Monthly State Let Construction Report For Abilene District As Of Feb 11, 2016 Page 2 Of 3

Last Update: Thursday, February 11, 2016
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyNOLAN
Highway US 84
From APPROX 1 MI NORTHWEST OF ROSCOE
To 5 MI EAST OF MITCHELL C/L(EBL ONLY)
CSJ 0053-12-057
Proj ID NH 2014(058)
Work Type RECONST, REALIGN, WIDN, STRS, SFTY & SURF
 
2.746 7054502.46 0.00 6726755.72 100.0
CountyNOLAN
Highway US 84
From NEAR FM 608
To MITCHELL COUNTY LINE (WBL ONLY)
CSJ 0053-12-062
Proj ID NH 2014(058)
Work Type 2" MILL & FILL DRIVING LN, 2" OVERL
 
8.670 4493543.14 0.00 5453870.36 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-23-14
Work Began 02-28-14
Work Completed 12-21-15
Time Computed 02-08-14
Contract Working Days 196
Addl Days Granted 81
Working Days Charged 339
Percent Time Used 122
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0053-12-057
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.03%)
CONTRACTORS SERVICE COMPANY(0.41%)
DOUBLE A CONTRACTING, L.P. (0.76%)
HJC FARMS, INC.(0.50%)
NOBLES ROAD CONSTRUCTION, INC. ( 24.30%)
REECE CONSTRUCTION CO., INC. (3.05%)
WEST TEXAS RUMBLE STRIP(0.15%)
TEX OP CONSTRUCTION, LP(0.98%)
VULCAN MATERIAL COMPANY_(ABILENE)( 49.90%)
P & S TRUCKING (0.11%)
MAX TRUCKING (0.23%)
SILVIO LOPEZ TRUCKING(0.57%)
ROBERTO MENDOZA TRUCKING (0.46%)
Contract # 10133004
Totals 11548045.60 0.00 12180626.08 100.0

CountyNOLAN
Highway US 84
From IH 20
To APPROX 1 MILE NORTHWEST OF ROSCOE
CSJ 0053-12-063
Proj ID NH 2015(297)
Work Type PLANE, FL PAV STR RPR, ACP FILL & OV
 
3.369 2878480.41 20220.85 2937042.14 100.0
Work Order 01-22-15
Work Began 04-13-15
Work Completed 01-26-16
Time Computed 04-13-15
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 136
Percent Time Used 133
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0053-12-063
A BROTHERS MILLING, LLC(1.37%)
MPB, INC.(0.90%)
WEST TEXAS RUMBLE STRIP(0.36%)
BARRICADES UNLIMITED (2.63%)
HJC FARMS, INC.(2.69%)
CONTRACTORS SERVICE COMPANY(0.68%)
VULCAN MATERIAL COMPANY_(ABILENE)(3.41%)
Contract # 11143017
Totals 2878480.41 20220.85 2937042.14 100.0

CountyTAYLOR
Highway US 84 ETC
From Y" NORTHEAST OF TUSCOLA
To COLEMAN COUNTY LINE
CSJ 0054-01-030
Proj ID STP 2015(049)HESG
Work Type TEXTURIZE SHOULDERS (PROF PAV MRKS)
 
78.867 618928.60 0.00 623128.60 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-09-14
Work Began 03-24-15
Work Completed 06-05-15
Time Computed 03-16-15
Contract Working Days 32
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 81
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0054-01-030
RED SIXTEEN CONSTRUCTION, INC(1.22%)
Contract # 09143212
Totals 618928.60 0.00 623128.60 100.0

CountyHOWARD
Highway US 87
From MARTIN COUNTY LINE
To 4.929 MI E OF MARTIN C/L (NBL ONLY)
CSJ 0068-07-050
Proj ID NH 1502(194)
Work Type PLAN, UNDSL, SUPER PAVE, MBGF
 
