Monthly State Let Construction Report For Laredo District As Of Sep 15, 2014 Page 1 Of 2

Last Update: Monday, September 15, 2014
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLASALLE
Highway IH 35
From 4.44 MI S OF FM469 AT THE UPRR WYE
To 4.160 MI S OF FM469
CSJ 0017-08-079
Proj ID BR 1402(071)
Work Type BRIDGE REHABILITATION
 
0.357 3430660.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 129
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-08-079
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143227
Totals 3430660.25 0.00 0.00 0.0

CountyLASALLE
Highway IH 35
From 0.224 MILES NORTH OF FM 468
To 5.210 MILES NORTH OF FM 468
CSJ 0017-08-088
Proj ID NH 2014(898)
Work Type CABLE BARRIER
 
14.283 1456897.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 110
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-08-088
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143028
Totals 1456897.00 0.00 0.00 0.0

CountyLASALLE
Highway IH 35
From APPROXIMATELY 5 MI SOUTH COTULLA
To APPROXIMATELY 5 MI SOUTH COTULLA
CSJ 0018-01-068
Proj ID STP 2011(338)TE
Work Type CONSTRUCT TOURIST & VISITOR CENTER
 
0.001 14508653.40 0.00 14801338.72 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-07-11
Work Began 03-23-11
Work Completed  
Time Computed 03-23-11
Contract Working Days 346
Addl Days Granted 277
Working Days Charged 631
Percent Time Used 101
Contractor(s)
MATL CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0018-01-068
MEJIA & RUIZ LAND SURVEYORS, L.L.C.(0.18%)
CENTRAL TEXAS ENVIRONMENTAL SERVICES, LLC(0.24%)
OLMOS EQUIPMENT COMPANY, INC.(3.16%)
RAMOS CONCRETE, INC. (0.51%)
HIGHWAY TECHNOLOGIES, INC. (0.29%)
SOUTHERN LANDSCAPES(1.21%)
FLASHER EQUIPMENT COMPANY(0.40%)
GLASCO & COMPANY LANDSCAPING, INC. (1.20%)
RAMOS CONCRETE, INC. (0.82%)
CHARLES KLUTTS CO. (0.85%)
BOSQUEZ ELECTRICAL, LLC. (8.79%)
KAY CONCRETE CONTRACTORS, INC. (3.18%)
PLAYWELL GROUP, INC. (THE) (0.22%)
RODRIGUEZ & SONS, INC. (1.15%)
S-TEX INDUSTRIES, LLC(2.68%)
DELMAR PLUMBING COMPANY LLC(2.90%)
ELLIS AND ELLIS(0.68%)
H. L. ZUMWALT CONSTRUCTION, INC. (7.03%)
MARTIN FIREPROOFING CORPORATION(2.90%)
MCKINLEY DRILLING CO.(3.43%)
INNOVATIVE WATER SOLUTIONS LLC (1.36%)
HOUSLEY COMMUNICATIONS, INC. (0.10%)
PEST SHIELD PEST CONTROL, INC. (0.01%)
SCS CONSTRUCTION MANAGEMENT, INC.(4.84%)
H & H DOOR CO.INC. (0.02%)
UNIVERSAL OVERHEAD DOORS (0.15%)
CUSTOM MASONRY (0.56%)
TRIPLE R CONSTRUCTION(1.27%)
J & P PAVING CO. (0.13%)
ALTERNATIVE POWER SOLUTIONS CORP (0.35%)
PUENTE STRUCTURAL CONCRETE LLC (0.38%)
HUGO GARCIA ELECTRIC, INC. (0.18%)
KING TILE & MARBLE, INC. (1.24%)
AMERETE, INC.(0.25%)
ENTEX ROOF SYSTEM(3.22%)
SURFACE AMERICA(0.15%)
OVERHEAD DOOR CO. OF SOUTH CENTRAL TEXAS (0.01%)
FIREPROOF CONTRACTORS, INC.(0.23%)
J & B TRIM (0.28%)
KLINGER SPECIALTIES DIRECT (0.04%)
AIRBORNE FLAG & FLAGPOLE, LLC(0.06%)
STEP IT UP CONSTRUCTION(2.73%)
LOHMER COMMERCIAL SERVICES (0.29%)
SERVICE SHADE SHOP (0.00%)
RIVERBED CONCRETE, INC.(0.26%)
GALLOS PLUMBING SERVICE, CO. (1.25%)
INTERTECH FLOORING (0.04%)
MICHAEL EDWARDS CUSTOM CABINETRY & MILLWORK(0.08%)
APCO TEXAS (0.02%)
BATTEN DRILLING, INC.(0.02%)
CLS TECHNOLOGY, INC. (1.02%)
RELIABLE AIR SERVICE NOW!(0.55%)
ABM UNDERGROUND UTILITY CONSTRUCTION COMPANY (0.02%)
TEXAS ELECTRONIC SYSTEMS SPECIALISTS, INC. (0.88%)
ARTISTIC COUNTERS, INC.(0.06%)
CBT PARTNERS, LTD(0.03%)
RODRIGUEZ SEAMLESS GUTTERS (0.04%)
CURB PLANET INC. (0.11%)
MATHIS DOOR SERVICE(0.02%)
D & S CONCRETE CONTRACTOR(0.29%)
GALLEON CONTRACTING(0.05%)
BAMEX PAINTING, INC. (0.05%)
J.C. ENTERPRISES (0.11%)
TREVINO CERAMIC TILE (0.03%)
RGV ALLIANCE CONSTRUCTION, L.L.C.(0.10%)
BROWNING ELECTRIC(0.04%)
CONCRETE FLOOR FINISHES(0.45%)
DELTA SPECIALTIES SIGNS & SUPPLIES (0.04%)
ON OUR OWN SERVICES, INC.(0.22%)
MBE COMMERCIAL, LLC(0.25%)
Contract # 01113219
Totals 14508653.40 0.00 14801338.72 99.9

