Monthly State Let Construction Report For Lufkin District As Of Jul 11, 2014 Page 2 Of 3

Last Update: Friday, July 11, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountySAN JACINTO
Highway US 59
From JUST S OF UPRR IN SHEPHERD
To JUST N OF FM 2914
CSJ 0177-02-089
Proj ID STP 2013(916)
Work Type ADD SB FRTG RD & RECONST MAIN LANES
 
1.642 8948536.85 0.00 0.00 0.0
Work Order 05-14-14
Work Began 00-00-00
Work Completed  
Time Computed 05-30-14
Contract Working Days 230
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0177-02-089
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143221
Totals 8948536.85 0.00 0.00 0.0

CountyPOLK
Highway PR 56
From US 190
To 1.317 MI S
CSJ 0213-12-009
Proj ID PLD 2014(053)
Work Type RECONSTRUCT & WIDEN EXISTING PVMT
 
1.317 1144070.43 147751.33 1035985.64 90.5
Work Order 01-17-14
Work Began 03-12-14
Work Completed  
Time Computed 03-12-14
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 100
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0213-12-009
LONESTAR TRAFFIC SAFETY, LLC (0.32%)
MOORE BROTHERS CONSTRUCTION COMPANY( 29.10%)
A R BROTHERS CONSTRUCTION SERVICES, INC. ( 13.34%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.52%)
AMERICAN REMEDIATION OPTIONS, INC. (5.88%)
Contract # 10133218
Totals 1144070.43 147751.33 1035985.64 90.5

CountySABINE
Highway SH 87
From 1.61 MI S OF FM 944
To 0.2 MI SE OF FM 2928
CSJ 0304-04-042
Proj ID STP 2013(463)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
7.996 1937298.95 114107.05 2135648.59 99.9
Work Order 05-23-13
Work Began 07-01-13
Work Completed  
Time Computed 06-08-13
Contract Working Days 62
Addl Days Granted 22
Working Days Charged 91
Percent Time Used 108
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0304-04-042
AMERICAN REMEDIATION OPTIONS, INC. (6.78%)
CRABTREE BARRICADE SYSTEMS, INC. (2.64%)
LONE STAR EQUIPMENT CO. INC. (INACTIVE--SEE 12687) ( 21.75%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.36%)
EXPRESS PERSONNEL SERVICES (0.25%)
Contract # 03133229
Totals 1937298.95 114107.05 2135648.59 99.9

CountyANGELINA
Highway SP 339
From LP 36
To SH 94
CSJ 0336-04-014
Proj ID STP 2013(120)
Work Type PLANE, SEAL AND OVERLAY
 
1.166 778694.77 30956.08 938257.51 99.9
CountyANGELINA
Highway SP 339
From LP 287
To LP 36
CSJ 0336-04-015
Proj ID PLD 1102(545)
Work Type RESURF & WIDEN FOR CTWLTL W / C & G
 
1.110 2633618.29 65689.94 2444397.18 92.8
Work Order 12-04-12
Work Began 02-08-13
Work Completed  
Time Computed 02-04-13
Contract Working Days 231
Addl Days Granted 1
Working Days Charged 222
Percent Time Used 95
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0336-04-014
HIGHWAY TECHNOLOGIES, INC. (1.80%)
AMERICAN REMEDIATION OPTIONS, INC. (1.48%)
J & M CONTRACTING, COMPANY ( 31.01%)
DUSTROL, INC.(2.89%)
LONE STAR EQUIPMENT CO. INC. (INACTIVE--SEE 12687) (6.61%)
M BROCK INC(0.46%)
PINTO CONSTRUCTION CO., INC. (5.74%)
CRABTREE BARRICADE SYSTEMS, INC. (1.81%)
Contract # 10123006
Totals 3412313.06 96646.02 3382654.69 99.1

CountyHOUSTON
Highway US 287
From LP 304
To TRINITY COUNTY LINE
CSJ 0340-01-040
Proj ID STP 2014(637)HES
Work Type IMPROVE GUARDRAIL AND SAFETY TREAT
 
14.369 1379201.46 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-10-14
Work Began 00-00-00
Work Completed  
Time Computed 07-26-14
Contract Working Days 217
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JW PAYNE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0340-01-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143216
Totals 1379201.46 0.00 0.00 0.0

