Monthly Local Let Maintenance Report For Amarillo District As Of Jul 14, 2017 Page 2 Of 3

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyPOTTER
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6303-17-001
Proj IDRMC - 630317001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001149867.8367215.9244.8
Work Order00-00-00
Work Began12-05-16
Work Completed
Time Computed09-01-16
Contract Working Days44
Addl Days Granted44
Working Days Charged7
Percent Time Used7
Contractor(s)
BERT WHITAKER
SUBCONTRACTOR(S) FOR CCSJ: 6303-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05160404
Totals149867.830.0067215.9244.8

CountyOLDHAM
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6303-18-001
Proj IDRMC - 630318001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001202845.7692703.8845.7
Work Order00-00-00
Work Began12-13-16
Work Completed
Time Computed09-01-16
Contract Working Days86
Addl Days Granted86
Working Days Charged11
Percent Time Used6
Contractor(s)
BERT WHITAKER
SUBCONTRACTOR(S) FOR CCSJ: 6303-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05160403
Totals202845.760.0092703.8845.7

CountyPOTTER
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6303-65-001
Proj IDRMC - 630365001
Work TypeTRAFFIC CONTROL
 
0.001295000.00345878.7599.9
Work Order00-00-00
Work Began07-12-16
Work Completed
Time Computed07-12-16
Contract Working Days365
Addl Days Granted365
Working Days Charged354
Percent Time Used48
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6303-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160401
Totals295000.0044137.50345878.7599.9

CountyOLDHAM
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6303-93-001
Proj IDSUP - 630393001
Work TypePICNIC AREA MAINT.AND LITTER PICKUP
 
0.00163457.6861627.1797.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-16
Work Completed
Time Computed05-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04160420
Totals63457.680.0061627.1797.1

CountyOLDHAM
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6303-94-001
Proj IDSUP - 630394001
Work TypeSTATE USE SPOT LITTER PICKUP
 
0.0019909.249909.2499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-16
Work Completed
Time Computed05-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04160421
Totals9909.240.009909.2499.9

CountyRANDALL
HighwayFM1541
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6304-44-001
Proj IDSUP - 630444001
Work TypeSTATE USE JANITORIAL
 
0.00114904.6313501.3090.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05160420
Totals14904.630.0013501.3090.5

CountyRANDALL
HighwayIH0027
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6307-65-001
Proj IDSUP - 630765001
Work TypeDISTRICT OFFICE JANITORIAL SERVICE
 
0.00174226.0468597.1292.4
Work Order00-00-00
Work Began08-01-16
Work Completed
Time Computed08-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160420
Totals74226.045628.9268597.1292.4

CountyCARSON
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6307-66-001
Proj IDRMC - 630766001
Work TypeCLEANING & SWEEPING HIGHWAYS
 
0.00198949.6291110.6892.0
Work Order00-00-00
Work Began09-26-16
Work Completed
Time Computed09-26-16
Contract Working Days365
Addl Days Granted0
Working Days Charged277
Percent Time Used75
Contractor(s)
PANHANDLE SWEEPING & MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6307-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160401
Totals98949.6222643.6791110.6892.0

CountyPOTTER
HighwayIH0040
FromVARIOUS
To.
CSJ6308-19-001
Proj IDSUP - 630819001
Work TypeJANITORIAL AND GROUNDS
 
0.001335405.80138297.4641.2
Work Order08-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged303
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160402
Totals335405.8013783.80138297.4641.2

CountyPOTTER
HighwayUS0087
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6308-76-001
Proj IDSUP - 630876001
Work TypeSTATE USE LITTER PICKUP(LIDS)
 
0.00192692.1568342.9073.7
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6308-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160420
Totals92692.156834.2968342.9073.7

CountyRANDALL
HighwayUS0060
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6309-52-001
Proj IDSUP - 630952001
Work TypeSTATE USE JANITORIAL CANYON MAINT.
 
0.0019900.085879.6359.3
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160421
Totals9900.080.005879.6359.3

CountyCARSON
HighwayBI0040F
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6309-53-001
Proj IDSUP - 630953001
Work TypeSTATE USE JANITORIAL SERVICE GROOM
 
0.0019900.086668.81100.0
Work Order00-00-00
Work Began09-01-16
Work Completed05-17-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged259
Percent Time Used70
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160422
Totals9900.080.006668.81100.0

CountyPOTTER
HighwayUS0087
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6310-09-001
Proj IDSUP - 631009001
Work TypeSTATE USE DEBRIS PICKUP
 
0.001178250.00126500.0070.9
Work Order00-00-00
Work Began10-01-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09160420
Totals178250.0017250.00126500.0070.9

CountyCARSON
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6310-10-001
Proj IDSUP - 631010001
Work TypeSTATE USE PICNIC AREA MAINTENANCE
 
0.00145108.3247209.2899.9
Work Order00-00-00
Work Began10-04-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09160421
Totals45108.329859.4447209.2899.9

CountyGRAY
HighwayIH0040
FromPOTTER COUNTY LINE
ToWHEELER COUNTY LINE
CSJ6313-04-001
Proj IDSUP - 631304001
Work TypeSTATE USE DEBRIS PICKUP
 
0.00176800.0036800.0047.9
Work Order00-00-00
Work Began01-02-17
Work Completed
Time Computed01-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged180
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12160420
Totals76800.006400.0036800.0047.9

CountyDEAF SMITH
HighwayUS0385
FromHEREFORD MAINTENANCE
ToJANITORIAL
CSJ6315-51-001
Proj IDSUP - 631551001
Work TypeHEREFORD JANITORIAL
 
0.0015887.921497.0025.4
Work Order00-00-00
Work Began03-01-17
Work Completed
Time Computed03-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02170420
Totals5887.92374.251497.0025.4

CountyPOTTER
HighwayIH0040
FromSEE PLANS
ToSEE PLANS
CSJ6316-48-001
Proj IDRMC - 631648001
Work TypeON CALL GUARDRAIL/CABLE BARRIER REPAIR
 
0.001164787.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMARILLO RMT ENTERPRISES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06170401
Totals164787.500.000.000.0

CountyOLDHAM
HighwayIH0040
FromSEE PLANS
ToSEE PLANS
CSJ6317-35-001
Proj IDSUP - 631735001
Work TypePICNIC AREA/LITTER PICKUP
 
0.00163457.6810983.0617.3
Work Order00-00-00
Work Began05-01-17
Work Completed
Time Computed05-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04170420
Totals63457.685491.5310983.0617.3

CountyOLDHAM
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6317-36-001
Proj IDSUP - 631736001
Work TypeSTATE USE SPOT LITTER PICKUP
 
0.0019909.241651.5416.6
Work Order00-00-00
Work Began05-01-17
Work Completed
Time Computed05-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04170421
Totals9909.24825.771651.5416.6

CountyRANDALL
HighwaySL0335
FromAMARILLO AE OFFICE
ToE-WAY MAINTENANCE OFFICE
CSJ6319-08-001
Proj IDSUP - 631908001
Work TypeSTATE USE JANITORIAL SERVICE
 
0.00115202.682340.4415.3
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed06-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged30
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05170420
Totals15202.682340.442340.4415.3

page 1 | page 2 | page 3