Monthly Local Let Maintenance Report For Dallas District As Of Jul 14, 2017 Page 2 Of 5

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyELLIS
HighwayFM0813
FromVARIOUS ROADWAYS IN THE
ToELLIS COUNTY MAINTENANCE SECTION
CSJ6296-95-001
Proj IDRMC - 629695001
Work TypeREMOVAL AND DISPOSAL OF DRIFTWOOD
 
0.001274500.00157770.0057.4
Work Order02-22-16
Work Began01-26-16
Work Completed
Time Computed02-29-16
Contract Working Days730
Addl Days Granted0
Working Days Charged486
Percent Time Used66
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6296-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01161801
Totals274500.000.00157770.0057.4

CountyELLIS
HighwayUS0287
FromVARIOUS ROADWAYS IN ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6297-44-001
Proj IDRMC - 629744001
Work TypeSPECIALTY MARKINGS
 
0.001273952.0045337.0816.5
Work Order06-27-16
Work Began07-06-16
Work Completed
Time Computed07-05-16
Contract Working Days730
Addl Days Granted0
Working Days Charged355
Percent Time Used48
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05161805
Totals273952.000.0045337.0816.5

CountyDALLAS
HighwayUS0080
FromVARIOUS ROADWAYS IN THE SOUTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6299-11-001
Proj IDRMC - 629911001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.00139801.0037184.9093.4
Work Order03-08-17
Work Began03-15-17
Work Completed
Time Computed03-15-17
Contract Working Days63
Addl Days Granted0
Working Days Charged26
Percent Time Used41
Contractor(s)
A&O GENERAL CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161803
Totals39801.000.0037184.9093.4

CountyDALLAS
HighwaySH0078
FromVARIOUS ROADWAYS IN THE NORTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6299-12-001
Proj IDRMC - 629912001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.001248800.0074475.8029.9
Work Order02-07-17
Work Began02-15-17
Work Completed
Time Computed02-15-17
Contract Working Days365
Addl Days Granted0
Working Days Charged131
Percent Time Used35
Contractor(s)
WEST TEXAS REBAR PLACERS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161804
Totals248800.0011525.0074475.8029.9

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6301-23-001
Proj IDRMC - 630123001
Work TypeRAISED PAVEMENT MARKERS
 
0.001111857.9493639.2383.7
Work Order09-23-16
Work Began09-30-16
Work Completed
Time Computed09-30-16
Contract Working Days365
Addl Days Granted0
Working Days Charged272
Percent Time Used74
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6301-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161802
Totals111857.9427717.2593639.2383.7

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6301-24-001
Proj IDRMC - 630124001
Work TypeCALL OUT REFLECTORIZED PAVEMENT MARKINGS
 
0.001171011.4442386.6024.7
Work Order09-13-16
Work Began09-20-16
Work Completed
Time Computed09-20-16
Contract Working Days730
Addl Days Granted0
Working Days Charged280
Percent Time Used38
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161803
Totals171011.4422935.7942386.6024.7

CountyDALLAS
HighwayUS0080
FromVARIOUS ROADWAYS IN THE SOUTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-00-001
Proj IDRMC - 630200001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.001253810.0075987.3029.9
Work Order02-03-17
Work Began02-10-17
Work Completed
Time Computed01-17-17
Contract Working Days365
Addl Days Granted0
Working Days Charged136
Percent Time Used37
Contractor(s)
IOWA BRIDGE & CULVERT, LC
SUBCONTRACTOR(S) FOR CCSJ: 6302-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161806
Totals253810.000.0075987.3029.9

CountyDALLAS
HighwaySH0078
FromVARIOUS ROADWAYS IN THE NORTHEAST DALLAS
ToCOUNTY MAINTENANCE SECTION
CSJ6302-02-001
Proj IDRMC - 630202001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.00152200.0050800.0097.3
Work Order04-05-17
Work Began04-17-17
Work Completed
Time Computed04-17-17
Contract Working Days63
Addl Days Granted0
Working Days Charged45
Percent Time Used71
Contractor(s)
WEST TEXAS REBAR PLACERS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161807
Totals52200.0033100.0050800.0097.3

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-03-001
Proj IDRMC - 630203001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.0010.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6302-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161802
Totals0.000.000.000.0

CountyDALLAS
HighwayUS0067
FromVARIOUS ROADWAYS IN THE SOUTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-04-001
Proj IDRMC - 630204001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.00155500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6302-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161803
Totals55500.000.000.000.0