28.052 12331796.40 831093.20 6522837.79 52.8
Work Order 06-16-15
Work Began 10-08-15
Work Completed  
Time Computed 10-05-15
Contract Working Days 126
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 49
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0068-07-050
BARRICADES UNLIMITED (1.52%)
CONTRACTORS SERVICE COMPANY(0.47%)
HJC FARMS, INC.(0.68%)
TEX OP CONSTRUCTION, LP(1.07%)
WEST TEXAS RUMBLE STRIP(0.30%)
Contract # 05153008
Totals 12331796.40 831093.20 6522837.79 52.8

CountySTONEWALL
Highway US 380 ETC
From 0.036 MI W OF FM 2211
To 0.346 MI E OF FM 2211
CSJ 0106-04-034
Proj ID STP 2016(672)HES
Work Type HIGH FRICT SURF TRT & PROF PAV MARK
 
2.117 695241.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AMERICAN CIVIL CONSTRUCTORS WEST COAST LLC
SUBCONTRACTOR(S) FOR CCSJ: 0106-04-034
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163016
Totals 695241.50 0.00 0.00 0.0

CountySTONEWALL
Highway SH 283 ETC
From US 380
To HASKELL COUNTY LINE
CSJ 0106-06-033
Proj ID STP 2015(546)
Work Type SEAL COAT
 
194.747 6122799.18 0.00 6152995.64 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-10-15
Work Began 05-18-15
Work Completed 10-12-15
Time Computed 03-13-15
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 95
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0106-06-033
FLATE LINE, INC. (8.34%)
RED SIXTEEN CONSTRUCTION, INC(0.40%)
Contract # 01153222
Totals 6122799.18 0.00 6152995.64 100.0

CountyJONES
Highway SH 6 ETC
From BU 277-G
To SHACKELFORD COUNTY LINE
CSJ 0107-01-036
Proj ID STP 2016(305)
Work Type SEAL COAT
 
225.805 5991840.62 214040.67 214040.67 3.5
Work Order 12-04-15
Work Began 00-00-00
Work Completed  
Time Computed 06-09-16
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0107-01-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153008
Totals 5991840.62 214040.67 214040.67 3.5

CountyCALLAHAN
Highway SH 36
From TAYLOR CO. LINE
To FM 603
CSJ 0181-02-029
Proj ID STP 2016(676)
Work Type PLAN, FLEX PAV STR RPR, SUPER PAV ACP
 
6.216 5388974.29 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 129
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0181-02-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163010
Totals 5388974.29 0.00 0.00 0.0

CountyNOLAN
Highway BS 70-G
From AVENUE B IN SWEETWATER
To IH 20
CSJ 0264-01-036
Proj ID STP 2013(372)
Work Type REHABILITATION, ACP, SIDEWALKS
 
1.287 6493251.00 0.00 6498115.87 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-20-13
Work Began 09-03-13
Work Completed 02-13-15
Time Computed 08-20-13
Contract Working Days 318
Addl Days Granted 0
Working Days Charged 299
Percent Time Used 94
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0264-01-036
DOUBLE A CONTRACTING, L.P. (0.44%)
KARMY CONSTRUCTION INC (4.04%)
WILLIS ELECTRIC CO., LP(4.46%)
HJC FARMS, INC.(0.35%)
DUSTROL, INC.(0.99%)
CONTRACTORS SERVICE COMPANY(0.69%)
Contract # 02133222
Totals 6493251.00 0.00 6498115.87 100.0

CountyTAYLOR
Highway US 277
From 5 MILES NORTH OF FM 89
To 2.6 MILES NORTH OF FM 1086
CSJ 0407-05-025
Proj ID STP 2016(008)HES
Work Type TEXTURIZE SHOULDERS / TEXTURING
 
27.351 192277.66 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-21-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0407-05-025
RED 16 CONSTRUCTION(6.43%)
Contract # 09153219
Totals 192277.66 0.00 0.00 0.0

CountyTAYLOR
Highway US 277
From FM 3438
To FM 707
CSJ 0407-06-040
Proj ID STP 1502(291)
Work Type PLAN, FL PAV STR RPR, SUPER PAV,
 