CountyLASALLE
Highway IH 35
From 0.775 MI NORTH OF BI35C (SOUTH INT)
To 1.031 MI SOUTH OF BI35C (SOUTH INT)
CSJ 0018-01-078
Proj ID NH 1402(072)
Work Type SMA OVERLAY AND PAVEMENT MRK
 
3.587 2087043.78 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
H. L. ZUMWALT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0018-01-078
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143038
Totals 2087043.78 0.00 0.00 0.0

CountyWEBB
Highway IH 35 ETC
From INT OF IH 35 AND SL 20
To .
CSJ 0018-06-171
Proj ID IM 0351(090)
Work Type INSTALL DUAL LEFT TURN LANES
 
1.581 1824453.25 324328.73 607017.26 33.2
Work Order 01-30-14
Work Began 07-07-14
Work Completed  
Time Computed 02-15-14
Contract Working Days 167
Addl Days Granted 0
Working Days Charged 40
Percent Time Used 23
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0018-06-171
STAR OPERATIONS, INC.( 39.63%)
INTERSTATE BARRICADES & MARKINGS, INC. (2.40%)
FLASHER EQUIPMENT COMPANY(3.45%)
Contract # 08133269
Totals 1824453.25 324328.73 607017.26 33.2

CountyZAVALA
Highway US 83
From 2.330 MI SOUTH OF FM 1025
To US 57
CSJ 0037-03-077
Proj ID NH 2014(730)
Work Type ACP, OVRLAY, PAV MRK, STRUC, SIGN
 
16.576 6445010.35 0.00 0.00 0.0
Work Order 07-08-14
Work Began 09-02-14
Work Completed  
Time Computed 07-24-14
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
H. L. ZUMWALT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0037-03-077
FLASHER EQUIPMENT COMPANY(1.23%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.11%)
BEAVER CONTRACTORS, LLC(7.59%)
Contract # 06143203
Totals 6445010.35 0.00 0.00 0.0

CountyDIMMIT
Highway US 83
From ASHERTON (SOUTH) CITY LIMITS
To 0.333 MI N OF FM 133
CSJ 0037-06-084
Proj ID C 37-6-84
Work Type GRAD, BASE, SURF, STR, STRIP & SIGN
 
10.134 3224328.65 22854.22 5611859.78 99.9
CountyDIMMIT
Highway US 83
From 0.333 MI NORTH OF FM 133
To DIMMIT/WEBB COUNTY LINE
CSJ 0037-08-035
Proj ID C 37-8-35
Work Type GRAD, BASE, SURF, STR, STRIP & SIGN
 
