Monthly Local Let Maintenance Report For Dallas District As Of Dec 10, 2014 Page 2 Of 4

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCOLLIN
Highway US0380
From VARIOUS LOCATIONS IN
To COLLIN COUNTY
CSJ 6256-57-001
Proj ID RMC - 625657001
Work Type VEGETATION MANAGEMENT
 
0.001 141380.75 0.00 141380.75 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-27-14
Work Began 05-05-14
Work Completed  
Time Computed 11-10-14
Contract Working Days 28
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 42
Contractor(s)
ANTHONY SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6256-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09131802
Totals 141380.75 0.00 141380.75 99.9

CountyDALLAS
Highway SH0114
From SH114 EAST AND WEST BOUND BRIDGE
To AT HACKBERRY CREEK
CSJ 6257-00-001
Proj ID RMC - 625700001
Work Type CHANNEL EROSION PROTECT & STRUCTURAL RPR
 
0.031 280387.32 0.00 268890.60 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-11-14
Work Began 06-02-14
Work Completed 09-30-14
Time Computed 03-17-14
Contract Working Days 28
Addl Days Granted 11
Working Days Charged 38
Percent Time Used 97
Contractor(s)
CD BUILDERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131801
Totals 280387.32 0.00 268890.60 100.0

CountyROCKWALL
Highway IH0030
From VARIOUS ROADWAYS IN
To ROCKWALL COUNTY
CSJ 6258-22-001
Proj ID RMC - 625822001
Work Type SWEEPING & DEBRIS REMOVAL
 
0.001 239695.60 6000.00 112124.60 46.7
Work Order 09-24-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 417
Percent Time Used 57
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6258-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131803
Totals 239695.60 6000.00 112124.60 46.7

CountyNAVARRO
Highway FM1126
From FM 1126 AT CHAMBER CREEK
To STR NBI # 18-175-0-1289-01-003
CSJ 6259-04-001
Proj ID RMC - 625904001
Work Type BRIDGE STRUCTURE REPAIR
 
0.001 215518.57 0.00 135166.10 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-21-14
Work Began 06-01-14
Work Completed 10-03-14
Time Computed 06-01-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 86
Contractor(s)
BEAR CREEK CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6259-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131802
Totals 215518.57 0.00 135166.10 100.0

CountyDENTON
Highway FM0407
From VARIOUS ROADWAYS IN THE DENTON COUNTY
To MAINTENANCE SECTION
CSJ 6259-09-001
Proj ID SUP - 625909001
Work Type LITTER REMOVAL
 
0.001 229288.88 6441.31 105885.04 46.1
Work Order 08-15-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 454
Percent Time Used 62
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09131831
Totals 229288.88 6441.31 105885.04 46.1

CountyELLIS
Highway IH0045
From VARIOUS ROADWAYS IN THE ELLIS
To COUNTY MAINTENANCE SECTION
CSJ 6259-21-001
Proj ID RMC - 625921001
Work Type REFLECTORIZED PAVEMENT MARKINGS
 
0.001 250100.00 0.00 58029.23 23.2
Work Order 03-14-14
Work Began 03-24-14
Work Completed  
Time Computed 03-24-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 243
Percent Time Used 33
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6259-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10131802
Totals 250100.00 0.00 58029.23 23.2

CountyROCKWALL
Highway IH0030
From IH30 AT PARKER CREEK, PARKER CREEK
To BRANCH, FM551 HACKBERRY CREEK, US175
CSJ 6259-42-001
Proj ID BPM - 625942001
Work Type REPLACE WINGWALLS & REPAIR SPALLING
 
0.001 130385.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131801
Totals 130385.00 0.00 0.00 0.0

CountyDALLAS
Highway IH0035E
From VARIOUS ROADWAYS IN
To DALLAS COUNTY
CSJ 6259-76-001
Proj ID EMC - 625976001
Work Type REFLECTORIZED PAVEMENT MARKINGS
 
0.001 455877.60 42780.52 3242407.03 99.9
Work Order 05-31-13
Work Began 06-17-13
Work Completed  
Time Computed 06-17-13
Contract Working Days 61
Addl Days Granted 470
Working Days Charged 531
Percent Time Used 100
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6259-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05131840
Totals 455877.60 42780.52 3242407.03 99.9

CountyDENTON
Highway FM0428
From VARIOUS ROADWAYS IN THE DENTON
To COUNTY MAINTENANCE SECTION
CSJ 6260-53-001
Proj ID RMC - 626053001
Work Type TREE TRIMMING & TREE AND BRUSH REMOVAL
 
0.100 178650.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-08-14
Work Began 00-00-00
Work Completed  
Time Computed 12-15-14
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ADVANCED TRANSOL CONSULTANTS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6260-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09141801
Totals 178650.00 0.00 0.00 0.0

CountyCOLLIN
Highway US0075
From VARIOUS LOCATIONS IN THE COLLIN
To COUNTY MAINTENANCE SECTION
CSJ 6260-59-001
Proj ID RMC - 626059001
Work Type FLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.001 304000.00 0.00 1060328.16 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-02-13
Work Began 10-07-13
Work Completed 09-30-14
Time Computed 10-14-13
Contract Working Days 66
Addl Days Granted 50
Working Days Charged 82
Percent Time Used 70
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6260-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131804
Totals 304000.00 0.00 1060328.16 100.0