6.543 6510587.92 1051680.05 2844293.36 43.6
Work Order 07-31-15
Work Began 10-05-15
Work Completed  
Time Computed 08-31-15
Contract Working Days 109
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 49
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0407-06-040
DOUBLE A CONTRACTING, L.P. (1.24%)
ACU CONSTRUCTION LLC (1.32%)
SCR CONSTRUCTION CO., INC. (0.23%)
SIGNAL SERVICES GROUP, INC.(0.42%)
HJC FARMS, INC.(1.67%)
CONTRACTORS SERVICE COMPANY(0.19%)
PRIME ECO GROUP, INC.(0.61%)
Contract # 06153254
Totals 6510587.92 1051680.05 2844293.36 43.6

CountyCALLAHAN
Highway US 283
From SH 36
To COLEMAN COUNTY LINE
CSJ 0437-04-025
Proj ID STP 2014(266)
Work Type REWORKING BASE, FLEX BASE, & 2CST
 
10.616 4270742.32 195809.25 2604316.75 60.9
Work Order 07-18-14
Work Began 02-16-15
Work Completed  
Time Computed 02-01-15
Contract Working Days 157
Addl Days Granted 0
Working Days Charged 149
Percent Time Used 94
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0437-04-025
DOUBLE A CONTRACTING, L.P. (2.20%)
CONTRACTORS SERVICE COMPANY(0.48%)
RICE ENVIRONMENTAL SERVICES(0.38%)
PRIME ECO GROUP, INC.(1.03%)
WILLIS ELECTRIC CO., LP(0.04%)
Contract # 05143008
Totals 4270742.32 195809.25 2604316.75 60.9

CountyMITCHELL
Highway SH 208
From CR 633
To COKE COUNTY LINE
CSJ 0454-03-041
Proj ID STP 2016(372)
Work Type SPOT REPAIR, UNDERSEAL, 2" OV SP - D
 
5.319 2654056.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-21-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 56
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0454-03-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10153230
Totals 2654056.80 0.00 0.00 0.0

CountyHOWARD
Highway SH 176
From MARTIN COUNTY LINE
To APPROX 1 MILE EAST OF FM 2599
CSJ 0548-04-019
Proj ID STP 1502(193)
Work Type PLANE, CMT TRT BS, BRG RL, SUPER PAVE
 
5.450 8697657.95 1604284.52 8265177.57 95.0
Work Order 07-07-15
Work Began 07-13-15
Work Completed  
Time Computed 07-13-15
Contract Working Days 252
Addl Days Granted 0
Working Days Charged 125
Percent Time Used 49
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0548-04-019
CONTRACTORS SERVICE COMPANY(0.35%)
DOUBLE A CONTRACTING, L.P. (3.81%)
HJC FARMS, INC.(1.41%)
SCR CONSTRUCTION CO., INC. (2.22%)
TEX OP CONSTRUCTION, LP(1.34%)
HUDSON, INC. (0.12%)
Contract # 05153227
Totals 8697657.95 1604284.52 8265177.57 95.0

CountyHOWARD
Highway FM 669
From BORDEN COUNTY LINE
To 0.055 MILES NORTH OF CR 30
CSJ 0558-04-021
Proj ID STP 2016(010)HES
Work Type TEXTURIZE SHOULDERS (PROFILE PAVEME
 
17.458 130266.35 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-22-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0558-04-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09153023
Totals 130266.35 0.00 0.00 0.0

CountyTAYLOR
Highway FM 1235
From MERKEL CITY LIMIT
To CR 392
CSJ 0663-03-027
Proj ID STP 2015(789)HES
Work Type FL BS, REWK BS MATL, 2CST, CMP & SET
 
11.020 4552099.47 116903.15 808538.54 17.7
Work Order 06-08-15
Work Began 09-08-15
Work Completed  
Time Computed 09-07-15
Contract Working Days 280
Addl Days Granted 50
Working Days Charged 19
Percent Time Used 8
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0663-03-027
CONTRACTORS SERVICE COMPANY(1.01%)
DOUBLE A CONTRACTING, L.P. (2.37%)
HJC FARMS, INC.(2.91%)
BRENDA CONSTRUCTION( 11.84%)
Contract # 04153037
Totals 4552099.47 116903.15 808538.54 17.7

