Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTARRANT
Highway IH0020
From VARIOUS ROADWAYS WITHIN
To SOUTH TARRANT COUNTY
CSJ 6272-25-001
Proj ID SUP - 627225001
Work Type LITTER REMOVAL
 
0.010 417751.89 39234.66 449402.97 99.9
Work Order 07-01-14
Work Began 07-01-14
Work Completed  
Time Computed 07-08-14
Contract Working Days 365
Addl Days Granted 62
Working Days Charged 387
Percent Time Used 90
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6272-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06140233
Totals 417751.89 39234.66 449402.97 99.9

CountyHOOD
Highway US0377
From HOOD, SOMMERVELL
To & ERATH COUNTIES
CSJ 6272-26-001
Proj ID SUP - 627226001
Work Type LITTER REMOVAL
 
0.010 53605.89 9998.34 30065.44 56.0
Work Order 03-16-15
Work Began 00-00-00
Work Completed  
Time Computed 04-01-15
Contract Working Days 176
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 5
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6272-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03150231
Totals 53605.89 9998.34 30065.44 56.0

CountyPARKER
Highway IH0020
From VARIOUS ROADWAYS WITHIN
To PARKER & PALO PINTO COUNTY
CSJ 6272-27-001
Proj ID SUP - 627227001
Work Type LITTER REMOVAL
 
0.010 207048.02 15217.54 215587.57 99.9
Work Order 07-01-14
Work Began 00-00-00
Work Completed  
Time Computed 07-08-14
Contract Working Days 365
Addl Days Granted 62
Working Days Charged 383
Percent Time Used 89
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6272-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06140236
Totals 207048.02 15217.54 215587.57 99.9

CountyTARRANT
Highway IH0820
From VARIOUS ROADWAYS WITHIN
To NORTH TARRANT COUNTY
CSJ 6272-28-001
Proj ID SUP - 627228001
Work Type LITTER REMOVAL
 
0.010 341445.56 0.00 323674.54 94.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 07-01-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06140234
Totals 341445.56 0.00 323674.54 94.7

CountyTARRANT
Highway IH0820
From VARIOUS ROADWAYS WITHIN
To NORTH TARRANT COUNTY
CSJ 6272-33-001
Proj ID RMC - 627233001
Work Type REFLECTORIZED PAV.MARKINGS & MARKERS
 
0.010 394966.05 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-21-15
Work Began 07-21-15
Work Completed  
Time Computed 07-28-15
Contract Working Days 18
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06150210
Totals 394966.05 0.00 0.00 0.0

CountyTARRANT
Highway IH0820
From JANITORIAL MAINTENANCE @
To DISTRICT COMPLEX
CSJ 6272-37-001
Proj ID SUP - 627237001
Work Type JANITORIAL MAINTENANCE
 
0.010 156163.46 0.00 174310.13 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 05-02-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 426
Percent Time Used 116
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6272-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04140232
Totals 156163.46 0.00 174310.13 99.9

CountyTARRANT
Highway IH0820
From VARIOUS ROADWAYS WITHIN
To NORTH TARRANT COUNTY
CSJ 6272-40-001
Proj ID RMC - 627240001
Work Type REFLECTORIZED PAV.MARKINGS & MARKERS
 
0.010 351001.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 17
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6272-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06150211
Totals 351001.50 0.00 0.00 0.0

CountyWISE
Highway US0380
From VARIOUS ROADWAYS WITHIN
To WISE AND JACK COUNTY
CSJ 6272-66-001
Proj ID RMC - 627266001
Work Type FLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010 338100.00 0.00 349451.94 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-10-14
Work Began 00-00-00
Work Completed  
Time Computed 09-17-14
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 40
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6272-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07140206
Totals 338100.00 0.00 349451.94 99.9

CountyTARRANT
Highway IH0030
From VARIOUS ROADWAYS IN SOUTH TARRANT,
To PARKER, & JOHNSON COUNTIES
CSJ 6273-53-001
Proj ID RMC - 627353001
Work Type CLEANING & SEALING JOINTS & CRACKS
 
0.010 195507.70 0.00 238868.51 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-05-15
Work Began 00-00-00
Work Completed  
Time Computed 01-12-15
Contract Working Days 37
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 64
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11140206
Totals 195507.70 0.00 238868.51 99.9

CountyWISE
Highway US0081
From VARIOUS ROADWAYS WITHIN
To WISE AND JACK COUNTIES
CSJ 6273-56-001
Proj ID RMC - 627356001
Work Type CLEANING AND SEALING JOINTS / CRACKS
 
0.010 139962.00 0.00 122673.80 87.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-05-15
Work Began 00-00-00
Work Completed  
Time Computed 01-12-15
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 48
Contractor(s)
ANTHONY SERVICES (INACTIVE)
SUBCONTRACTOR(S) FOR CCSJ: 6273-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11140203
Totals 139962.00 0.00 122673.80 87.6