10.821 2563199.91 36153.30 2552010.87 99.5
CountyWEBB
Highway US 83
From WEBB/DIMMIT COUNTY LINE
To 3.442 MI SOUTH OF SH 44
CSJ 0037-09-027
Proj ID C 37-9-27
Work Type GRAD, BASE, SURF, STR, STRIP & SIGN
 
16.479 3642746.25 63563.94 2359113.85 64.7
CountyWEBB
Highway US 83
From 3.422 MI SOUTH OF SH 44
To IH 35
CSJ 0037-10-029
Proj ID C 37-10-29
Work Type GRAD, BASE, SURF, STR, STRIP & SIGN
 
16.409 5373174.68 0.00 4228004.55 78.6
Work Order 10-24-12
Work Began 11-09-12
Work Completed  
Time Computed 11-09-12
Contract Working Days 282
Addl Days Granted 72
Working Days Charged 363
Percent Time Used 102
Contractor(s)
H. L. ZUMWALT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0037-06-084
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.02%)
FLASHER EQUIPMENT COMPANY(2.68%)
ROAD REPAIR, LLC ( 42.36%)
ALL AMERICAN TRUCKING, INC.(4.10%)
FUQUAY, INC. (1.36%)
BEAVER CONTRACTORS, LLC(0.26%)
BEAVER CONTRACTORS, LLC(0.33%)
Contract # 08123206
Totals 14803449.49 122571.46 14750989.05 99.7

CountyWEBB
Highway US 83
From 0.160 MI SOUTH OF SH 255
To US83/IH35 INTERSECTION
CSJ 0037-10-033
Proj ID NH 2014(899)
Work Type ACP OVERLAY, PAV MRKS
 
4.480 1981541.31 0.00 0.00 0.0
Work Order 08-15-14
Work Began 00-00-00
Work Completed  
Time Computed 08-31-14
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0037-10-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143038
Totals 1981541.31 0.00 0.00 0.0

CountyWEBB
Highway SL 20
From 0.457 MI S OF SS 400 (KCS RR OVP)
To 0.450 MI N OF US 59 (STA. 140+00)
CSJ 0086-14-046
Proj ID CBI 2013(281)
Work Type GRAD, WID STRS, BASE AND PAV
 
1.751 33883949.20 0.00 0.00 0.0
CountyWEBB
Highway SL 20
From 0.457 MI S OF SS 400 (KCS RR OVP)
To 0.450 MI N OF US 59 (STA. 140+00)
CSJ 0086-14-056
Proj ID ROW 86-14-56
Work Type ACQUISITION & UTILITY ADJUSTMENTS
 
1.751 1993938.70 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 535
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0086-14-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143002
Totals 35877887.90 0.00 0.00 0.0

CountyWEBB
Highway SL 20
From MANGANA-HEIN ROAD
To CIELITO LINDO
CSJ 0086-16-004
Proj ID C 86-16-4
Work Type GRADING, BASE, STRUCTURES & SURFACE
 
2.292 11417278.20 349918.38 8535199.36 74.7
Work Order 10-18-12
Work Began 01-14-13
Work Completed  
Time Computed 11-03-12
Contract Working Days 351
Addl Days Granted 30
Working Days Charged 363
Percent Time Used 95
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0086-16-004
CABCOS CONTRACTORS LLC (5.22%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.28%)
HIGHWAY TECHNOLOGIES, INC. (0.45%)
KELLYSTONE, INC(1.59%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.40%)
STAR OPERATIONS, INC.(1.52%)
WEBBER, LLC(0.82%)
CERTIFIED PLACERS LLC(0.32%)
NORTH TEXAS REBAR, LLC (0.06%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.05%)
PRIMATE CONSTRUCTION, INC. (0.07%)
ABC EROSION CONTROL, INC.(0.48%)
RGV ALLIANCE CONSTRUCTION, L.L.C.(0.70%)
AARON CONCRETE CONTRACTORS, L.P. (0.33%)
PATRICIA ANN SANCHEZ (DBA) P.A.G. CONCRETE CO. (0.17%)
Contract # 08123042
Totals 11417278.20 349918.38 8535199.36 74.7

CountyLASALLE
Highway SH 44
From BI 35-B
To WEBB EAST COUNTY LINE
CSJ 0237-02-016
Proj ID STP 2014(373)
Work Type MILL , ACP OVERLAY, SIGNS, PAV MRKS
 