CountyTAYLOR
Highway FM 613
From FM 89 IN BUFFALO GAP
To 0.39 MILES WEST OF US 83 IN TUSCOLA
CSJ 0699-03-017
Proj ID STP 2013(951)
Work Type REHAB & WIDEN
 
7.051 2058772.50 0.00 2023339.18 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-10-13
Work Began 04-08-14
Work Completed 10-02-15
Time Computed 05-01-14
Contract Working Days 154
Addl Days Granted 0
Working Days Charged 240
Percent Time Used 155
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0699-03-017
O. TREVINO CONSTRUCTION, LLC ( 18.63%)
MURRAY CONSTRUCTION(3.38%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.00%)
CONTRACTORS SERVICE COMPANY(0.70%)
Contract # 08133258
Totals 2058772.50 0.00 2023339.18 100.0

CountyTAYLOR
Highway VA
From BI 20-M IN NOLAN COUNTY
To FM 700, AND SH 350 IN HOWARD COUNTY
CSJ 0908-00-079
Proj ID NH 2015(793)
Work Type INS RD IL AM, DRILL SHAFT, ELEC CON
 
1.000 402151.50 375.00 396586.50 98.6
Work Order 05-21-15
Work Began 08-24-15
Work Completed  
Time Computed 08-20-15
Contract Working Days 89
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 47
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0908-00-079
CONTRACTORS SERVICE COMPANY(1.91%)
Contract # 04153224
Totals 402151.50 375.00 396586.50 98.6

CountyTAYLOR
Highway VA
From VARIOUS LOCATIONS IN KENT,SCURRY,
To STONEWALL,AND HASKELL COUNTIES
CSJ 0908-00-080
Proj ID NH 2016(677)
Work Type INSTALL HIGH MAST ILLUMINATION
 
1.000 448260.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0908-00-080
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163037
Totals 448260.50 0.00 0.00 0.0

CountyHOWARD
Highway VA
From RM 33
To IH 20
CSJ 0908-12-019
Proj ID BOR 2004(670)
Work Type CONSTRUCT NEW RELIEF ROUTE
 
8.456 44837998.95 2024767.46 40452959.92 90.2
Work Order 03-12-14
Work Began 07-21-14
Work Completed  
Time Computed 05-05-14
Contract Working Days 679
Addl Days Granted 0
Working Days Charged 406
Percent Time Used 59
Contractor(s)
SUNDT CONSTRUCTION, INC.
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0908-12-019
MJE, LLC (2.01%)
HARDY HOLE DRILLING(1.14%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.25%)
CMT ENGINEERING, INC.(0.11%)
MCL CONTRACTING, LLC (1.29%)
DUSTROL, INC.(0.95%)
OTTO TRUCKING, INC.(4.17%)
PENHALL COMPANY(0.03%)
DUSTIN ALLEN, INC. (0.27%)
WILLIS ELECTRIC CO., LP(0.61%)
DYNAMIC VISION CO., INC. (0.18%)
DIVERSIFIED HIGHWAY PRODUCTS AND SERVICES(0.06%)
ENERGY ELECTRIC SUPPLY, INC. (0.28%)
DOUBLE A CONTRACTING, L.P. (0.37%)
CRANE SERVICES, INC. (0.18%)
LONE STAR HIGHWAY PRODUCTS, INC. (4.86%)
SILVIO LOPEZ TRUCKING(0.49%)
VULCAN MATERIAL COMPANY_(ABILENE)(1.23%)
ROBERTO MENDOZA TRUCKING (0.39%)
MAX TRUCKING (0.19%)
P & S TRUCKING (0.09%)
LAREDO PAVING, INC.(0.11%)
CMT ENGINEERING, INC.(0.12%)
AARON CONCRETE CONTRACTORS, L.P. (0.10%)
GESCH CONTRACTING, INC.(0.00%)
Contract # 12133201
Totals 44837998.95 2024767.46 40452959.92 90.2

page 1 | page 2 | page 3