2.05%)
SAENZ TRANSPORT, LLC (6.16%)
ARANDA"S TRUCKING(2.26%)
GONZALES DUMP TRUCK SERVICES (0.80%)
Contract # 02153010
Totals 6178220.66 394782.13 4533646.63 73.3

CountyMITCHELL
Highway FM 2836
From AT CHERRY CREEK
To .
CSJ 2331-01-014
Proj ID BR 2016(615)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.165 1445914.79 464922.84 698303.88 48.2
Work Order 02-10-16
Work Began 03-14-16
Work Completed  
Time Computed 03-14-16
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 62
Contractor(s)
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2331-01-014
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.75%)
WOLFE CONSTRUCTION GROUP, INC. (0.30%)
ALTUS TRAFFIC MANAGEMENT LLC (0.31%)
KLP COMMERCIAL, LLC(0.00%)
Contract # 12153044
Totals 1445914.79 464922.84 698303.88 48.2

CountyFISHER
Highway FM 2832
From AT ALKALI CREEK
To .
CSJ 2857-01-005
Proj ID BR 1502(568)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.068 678682.96 67462.47 393991.73 58.0
Work Order 11-12-15
Work Began 12-01-15
Work Completed  
Time Computed 12-08-15
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 69
Contractor(s)
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2857-01-005
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.76%)
PENHALL COMPANY(0.58%)
MARKS CRANE & RIGGING CO., LIMITED (0.88%)
WOLFE CONSTRUCTION GROUP, INC. (0.43%)
Contract # 08153220
Totals 678682.96 67462.47 393991.73 58.0

page 1 | page 2