Monthly State Let Construction Report For Abilene District As Of Jul 12, 2016 Page 2 Of 2

Last Update: Tuesday, July 12, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountySCURRY
Highway FM 1606
From SH 350
To SH 208
CSJ 1526-02-009
Proj ID STP 1502(293)
Work Type SUBGR WIDEN, FL BS, STRS, 2CST, MBGF
 
7.101 6584662.31 542726.36 5337000.22 81.0
Work Order 08-24-15
Work Began 10-14-15
Work Completed  
Time Computed 10-14-15
Contract Working Days 194
Addl Days Granted 0
Working Days Charged 154
Percent Time Used 79
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1526-02-009
W.S. CONSTRUCTION COMPANY(8.07%)
BARRICADES UNLIMITED (1.33%)
DUSTIN ALLEN, INC. (1.64%)
BLACK JACK ENERGY SERVICES ( 48.00%)
MURRAY CONSTRUCTION(0.68%)
CONTRACTORS SERVICE COMPANY(0.22%)
Contract # 06153058
Totals 6584662.31 542726.36 5337000.22 81.0

CountySCURRY
Highway FM 1606
From SH 208
To US 84
CSJ 1526-03-015
Proj ID STP 2016(678)
Work Type SUBGR WIDEN, FL BS, STRS, 2CST, MBGF
 
9.330 6876410.35 637262.48 1184677.38 17.2
Work Order 04-19-16
Work Began 05-09-16
Work Completed  
Time Computed 05-09-16
Contract Working Days 228
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 12
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1526-03-015
CONTRACTORS SERVICE COMPANY(0.33%)
DOUBLE A CONTRACTING (0.33%)
HJC FARMS, INC.(3.44%)
Contract # 02163233
Totals 6876410.35 637262.48 1184677.38 17.2

CountySCURRY
Highway FM 1610
From BORDEN COUNTY LINE
To FM 1606
CSJ 1531-02-012
Proj ID STP 2016(679)
Work Type RESTORE AND WIDEN EXISTING ROADWAY
 
7.044 5397845.79 41640.00 41640.00 0.7
Work Order 04-14-16
Work Began 00-00-00
Work Completed  
Time Computed 05-14-16
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 6
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1531-02-012
CONTRACTORS SERVICE COMPANY(0.49%)
BRENDA CONSTRUCTION(7.82%)
BARRICADES UNLIMITED (1.08%)
HJC FARMS, INC.(2.28%)
Contract # 02163022
Totals 5397845.79 41640.00 41640.00 0.7

CountyHOWARD
Highway FM 846
From FM 669
To FM 1205
CSJ 1872-02-017
Proj ID STP 1502(216)
Work Type EMB, EXC, STRS, SET, SURF, MBGF
 
16.092 9519743.52 506240.45 2314549.18 24.3
Work Order 07-30-15
Work Began 11-16-15
Work Completed  
Time Computed 09-28-15
Contract Working Days 311
Addl Days Granted 0
Working Days Charged 118
Percent Time Used 37
Contractor(s)
SBBI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1872-02-017
BARRICADES UNLIMITED (3.62%)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (5.46%)
WEST TEXAS ROCK RESOURCES, LLC ( 10.51%)
BRETT CONSTRUCTION COMPANY (0.43%)
Contract # 05153055
Totals 9519743.52 506240.45 2314549.18 24.3

CountyHOWARD
Highway FM 2230
From US 87
To FM 846
CSJ 2149-01-009
Proj ID STP 2013(765)
Work Type EXC, EMB, FL BS, STRS, 2 CRSE SURF TRT
 
10.965 6178220.66 57108.04 4825796.86 78.1
Work Order 04-02-15
Work Began 05-20-15
Work Completed  
Time Computed 06-01-15
Contract Working Days 331
Addl Days Granted 10
Working Days Charged 221
Percent Time Used 64
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2149-01-009
REECE CONSTRUCTION CO., INC. ( 26.62%)
GARY A. CRAIN, INC.(0.05%)
TEXAS SHAFTS, INC. (1.31%)
ALTUS TRAFFIC MANAGEMENT LLC (0.50%)
BARRICADES UNLIMITED (1.44%)
HJC FARMS, INC.(1.06%)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (2.05%)
SAENZ TRANSPORT, LLC (6.16%)
ARANDA"S TRUCKING(2.26%)
GONZALES DUMP TRUCK SERVICES (0.80%)
Contract # 02153010
Totals 6178220.66 57108.04 4825796.86 78.1

CountyMITCHELL
Highway FM 2836
From AT CHERRY CREEK
To .
CSJ 2331-01-014
Proj ID BR 2016(615)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.165 1445914.79 24347.50 1122808.38 79.0
Work Order 02-10-16
Work Began 03-14-16
Work Completed  
Time Computed 03-14-16
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 111
Percent Time Used 135
Contractor(s)
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2331-01-014
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.75%)
WOLFE CONSTRUCTION GROUP, INC. (0.30%)
ALTUS TRAFFIC MANAGEMENT LLC (0.31%)
KLP COMMERCIAL, LLC(2.55%)
RIO"S STEEL(0.62%)
HOUSTON SAWING & DRILLING(0.30%)
BARRICADES UNLIMITED (0.20%)
BICK"S CONSTRUCTION, INC.(1.11%)
Contract # 12153044
Totals 1445914.79 24347.50 1122808.38 79.0

CountyFISHER
Highway FM 2832
From AT ALKALI CREEK
To .
CSJ 2857-01-005
Proj ID BR 1502(568)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.068 678682.96 76091.16 603856.80 90.0
Work Order 11-12-15
Work Began 12-01-15
Work Completed  
Time Computed 12-08-15
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 84
Percent Time Used 116
Contractor(s)
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2857-01-005
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.76%)
PENHALL COMPANY(0.58%)
MARKS CRANE & RIGGING CO., LIMITED (0.88%)
WOLFE CONSTRUCTION GROUP, INC. (0.43%)
BICK"S CONSTRUCTION, INC.(2.16%)
BARRICADES UNLIMITED (0.90%)
Contract # 08153220
Totals 678682.96 76091.16 603856.80 90.0

page 1 | page 2