CountyPOLK
Highway US 287
From US 59
To TYLER COUNTY LINE
CSJ 0341-03-037
Proj ID STP 2014(925)HESG
Work Type IMPROVE GUARDRAIL AND SAFETY TREAT
 
23.125 928912.62 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 219
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0341-03-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143213
Totals 928912.62 0.00 0.00 0.0

CountyNACOGDOCHES
Highway SH 204
From CHEROKEE C/L (@ ANGELINA RIVER)
To 0.1 MI E OF FM 2783
CSJ 0450-04-044
Proj ID STP 2014(840)
Work Type OCST AND SUPERPAVE
 
2.556 1010920.03 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 28
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0450-04-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143031
Totals 1010920.03 0.00 0.00 0.0

CountyANGELINA
Highway VA
From AT VARIOUS LOCATIONS IN LUFKIN
To DISTRICT
CSJ 0911-00-073
Proj ID STP 2014(928)
Work Type CONSTRUCT CURB RAMPS
 
0.001 556965.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 126
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-00-073
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143009
Totals 556965.00 0.00 0.00 0.0

CountyPOLK
Highway VA
From AT LAKE LIVINGSTON STATE PARK
To .
CSJ 0911-04-053
Proj ID C 911-4-53
Work Type REPAIR AND RESURFACE PAVED AREAS
 
0.818 819806.93 0.00 814786.23 99.3
Work Order 06-14-13
Work Began 07-25-13
Work Completed  
Time Computed 06-03-13
Contract Working Days 35
Addl Days Granted 5
Working Days Charged 34
Percent Time Used 85
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-053
PANOLA SIGN & BARRICADE, INC.(0.36%)
CCC BLACKTOPPING, LLC( 26.67%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.76%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.40%)
Contract # 04133024
Totals 819806.93 0.00 814786.23 99.3

CountyNACOGDOCHES
Highway CR
From CR 706 AT YSELETA CREEK
To .
CSJ 0911-08-044
Proj ID BR 2013(438)
Work Type BRIDGE REPLACEMENT
 
0.041 217515.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-08-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143032
Totals 217515.25 0.00 0.00 0.0

CountySABINE
Highway CR
From ROCK CREEK RD AT ROCK CREEK
To .
CSJ 0911-29-036
Proj ID BR 2012(488)
Work Type BRIDGE REPLACEMENT
 
0.129 436864.83 0.00 429704.14 98.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-14-13
Work Began 03-04-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 89
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 76
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-29-036
AMERICAN REMEDIATION OPTIONS, INC. (6.81%)
CRABTREE BARRICADE SYSTEMS, INC. (2.02%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 10.92%)
MESA ROD BUSTERS, INC. (0.59%)
Contract # 04133226
Totals 436864.83 0.00 429704.14 98.3

CountySAN AUGUSTINE
Highway CR
From CR 4320 AT CHIAMON BAYOU
To .
CSJ 0911-30-021
Proj ID BR 2013(435)
Work Type BRIDGE REPLACEMENT
 
0.176 510181.60 0.00 63824.31 12.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-12-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-30-021
DUSTY ALLEN, INC.(7.41%)
PANOLA SIGN & BARRICADE, INC.(0.68%)
TEXAS ALTERNATIVE GRASSER, INC.(1.70%)
Contract # 01143019
Totals 510181.60 0.00 63824.31 12.5

CountySAN AUGUSTINE
Highway CR
From CR 201 AT BIG IRON ORE CREEK
To .
CSJ 0911-30-028
Proj ID BR 2013(437)
Work Type BRIDGE REPLACEMENT
 
0.211 644984.12 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 73
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-30-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143023
Totals 644984.12 0.00 0.00 0.0

CountyTRINITY
Highway CR
From PORT BLVD AT MILL CREEK
To .
CSJ 0911-40-028
Proj ID BR 2013(408)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.105 604354.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-12-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-40-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143032
Totals 604354.25 0.00 0.00 0.0

CountyHOUSTON
Highway FM 227
From BU 287-V
To 0.5 MI E OF CR 1685
CSJ 0937-02-029
Proj ID STP 2013(546)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
11.160 4278380.79 154504.32 2157983.00 50.4
Work Order 06-19-13
Work Began 07-10-13
Work Completed  
Time Computed 07-10-13
Contract Working Days 168
Addl Days Granted 0
Working Days Charged 86
Percent Time Used 51
Contractor(s)
L. S. EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0937-02-029
STRIPING TECHNOLOGY, L.P.(2.43%)
ROBINSON CONSTRUCTION(4.56%)
ODUM SERVICES, L.P.(3.30%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.66%)
Contract # 04133219
Totals 4278380.79 154504.32 2157983.00 50.4

