Monthly State Let Construction Report For Abilene District As Of Dec 10, 2014 Page 2 Of 2

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHOWARD
Highway VA
From RM 33
To IH 20
CSJ 0908-12-019
Proj ID BOR 2004(670)
Work Type CONSTRUCT NEW RELIEF ROUTE
 
8.456 44837998.95 642705.00 8409227.00 18.7
Work Order 03-12-14
Work Began 07-21-14
Work Completed  
Time Computed 05-05-14
Contract Working Days 679
Addl Days Granted 0
Working Days Charged 96
Percent Time Used 14
Contractor(s)
SUNDT CONSTRUCTION, INC.
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0908-12-019
MJE, LLC (2.01%)
HARDY HOLE DRILLING(1.14%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.15%)
CMT ENGINEERING, INC.(0.24%)
MCL CONTRACTING, LLC (1.29%)
DUSTROL, INC.(0.95%)
OTTO TRUCKING, INC.(4.17%)
PENHALL COMPANY(0.03%)
DUSTIN ALLEN, INC. (0.27%)
WILLIS ELECTRIC CO., LP(0.20%)
Contract # 12133201
Totals 44837998.95 642705.00 8409227.00 18.7

CountyMITCHELL
Highway CR
From ON CR 142
To AT THE COLORADO RIVER
CSJ 0908-21-016
Proj ID BR 2008(757)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.173 1272147.12 56199.62 328465.66 25.8
CountyMITCHELL
Highway CR
From 0.02 MILES NORTH CR 123
To AT NO NAME DRAW
CSJ 0908-21-019
Proj ID BR 2008(760)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.060 310822.15 35424.31 64058.44 20.6
Work Order 06-23-14
Work Began 10-24-14
Work Completed  
Time Computed 10-20-14
Contract Working Days 209
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 7
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-21-016
TWIN MOUNTAIN FENCE CO.(0.12%)
BARRICADES UNLIMITED (5.23%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.85%)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.21%)
MCL CONTRACTING, LLC (0.22%)
Contract # 04143228
Totals 1582969.27 91623.93 392524.10 24.7

CountyFISHER
Highway CR
From ON CR 153
To AT PLUM CREEK (PSN 1)
CSJ 0908-23-034
Proj ID BR 2013(642)
Work Type REPLACE BR AND APPRS
 
0.066 290974.50 -22631.52 60916.00 20.9
CountyFISHER
Highway CR
From ON CR 146
To AT BUFFALO CREEK (PSN 1)
CSJ 0908-23-035
Proj ID BR 2013(643)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.067 340532.50 147963.50 259207.18 76.1
CountyFISHER
Highway CR
From ON CR 119
To AT ALKALI CREEK (PSN 1)
CSJ 0908-23-036
Proj ID BR 2013(644)
Work Type REPLACE BR AND APPRS
 
0.063 237814.00 28380.00 28380.00 11.9
Work Order 06-20-14
Work Began 09-03-14
Work Completed  
Time Computed 09-03-14
Contract Working Days 215
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 24
Contractor(s)
ASHLAR CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0908-23-034
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.91%)
Contract # 05143039
Totals 869321.00 153711.98 348503.18 40.0

CountyJONES
Highway CR
From CR 201
To AT POST OAK CREEK (PSN 1)
CSJ 0908-24-048
Proj ID BR 2014(043)
Work Type REPLACE BRIDGE
 
0.095 376415.00 -5347.78 99549.07 26.4
CountyJONES
Highway CR
From ON CR 111
To AT CARTER CREEK
CSJ 0908-24-049
Proj ID BR 2014(044)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.063 242558.00 55036.00 187549.00 77.3
Work Order 07-02-14
Work Began 09-09-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 143
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 34
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-24-048
CONTRACTORS SERVICE COMPANY(0.99%)
TEXAS ALTERNATIVE GRASSER, INC.(2.18%)
DUSTIN ALLEN, INC. (5.15%)
Contract # 05143020
Totals 618973.00 49688.22 287098.07 46.3

CountyKENT
Highway FM 1081
From US 380
To DICKENS COUNTY LINE
CSJ 2329-02-015
Proj ID STP 2014(002)
Work Type WIDENING AND REHAB
 
17.284 5496256.20 287040.91 2526063.90 46.3
Work Order 01-06-14
Work Began 01-13-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 170
Addl Days Granted 0
Working Days Charged 190
Percent Time Used 111
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2329-02-015
E. DIAZ TRUCKING (3.48%)
DOUBLE A CONTRACTING, L.P. (1.64%)
DUSTIN ALLEN, INC. (0.58%)
BARRICADES UNLIMITED (0.79%)
Contract # 09133024
Totals 5496256.20 287040.91 2526063.90 46.3

CountyTAYLOR
Highway LP 322
From LYTLE CREEK
To NEAR MAPLE STREET
CSJ 2398-01-047
Proj ID C 2398-1-47
Work Type EXC, EMB, STRS, SURF, & SAFE LIGHT
 
2.254 4222065.15 54245.09 3657320.83 88.1
Work Order 10-17-13
Work Began 10-21-13
Work Completed  
Time Computed 10-21-13
Contract Working Days 137
Addl Days Granted 0
Working Days Charged 205
Percent Time Used 149
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 2398-01-047
ALTUS TRAFFIC MANAGEMENT LLC (0.57%)
WILLIS ELECTRIC CO., LP( 13.70%)
TEXAS ALTERNATIVE GRASSER, INC.(0.35%)
DETON, INC. DBA SLATON BROS., INC. (7.81%)
EARTH REINFORCEMENT SPECIALISTS(6.27%)
DUSTIN ALLEN, INC. (1.76%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.38%)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (0.70%)
Contract # 09133034
Totals 4222065.15 54245.09 3657320.83 88.1

CountyJONES
Highway FM 2404
From FM 605
To 0.803 MI N OF CR 410
CSJ 2474-01-006
Proj ID STP 2014(797)
Work Type WIDEN, FLEX BASE, AND SURF TRT
 
2.400 761253.38 221111.00 606953.50 79.7
Work Order 08-08-14
Work Began 09-02-14
Work Completed  
Time Computed 08-24-14
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 70
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2474-01-006
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143023
Totals 761253.38 221111.00 606953.50 79.7

CountyTAYLOR
Highway FM 2404
From JONES COUNTY LINE
To US 83/US 277 WEST FRONTAGE ROAD
CSJ 2474-02-008
Proj ID STP 2014(798)
Work Type FL PAV SPOT RPR, SUPER PAV
 
2.810 865076.58 83354.85 83354.85 9.6
Work Order 07-18-14
Work Began 11-10-14
Work Completed  
Time Computed 09-16-14
Contract Working Days 62
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 9
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2474-02-008
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143051
Totals 865076.58 83354.85 83354.85 9.6

page 1 | page 2