CountyELLIS
Highway IH0045
From VARIOUS ROADWAYS IN THE
To ELLIS COUNTY MAINTENANCE SECTION
CSJ 6260-80-001
Proj ID RMC - 626080001
Work Type REMOVAL AND DISPOSAL OF DRIFTWOOD
 
0.001 75000.00 0.00 33960.00 45.2
Work Order 04-28-14
Work Began 06-02-14
Work Completed  
Time Computed 05-05-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 200
Percent Time Used 54
Contractor(s)
MANNY GENERAL CONTRACTOR CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6260-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02141801
Totals 75000.00 0.00 33960.00 45.2

CountyDALLAS
Highway US0080
From DALLAS DISTRICT
To COMPLEX
CSJ 6261-97-001
Proj ID SUP - 626197001
Work Type GROUNDS MAINTENANCE
 
0.001 82884.50 2630.00 42308.55 51.0
Work Order 09-04-13
Work Began 09-01-13
Work Completed  
Time Computed 11-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 395
Percent Time Used 54
Contractor(s)
TIBH INDUSTRIES, INC.
LIFENET COMMUNITY BEHAVIORAL HEALTHCARE
SUBCONTRACTOR(S) FOR CCSJ: 6261-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131830
Totals 82884.50 2630.00 42308.55 51.0

CountyELLIS
Highway US0077
From SOUTHBOUND US 77 1.2 MILES
To SOUTH OF FORRESTON
CSJ 6261-98-001
Proj ID SUP - 626198001
Work Type PICNIC AREA MAINTENANCE
 
0.001 12920.00 315.00 5970.00 46.2
Work Order 11-15-13
Work Began 12-01-13
Work Completed  
Time Computed 12-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 356
Percent Time Used 48
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6261-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131830
Totals 12920.00 315.00 5970.00 46.2

CountyELLIS
Highway FM0876
From ELLIS COUNTY AREA OFFICE AND
To MAINTENANCE FACILITIES
CSJ 6261-99-001
Proj ID SUP - 626199001
Work Type JANITORIAL AND GROUNDS MAINTENANCE
 
0.001 64514.40 1938.10 30907.20 47.9
Work Order 11-15-13
Work Began 12-01-13
Work Completed  
Time Computed 12-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 326
Percent Time Used 44
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6261-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131831
Totals 64514.40 1938.10 30907.20 47.9

CountyNAVARRO
Highway SH0031
From NAVARRO COUNTY AREA OFFICE &
To MAINTENANCE FACILITY
CSJ 6262-00-001
Proj ID SUP - 626200001
Work Type JANITORIAL AND GROUNDS MAINTENANCE
 
0.001 23043.92 805.08 10004.96 43.4
Work Order 10-09-13
Work Began 12-01-13
Work Completed  
Time Computed 12-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 359
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6262-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131832
Totals 23043.92 805.08 10004.96 43.4

CountyNAVARRO
Highway SH0031
From NAVARRO COUNTY
To MAINTENANCE SECTION
CSJ 6262-01-001
Proj ID SUP - 626201001
Work Type PICNIC AREA MAINTENANCE
 
0.001 27280.00 1020.00 11730.00 42.9
Work Order 10-09-13
Work Began 12-01-13
Work Completed  
Time Computed 12-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 359
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6262-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12131833
Totals 27280.00 1020.00 11730.00 42.9

CountyELLIS
Highway US0287
From VARIOUS ROADWAYS EXCEPT IH 45 IN THE
To ELLIS COUNTY MAINTENANCE SECTION
CSJ 6262-33-001
Proj ID RMC - 626233001
Work Type REFLECTORIZED PAVEMENT MARKERS
 
0.001 203110.00 0.00 197069.00 97.0
Work Order 04-28-14
Work Began 05-12-14
Work Completed  
Time Computed 05-12-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 194
Percent Time Used 53
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6262-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141801
Totals 203110.00 0.00 197069.00 97.0

CountyKAUFMAN
Highway IH0020
From VARIOUS ROADWAYS IN THE
To KAUFMAN/ROCKWALL MAINTENANCE SECTION
CSJ 6263-62-001
Proj ID RMC - 626362001
Work Type DITCH MAINTENANCE & GUARDRAIL CLEANING
 
0.001 264700.00 0.00 7285.00 2.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-02-14
Work Began 09-08-14
Work Completed  
Time Computed 09-09-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 74
Percent Time Used 10
Contractor(s)
WEST TEXAS REBAR PLACERS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141801
Totals 264700.00 0.00 7285.00 2.7

CountyROCKWALL
Highway IH0030
From VARIOUS ROADWAYS IN ROCKWALL
To & COLLIN COUNTY
CSJ 6263-70-001
Proj ID RMC - 626370001
Work Type DELINEATOR & SMALL SIGN INSTALLATION
 
0.001 187424.30 0.00 167682.20 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-02-14
Work Began 07-14-14
Work Completed 10-28-14
Time Computed 07-14-14
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 40
Percent Time Used 114
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6263-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141802
Totals 187424.30 0.00 167682.20 100.0

CountyDALLAS
Highway IH0045
From 1.04 MILES SOUTH OF MALLOY BRIDGE
To IH 45 UNDERPASS
CSJ 6263-93-001
Proj ID RMC - 626393001
Work Type BRIDGE REPAIR
 
0.001 110628.00 0.00 32572.00 29.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-30-14
Work Began 11-11-14
Work Completed  
Time Computed 11-10-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 23
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141803
Totals 110628.00 0.00 32572.00 29.4