CountyTARRANT
Highway SH0183
From VARIOUS ROADWAYS IN NORTH TARRANT,
To PARKER, & PALO PINTO COUNTIES
CSJ 6273-57-001
Proj ID RMC - 627357001
Work Type CLEANING & SEALING JOINTS & CRACKS
 
0.010 220900.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-22-15
Work Began 00-00-00
Work Completed  
Time Computed 03-01-15
Contract Working Days 43
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11140202
Totals 220900.50 0.00 0.00 0.0

CountyTARRANT
Highway FM0156
From JANITORIAL MAINTENANCE AT
To SAGINAW MAINTENANCE OFFICE
CSJ 6274-44-001
Proj ID SUP - 627444001
Work Type JANITORIAL MAINTENANCE
 
0.010 11411.52 0.00 11411.52 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-01-14
Work Began 07-01-14
Work Completed  
Time Computed 07-08-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 360
Percent Time Used 98
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6274-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06140231
Totals 11411.52 0.00 11411.52 99.9

CountyTARRANT
Highway IH0030
From IH 30 @ SH 360 (N. WATSON RD)
To IN TARRANT COUNTY
CSJ 6274-79-001
Proj ID RMC - 627479001
Work Type STEEL BRIDGE REPAIR
 
0.010 43200.00 0.00 44934.69 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-19-15
Work Began 01-19-15
Work Completed  
Time Computed 01-26-15
Contract Working Days 12
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 16
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-79-001
GIBSON & ASSOCIATES, INC.( 64.81%)
ALTUS TRAFFIC MANAGEMENT LLC (2.76%)
Contract # 11140201
Totals 43200.00 0.00 44934.69 99.9

CountyTARRANT
Highway IH0020
From FORT WORTH
To DISTRICT COMPLEX
CSJ 6277-91-001
Proj ID SUP - 627791001
Work Type GROUNDS MAINTENANCE
 
0.010 50990.34 0.00 33311.76 65.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 74
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6277-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09140231
Totals 50990.34 0.00 33311.76 65.3

CountyWISE
Highway US0081
From WISE & JACK COUNTY
To MAINTENANCE
CSJ 6277-92-001
Proj ID SUP - 627792001
Work Type JANITORIAL MAINTENANCE
 
0.010 32692.68 2724.39 24519.51 75.0
Work Order 10-31-14
Work Began 00-00-00
Work Completed  
Time Computed 11-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 266
Percent Time Used 72
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6277-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10140231
Totals 32692.68 2724.39 24519.51 75.0

CountyPARKER
Highway 0020
From JANITORIAL MAINTENANCE
To WEATERFORD MAINTENANCE OFFICE
CSJ 6277-93-001
Proj ID SUP - 627793001
Work Type JANITORIAL MAINTENANCE
 
0.010 31380.00 0.00 15690.00 50.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 168
Percent Time Used 46
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6277-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01150234
Totals 31380.00 0.00 15690.00 50.0

CountyWISE
Highway US0380
From VARIOUS LOCATIONS WITHIN
To WISE & JACK COUNTIES
CSJ 6277-94-001
Proj ID SUP - 627794001
Work Type PICNIC AREA MAINTENANCE
 
0.010 53926.60 5343.12 31595.36 58.5
Work Order 01-01-15
Work Began 00-00-00
Work Completed  
Time Computed 01-08-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 205
Percent Time Used 56
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6277-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01150233
Totals 53926.60 5343.12 31595.36 58.5

CountyHOOD
Highway FM0051
From VARIOS LOCATIONS WITHIN HOOD/SOMERVELL &
To ERATH COUNTIES
CSJ 6277-95-001
Proj ID SUP - 627795001
Work Type PICNIC AREA MAINTENANCE
 
0.010 97613.02 0.00 53679.05 54.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-09-15
Work Began 00-00-00
Work Completed  
Time Computed 04-16-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 153
Percent Time Used 41
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01150231
Totals 97613.02 0.00 53679.05 54.9

CountyPARKER
Highway IH0020
From VARIOUS LOCATIONS WITHIN
To PARKER/PALO PINTO COUNTIES
CSJ 6277-96-001
Proj ID SUP - 627796001
Work Type PICNIC AREA MAINTENANCE
 
0.010 71135.62 5858.51 37182.05 52.2
Work Order 01-01-15
Work Began 00-00-00
Work Completed  
Time Computed 01-08-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 206
Percent Time Used 56
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6277-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01150232
Totals 71135.62 5858.51 37182.05 52.2

CountyTARRANT
Highway IH0035W
From SPECIAL MAINTENANCE OFFICE
To WAGGOMAN STREET
CSJ 6277-97-001
Proj ID SUP - 627797001
Work Type JANITORIAL MAINTENANCE
 
0.010 8253.48 0.00 1375.58 16.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 16
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6277-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04150232
Totals 8253.48 0.00 1375.58 16.6