CountySABINE
Highway FM 1592
From SH 103
To SH 184
CSJ 1510-01-019
Proj ID STP 2014(747)HRR
Work Type SAFETY TREAT FIXED OBJECTS
 
17.157 1226352.49 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 1510-01-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143233
Totals 1226352.49 0.00 0.00 0.0

CountyHOUSTON
Highway FM 1280
From SH 21
To FM 230
CSJ 1676-02-015
Proj ID STP 2013(394)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
25.772 4387077.87 403731.09 2656800.72 60.5
Work Order 04-10-13
Work Began 05-20-13
Work Completed  
Time Computed 04-26-13
Contract Working Days 254
Addl Days Granted 0
Working Days Charged 149
Percent Time Used 58
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1676-02-015
COLD CREEK CONSTRUCTION, LTD (1.27%)
J & M CONTRACTING, COMPANY ( 13.60%)
MURRAY CONSTRUCTION(0.75%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.77%)
PROFESSIONAL TRAFFIC CONTROL, LLC(2.07%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.17%)
TRAFCO INDUSTRIES, INC.(0.03%)
Contract # 02133020
Totals 4387077.87 403731.09 2656800.72 60.5

CountyHOUSTON
Highway FM 1733
From SH 21
To SH 7
CSJ 1677-01-015
Proj ID STP 2014(210)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
10.353 3771800.47 606528.76 2192167.15 58.1
Work Order 01-23-14
Work Began 02-17-14
Work Completed  
Time Computed 02-08-14
Contract Working Days 167
Addl Days Granted 0
Working Days Charged 69
Percent Time Used 41
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1677-01-015
ROADSAFE TRAFFIC SYSTEMS, INC. (2.27%)
ODUM SERVICES, L.P.(1.11%)
MURRAY CONSTRUCTION(0.75%)
J & M CONTRACTING, COMPANY (7.25%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.95%)
DREWERY & WHEATON, LLC (1.65%)
Contract # 11133211
Totals 3771800.47 606528.76 2192167.15 58.1

CountyHOUSTON
Highway FM 2022
From ANDERSON COUNTY LINE
To 0.1 MI N OF FM 3313
CSJ 1875-02-021
Proj ID STP 2013(677)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
38.913 4505244.42 667328.30 3142301.89 69.7
Work Order 07-23-13
Work Began 08-13-13
Work Completed  
Time Computed 08-13-13
Contract Working Days 168
Addl Days Granted 6
Working Days Charged 126
Percent Time Used 72
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1875-02-021
MURRAY CONSTRUCTION(0.64%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.61%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.91%)
ODUM SERVICES, L.P.(3.30%)
COLD CREEK CONSTRUCTION, LTD (2.18%)
PANOLA SIGN & BARRICADE, INC.(0.98%)
MOORE BROTHERS CONSTRUCTION COMPANY( 30.94%)
A R BROTHERS CONSTRUCTION SERVICES, INC. ( 20.26%)
SAND HILL FOUNDATION, LLC(0.11%)
Contract # 05133020
Totals 4505244.42 667328.30 3142301.89 69.7

CountyHOUSTON
Highway FM 2423
From BU 287-V
To FM 2022
CSJ 2299-01-007
Proj ID STP 2014(336)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
5.970 1440516.50 7322.67 542615.25 37.6
Work Order 02-27-14
Work Began 03-18-14
Work Completed  
Time Computed 03-15-14
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 60
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 2299-01-007
SOUTHWEST ENVIRONMENT SERVICES LLC (1.42%)
AMERICAN REMEDIATION OPTIONS, INC. (1.15%)
A R BROTHERS CONSTRUCTION SERVICES, INC. ( 18.69%)
BATTERSON,LLP(2.42%)
EROSION CONTROL MANAGEMENT SERVICES(1.24%)
COLD CREEK CONSTRUCTION, LTD (6.12%)
PANOLA SIGN & BARRICADE, INC.(0.76%)
Contract # 01143014
Totals 1440516.50 7322.67 542615.25 37.6

page 1 | page 2 | page 3