17.015 3878123.64 1500.00 1490987.17 38.4
Work Order 03-07-14
Work Began 05-12-14
Work Completed  
Time Computed 03-23-14
Contract Working Days 81
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 28
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0237-02-016
ALTUS TRAFFIC MANAGEMENT LLC (0.26%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.44%)
HIGHWAY BARRICADES AND SERVICES, LLC (6.70%)
Contract # 01143016
Totals 3878123.64 1500.00 1490987.17 38.4

CountyZAVALA
Highway US 57
From MAVERICK COUNTY LINE
To US 83
CSJ 0276-03-041
Proj ID STP 2014(541)
Work Type BASE REPAIR, ACP OVERLAY, PAV MRKS
 
20.481 6111226.85 435338.75 4394495.17 71.9
Work Order 05-01-14
Work Began 06-13-14
Work Completed  
Time Computed 05-17-14
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 60
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0276-03-041
PENHALL COMPANY(0.13%)
ALTUS TRAFFIC MANAGEMENT LLC (0.25%)
MPB, INC.(0.57%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.38%)
FLASHER EQUIPMENT COMPANY(2.11%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) ( 10.31%)
Contract # 03143003
Totals 6111226.85 435338.75 4394495.17 71.9

CountyZAVALA
Highway US 57
From 1.239 MI EAST OF US 83
To FM 117
CSJ 0276-04-024
Proj ID STP 2013(264)
Work Type CONSISTING OF PLANING AND OVERLAY
 
13.407 5829448.19 -156.10 5819916.94 99.8
Work Order 02-13-13
Work Began 05-13-13
Work Completed  
Time Computed 03-01-13
Contract Working Days 100
Addl Days Granted 12
Working Days Charged 112
Percent Time Used 100
Contractor(s)
H. L. ZUMWALT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0276-04-024
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.04%)
FLASHER EQUIPMENT COMPANY(1.74%)
ALL AMERICAN TRUCKING, INC.(3.12%)
Contract # 12123034
Totals 5829448.19 156.10 5819916.94 99.8

CountyMAVERICK
Highway US 277
From US 57
To 10.17 MI EAST
CSJ 0300-01-081
Proj ID C 300-1-81
Work Type GRADE, BASE, STR, ACP, SURF, SIGN, PAV MK
 
38.212 10814536.51 563488.95 4630880.77 42.8
Work Order 09-05-13
Work Began 11-13-13
Work Completed  
Time Computed 09-21-13
Contract Working Days 209
Addl Days Granted 22
Working Days Charged 182
Percent Time Used 78
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0300-01-081
BLACKTOPPER TECHNOLOGY, INC. ( 16.07%)
D. I. J. CONSTRUCTION, INC.(3.38%)
D S TEXAS ICON CONSTRUCTION, LLC (4.15%)
FLASHER EQUIPMENT COMPANY(0.56%)
RELMCO, INC. (7.13%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.79%)
Contract # 06133004
Totals 10814536.51 563488.95 4630880.77 42.8

CountyDUVAL
Highway US 59
From SH 44
To FM 2359
CSJ 0542-04-030
Proj ID NH 2014(900)
Work Type BASE, MILL, ACP INLAY, PAV MRKS
 
11.737 3092471.65 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 198
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0542-04-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143215
Totals 3092471.65 0.00 0.00 0.0

CountyLASALLE
Highway FM 624
From 3.14 MI SOUTH OF FM 469
To 7.57 MI SOUTH OF FM 469
CSJ 0652-05-017
Proj ID STP 2014(732)
Work Type GRAD, BASE, SURF, STRIPING
 
4.426 1455450.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-09-14
Work Began 00-00-00
Work Completed  
Time Computed 09-25-14
Contract Working Days 28
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0652-05-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143025
Totals 1455450.00 0.00 0.00 0.0

CountyWEBB
Highway VA
From LOCATED IN VICINITY OF GSA FACILITY
To COLOMBIA/SOLIDARITY
CSJ 0922-00-025
Proj ID BOR 2010(340)
Work Type CONST SAFETY BORDER INSPEC FACILITY
 
