Monthly Local Let Maintenance Report For Amarillo District As Of Oct 14, 2014 Page 1 Of 2

Last Update: Tuesday, October 14, 2014
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPOTTER
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6191-59-001
Proj ID RMC - 619159001
Work Type LITTER PICKUP AND DISPOSAL
 
0.001 276000.00 0.00 424600.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-15-10
Work Began 04-05-10
Work Completed  
Time Computed 04-05-10
Contract Working Days 730
Addl Days Granted 790
Working Days Charged 1,487
Percent Time Used 97
Contractor(s)
ALL HANDS & DUKE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6191-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02100401
Totals 276000.00 0.00 424600.00 99.9

CountyDALLAM
Highway US0087
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6191-87-001
Proj ID RMC - 619187001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 305584.62 0.00 604524.72 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-05-10
Work Began 10-11-10
Work Completed  
Time Computed 10-20-10
Contract Working Days 154
Addl Days Granted 154
Working Days Charged 158
Percent Time Used 51
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6191-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05100405
Totals 305584.62 0.00 604524.72 99.9

CountyMOORE
Highway US0087
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6191-88-001
Proj ID RMC - 619188001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 289367.38 0.00 558483.97 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-04-10
Work Began 10-04-10
Work Completed  
Time Computed 10-04-10
Contract Working Days 146
Addl Days Granted 0
Working Days Charged 110
Percent Time Used 75
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6191-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05100406
Totals 289367.38 0.00 558483.97 99.9

CountyGRAY
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6191-93-001
Proj ID RMC - 619193001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 335852.72 0.00 663814.24 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-05-10
Work Began 10-11-10
Work Completed  
Time Computed 10-11-10
Contract Working Days 207
Addl Days Granted 207
Working Days Charged 235
Percent Time Used 56
Contractor(s)
3JB CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6191-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05100409
Totals 335852.72 0.00 663814.24 99.9

CountyPOTTER
Highway US0087
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6219-13-001
Proj ID RMC - 621913001
Work Type CLEANING & SWEEPING HIGHWAYS (4 COUNTIES)
 
0.001 278306.20 0.00 330401.53 99.9
Work Order 02-27-12
Work Began 03-05-12
Work Completed  
Time Computed 03-05-12
Contract Working Days 730
Addl Days Granted 730
Working Days Charged 940
Percent Time Used 64
Contractor(s)
PANHANDLE SWEEPING & MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6219-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12110402
Totals 278306.20 0.00 330401.53 99.9

CountyPOTTER
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6224-70-001
Proj ID RMC - 622470001
Work Type ON CALL STRIPING
 
0.001 292000.68 0.00 291224.78 99.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-07-11
Work Began 06-14-11
Work Completed  
Time Computed 06-15-11
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 6
Contractor(s)
TEXAS PANHANDLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6224-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05110404
Totals 292000.68 0.00 291224.78 99.7

CountyPOTTER
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6245-10-001
Proj ID RMC - 624510001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 175332.44 0.00 118771.18 67.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-03-12
Work Began 11-12-12
Work Completed  
Time Computed 11-12-12
Contract Working Days 72
Addl Days Granted 10
Working Days Charged 76
Percent Time Used 92
Contractor(s)
GORMAN OUTDOOR, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6245-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07120401
Totals 175332.44 0.00 118771.18 67.7

CountyRANDALL
Highway IH0027
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6245-11-001
Proj ID RMC - 624511001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 245032.00 0.00 234833.40 96.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-16-12
Work Began 10-18-12
Work Completed  
Time Computed 10-18-12
Contract Working Days 139
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 33
Contractor(s)
BERT WHITAKER
SUBCONTRACTOR(S) FOR CCSJ: 6245-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07120402
Totals 245032.00 0.00 234833.40 96.4

CountyPOTTER
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6252-37-001
Proj ID RMC - 625237001
Work Type TRAFFIC CONTROL
 
0.001 192016.50 0.00 75269.95 39.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-14-13
Work Began 01-21-13
Work Completed  
Time Computed 01-21-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 131
Percent Time Used 35
Contractor(s)
HIGHWAY TECHNOLOGIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6252-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12120401
Totals 192016.50 0.00 75269.95 39.1

