Monthly State Let Construction Report For Atlanta District As Of Dec 10, 2014 Page 3 Of 3

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRISON
Highway CR
From ON CR 1114 AT DRAW
To .
CSJ 0919-03-050
Proj ID BR 2012(676)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.171 469994.95 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-14-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0919-03-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143020
Totals 469994.95 0.00 0.00 0.0

CountyHARRISON
Highway CR
From ON CR 2607 AT HARRISON BAYOU BRANCH
To .
CSJ 0919-03-051
Proj ID BR 2012(677)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.058 309840.45 20857.67 305509.97 98.6
Work Order 07-22-14
Work Began 09-03-14
Work Completed  
Time Computed 09-03-14
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 90
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0919-03-051
PANOLA SIGN & BARRICADE, INC.(0.96%)
ODUM SERVICES, L.P.(3.58%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.49%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 12.19%)
REDROD STEEL AND CABLE, LLC(0.49%)
Contract # 06143054
Totals 309840.45 20857.67 305509.97 98.6

CountyMARION
Highway CR
From ON CR 113CC AT BLACK CYPRESS CREEK
To .
CSJ 0919-22-019
Proj ID BR 2002(373)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.001 304786.50 0.00 333155.27 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-10-13
Work Began 06-13-14
Work Completed 09-16-14
Time Computed 12-09-13
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 33
Percent Time Used 45
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0919-22-019
DUSTIN ALLEN, INC. (2.91%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 10.67%)
REDROD STEEL AND CABLE, LLC(0.72%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.85%)
Contract # 09133226
Totals 304786.50 0.00 333155.27 100.0

CountyMARION
Highway CR
From ON CR 3306 AT HUNTS CREEK
To .
CSJ 0919-22-031
Proj ID BR 1102(243)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.059 231033.00 0.00 228056.18 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-10-14
Work Began 04-11-14
Work Completed 09-17-14
Time Computed 04-11-14
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 104
Contractor(s)
J.M. YANEZ CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0919-22-031
SOUTHWEST ENVIRONMENT SERVICES LLC (1.37%)
DUSTIN ALLEN, INC. (3.80%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.87%)
WILDER BROTHERS CONSTRUCTION, INC. (3.22%)
FRITCHER CONSTRUCTION SERVICES (3.02%)
Contract # 01143217
Totals 231033.00 0.00 228056.18 100.0

CountyTITUS
Highway FM 1402
From 1.2 MI N OF IH 30
To 1.8 MI N OF IH 30
CSJ 1384-01-021
Proj ID C 1384-1-21
Work Type GR, BASE, SURF & PM
 
0.622 1351578.66 17365.28 1225333.57 90.6
Work Order 01-17-14
Work Began 02-24-14
Work Completed  
Time Computed 03-01-14
Contract Working Days 95
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 52
Contractor(s)
TEXANA LAND & ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1384-01-021
BAHENA CONSTRUCTION CO.,INC. (9.74%)
GIST ENTERPRISES, INC. (1.45%)
LYON BARRICADE AND CONSTRUCTION CO.(0.76%)
SAMMY G. SMALLWOOD (0.50%)
STRIPING TECHNOLOGY, L.P.(4.23%)
TURF WORKZ (2.28%)
MOORE CONSTRUCTION, INC. (3.27%)
Contract # 10133211
Totals 1351578.66 17365.28 1225333.57 90.6

CountyPANOLA
Highway FM 1971
From SH 315
To RUSK COUNTY LINE
CSJ 1894-01-021
Proj ID STP 2014(447)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
9.589 591745.22 6449.00 543281.74 100.0
Work Order 03-25-14
Work Began 04-10-14
Work Completed 11-18-14
Time Computed 04-10-14
Contract Working Days 52
Addl Days Granted 5
Working Days Charged 55
Percent Time Used 96
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1894-01-021
PANOLA SIGN & BARRICADE, INC.(0.64%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.10%)
ODUM SERVICES, L.P.(3.05%)
Contract # 02143217
Totals 591745.22 6449.00 543281.74 100.0

CountyBOWIE
Highway FM 2253
From IH 30
To US 82
CSJ 2048-01-014
Proj ID STP 2014(596)
Work Type GRADING, BASE, SURFACING & PAV MARKS
 
0.383 2250079.40 0.00 292886.32 13.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-18-14
Work Began 08-18-14
Work Completed  
Time Computed 08-18-14
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2048-01-014
MAC TRANSPORTATION, LTD, L.L.P.(1.98%)
STRIPING TECHNOLOGY, L.P.(1.08%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.98%)
ODUM SERVICES, L.P.(1.02%)
PANOLA SIGN & BARRICADE, INC.(0.23%)
N-LINE TRAFFIC MAINTENANCE, L.P. (2.12%)
RICK HARGROVE TRUCKING (1.98%)
Contract # 04143206
Totals 2250079.40 0.00 292886.32 13.0

CountyBOWIE
Highway FM 3287
From END OF MAINTENANCE
To FM 989
CSJ 2050-02-002
Proj ID STP 2014(795)HES
Work Type CONSTRUCT PAVED SHOULDERS
 
1.324 358934.38 605.00 374145.64 99.9
Work Order 06-16-14
Work Began 08-04-14
Work Completed  
Time Computed 08-04-14
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 38
Percent Time Used 76
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2050-02-002
BANNER SIGN & BARRICADE, INC. (HOOKS)(0.69%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.93%)
SAMMY G. SMALLWOOD (2.81%)
TOTAL HIGHWAY MAINTENANCE, LLC (4.49%)
TEXARKANA CONSTRUCTION COMPANY, INC. (4.42%)
RED RIVER HYDRO-SEEDING, INC.(0.86%)
Contract # 05143041
Totals 358934.38 605.00 374145.64 99.9

CountyUPSHUR
Highway FM 3245
From US 259
To SH 154
CSJ 3344-03-003
Proj ID STP 2014(793)HES
Work Type CONSTRUCT PAVED SHOULDERS
 
1.994 527788.66 44637.50 265305.95 50.2
Work Order 07-18-14
Work Began 09-02-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 32
Contractor(s)
H. H. HOWARD & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3344-03-003
DUSTIN ALLEN, INC. (3.91%)
PANOLA SIGN & BARRICADE, INC.(1.63%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.78%)
STRIPING TECHNOLOGY, L.P.(4.76%)
Contract # 05143011
Totals 527788.66 44637.50 265305.95 50.2

page 1 | page 2 | page 3