0.687 15396297.93 0.00 15194288.47 98.6
Work Order 02-19-10
Work Began 03-22-10
Work Completed  
Time Computed 03-07-10
Contract Working Days 282
Addl Days Granted 34
Working Days Charged 295
Percent Time Used 93
Contractor(s)
E. E. HOOD & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0922-00-025
HILL COUNTRY FENCE, INC. (0.92%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.11%)
COLLECTIVE CONTRACTING (1.41%)
CF JORDAN CONSTRUCTION LLC ( 19.00%)
BOSQUEZ ELECTRICAL, LLC. (5.03%)
FLASHER EQUIPMENT COMPANY(0.76%)
INTERTECT FLOORING (0.22%)
JUNG TILE SERVICES,INC.(0.21%)
GARDNER & MARTIN (0.04%)
SERVICE SHADE SHOP (0.01%)
TRAUGOTT, INC. PAINTING AND DECORATING (0.92%)
ALAMO DOOR SYSTEMS (0.24%)
CSI MILLWORK (0.24%)
LONGHORN LOCKER(0.05%)
MILLARD DRYWALL(0.69%)
MULTI-GRAPHICS, INC. (0.01%)
R.R. CAUBLE LATH & PLASTER (0.14%)
SOUTHERN STEEL FABRICATORS (3.15%)
TOTAL TERMITE & PEST CONTROL (0.04%)
IVF, INC.(3.09%)
MUSTANG GENERAL CONTRACTING(3.08%)
BALLISTIC PROTECTION GROUP (1.23%)
CROSSROADS SPECIALTIES (0.10%)
M & M SPECIALTY CAULKING (0.20%)
ELLIS AND ELLIS(0.64%)
KAY CONCRETE CONTRACTORS, INC. (2.61%)
KGS CONSTRUCTION, INC. (0.70%)
LOUISIANA CRANE COMPANY, LLC (0.09%)
H. L. ZUMWALT CONSTRUCTION, INC. (5.92%)
FOX & HEARN(3.08%)
FUQUAY, INC. (0.01%)
DOUBLE S PAVING, INC.(0.18%)
C & K CONSTRUCTION ( 19.00%)
TRECO SERVICES, INC. (0.05%)
A-1 SCALE SERVICE, INC.(0.08%)
GEOSOURCE, INC.(0.15%)
HIGHWAY TECHNOLOGIES, INC. (0.08%)
METTLER TOTLEDO(3.41%)
PARADIGM TRAFFIC_INC.(0.00%)
THE SAN ANTONIO TELEPHONE COMPANY INC. (0.64%)
ZINSMEYER MECHANICAL & WELDING, LTD. (0.09%)
ADVANCED CONCRETE PROTECTION (0.18%)
Contract # 12093201
Totals 15396297.93 0.00 15194288.47 98.6

CountyWEBB
Highway VA
From DISTRICTWIDE
To WEBB COUNTY, ETC.
CSJ 0922-00-054
Proj ID STP 2013(938)G
Work Type METAL BEAM GUARD FENCE AND SGT
 
0.100 578205.90 38920.00 518957.98 91.6
Work Order 10-24-13
Work Began 11-18-13
Work Completed  
Time Computed 11-09-13
Contract Working Days 145
Addl Days Granted 0
Working Days Charged 163
Percent Time Used 112
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0922-00-054
ENVIRONMENTAL SAFETY SERVICES, INC.(7.64%)
Contract # 08133032
Totals 578205.90 38920.00 518957.98 91.6

CountyWEBB
Highway VA
From DISTRICTWIDE
To .
CSJ 0922-00-057
Proj ID STP 1402(073)
Work Type UPGRADE BRIDGE RAIL AND MBGF
 
0.100 912820.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 178
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0922-00-057
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143245
Totals 912820.00 0.00 0.00 0.0

CountyWEBB
Highway VA
From VARIOUS LOCATIONS IN WEBB & DUVAL
To .
CSJ 0922-00-059
Proj ID STP 2012(541)
Work Type CONSTRUCT CURB RAMPS
 
0.100 2192500.00 0.00 1823968.02 83.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-12-12
Work Began 08-23-12
Work Completed  
Time Computed 07-28-12
Contract Working Days 295
Addl Days Granted 5
Working Days Charged 300
Percent Time Used 100
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0922-00-059
HIGHWAY BARRICADES AND SERVICES, LLC (1.48%)
VALLEY STRIPING CORP.(3.51%)
D&G ENERGY CORPORATION (6.26%)
Contract # 05123230
Totals 2192500.00 0.00 1823968.02 83.1

page 1 | page 2