CountyCARSON
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6256-24-001
Proj ID RMC - 625624001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 167010.00 0.00 83480.00 49.9
Work Order 08-27-13
Work Began 08-27-13
Work Completed  
Time Computed 08-27-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 370
Percent Time Used 50
Contractor(s)
COMMERCIAL SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6256-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03130403
Totals 167010.00 0.00 83480.00 49.9

CountyGRAY
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6257-98-001
Proj ID RMC - 625798001
Work Type ON CALL GUARDRAIL REPAIR
 
0.001 149550.00 0.00 66246.00 44.2
Work Order 10-24-13
Work Began 10-28-13
Work Completed  
Time Computed 10-28-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 308
Percent Time Used 42
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6257-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06130401
Totals 149550.00 0.00 66246.00 44.2

CountyMOORE
Highway US0087
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6258-92-001
Proj ID RMC - 625892001
Work Type ON CALL GUARDRAIL REPAIR
 
0.001 163788.30 0.00 56978.22 34.7
Work Order 11-04-13
Work Began 11-05-13
Work Completed  
Time Computed 11-05-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 326
Percent Time Used 44
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6258-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130401
Totals 163788.30 0.00 56978.22 34.7

CountyHUTCHINSON
Highway SH0152
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6259-24-001
Proj ID BPM - 625924001
Work Type MISC BRIDGE REPAIRS
 
0.001 219789.00 104333.50 149688.70 68.1
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 03-17-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 60
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6259-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130402
Totals 219789.00 104333.50 149688.70 68.1

CountyOCHILTREE
Highway SH0015
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6259-25-001
Proj ID RMC - 625925001
Work Type MILLING AND OVERLAY
 
0.001 298447.60 307044.38 307044.38 99.9
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 06-01-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 13
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04140403
Totals 298447.60 307044.38 307044.38 99.9

CountyPOTTER
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6259-27-001
Proj ID BPM - 625927001
Work Type MISC. BRIDGE REPAIRS
 
0.001 301428.50 0.00 341036.72 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-11-14
Work Began 00-00-00
Work Completed  
Time Computed 03-03-14
Contract Working Days 40
Addl Days Granted 23
Working Days Charged 63
Percent Time Used 100
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6259-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10130401
Totals 301428.50 0.00 341036.72 99.9

CountyRANDALL
Highway IH0027
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6259-28-001
Proj ID BPM - 625928001
Work Type MISC BRIDGE REPAIRS
 
0.001 279192.00 205235.40 267683.00 95.8
Work Order 07-08-14
Work Began 00-00-00
Work Completed  
Time Computed 07-21-14
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 85
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05140401
Totals 279192.00 205235.40 267683.00 95.8

CountyROBERTS
Highway SH0070
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6259-29-001
Proj ID BPM - 625929001
Work Type MISC BRIDGE REPAIRS
 
0.001 98192.00 0.00 133478.19 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-18-14
Work Began 00-00-00
Work Completed  
Time Computed 03-10-14
Contract Working Days 40
Addl Days Granted 47
Working Days Charged 41
Percent Time Used 47
Contractor(s)
DRS CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130401
Totals 98192.00 0.00 133478.19 99.9

CountyHANSFORD
Highway SH0015
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6259-37-001
Proj ID RMC - 625937001
Work Type RAILROAD CROSSING REMOVAL & REHAB
 
0.001 293001.80 0.00 382422.56 99.9
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 06-01-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 70
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04140402
Totals 293001.80 0.00 382422.56 99.9

CountyPOTTER
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6260-01-001
Proj ID RMC - 626001001
Work Type TRAFFIC CONTROL
 
0.001 196575.00 20900.00 245277.50 99.9
Work Order 07-17-13
Work Began 07-17-13
Work Completed  
Time Computed 07-17-13
Contract Working Days 365
Addl Days Granted 365
Working Days Charged 441
Percent Time Used 60
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6260-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06130403
Totals 196575.00 20900.00 245277.50 99.9

CountyPOTTER
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6261-83-001
Proj ID RMC - 626183001
Work Type MOWING HIGHWAY RIGHT OF WAY (URBAN)
 
0.001 336620.00 0.00 97770.00 29.0
Work Order 10-10-13
Work Began 11-04-13
Work Completed  
Time Computed 10-21-13
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 38
Percent Time Used 31
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130403
Totals 336620.00 0.00 97770.00 29.0

page 1 | page 2