CountyDALLAS
HighwayIH0030
FromVARIOUS LOCATIONS IN NORTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-37-001
Proj IDRMC - 630237001
Work TypeRAISED PAVEMENT MARKERS
 
0.001121982.34113042.3492.6
Work Order02-07-17
Work Began02-15-17
Work Completed
Time Computed02-15-17
Contract Working Days365
Addl Days Granted0
Working Days Charged129
Percent Time Used35
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6302-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161808
Totals121982.340.00113042.3492.6

CountyNAVARRO
HighwayIH0045
FromVARIOUS ROADWAYS IN THE NAVARRO
ToCOUNTY MAINTENANCE SECTION
CSJ6302-47-001
Proj IDSUP - 630247001
Work TypeLITTER REMOVAL
 
0.00148732.2428372.5858.2
Work Order06-18-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged300
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6302-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161830
Totals48732.245174.7228372.5858.2

CountyDALLAS
HighwayIH0020
FromVARIOUS ROADWAYS IN THE NORTHWEST DALLAS
ToCOUNTY MAINTENANCE SECFTION
CSJ6302-48-001
Proj IDSUP - 630248001
Work TypeLITTER REMOVAL
 
0.00194310.4647185.0350.0
Work Order07-21-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged296
Percent Time Used40
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161831
Totals94310.462212.3247185.0350.0

CountyDALLAS
HighwayIH0045
FromVARIOUS ROADWAYS IN THE SOUTHEAST DALLAS
ToCOUNTY MAINTENANCE SECTION
CSJ6302-49-001
Proj IDSUP - 630249001
Work TypeLITTER REMOVAL
 
0.001212694.9486603.9840.7
Work Order07-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged298
Percent Time Used40
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161832
Totals212694.9410509.6386603.9840.7

CountyKAUFMAN
HighwayUS0080
FromVARIOUS ROADWAYS IN KAUFMAN
ToMAINTENANCE SECTION
CSJ6302-50-001
Proj IDSUP - 630250001
Work TypeLITTER REMOVAL
 
0.001222173.0281868.7136.8
Work Order08-02-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged299
Percent Time Used40
Contractor(s)
TIBH INDUSTRIES, INC.
P G SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6302-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161833
Totals222173.029427.4881868.7136.8

CountyCOLLIN
HighwayUS0380
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6302-51-001
Proj IDSUP - 630251001
Work TypeLITTER REMOVAL
 
0.001196309.7083876.6842.7
Work Order05-27-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged299
Percent Time Used40
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6302-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161834
Totals196309.7012205.5783876.6842.7

CountyDALLAS
HighwayIH0030
FromVARIOUS ROADWAYS IN THE NORTHEAST DALLAS
ToCOUNTY MAINTENANCE SECTION
CSJ6302-52-001
Proj IDSUP - 630252001
Work TypeLITTER REMOVAL
 
0.00195207.7127497.7228.8
Work Order07-25-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged296
Percent Time Used40
Contractor(s)
TIBH INDUSTRIES, INC.
P G SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6302-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161835
Totals95207.712588.4827497.7228.8

CountyELLIS
HighwayUS0287
FromVARIOUS ROADWAYS IN THE ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6302-53-001
Proj IDSUP - 630253001
Work TypeLITTER REMOVAL
 
0.001120015.9545836.5338.1
Work Order07-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged294
Percent Time Used40
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6302-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161836
Totals120015.95867.9045836.5338.1

CountyELLIS
HighwayIH0035E
FromVARIOUS ROADWAYS IN THE ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6302-54-001
Proj IDSUP - 630254001
Work TypeLITTER REMOVAL
 
0.001128893.4597576.1775.7
Work Order07-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged298
Percent Time Used81
Contractor(s)
TIBH INDUSTRIES, INC.
P G SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6302-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161837
Totals128893.454652.9497576.1775.7

CountyDALLAS
HighwayIH0020
FromVARIOUS ROADWAYS IN THE SOUTHWEST DALLAS
ToCOUNTY MAINTENANCE SECTION
CSJ6302-55-001
Proj IDSUP - 630255001
Work TypeLITTER REMOVAL
 
0.001268527.7255881.4920.8
Work Order07-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged297
Percent Time Used40
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161838
Totals268527.724948.7955881.4920.8