Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyZAVALA
Highway US 57
From FM 117
To FRIO COUNTY LINE
CSJ 0276-05-026
Proj ID STP 1502(254)
Work Type ONE COURSE SURFACE TREAT, PAV MRKS
 
32.067 6314120.64 0.00 7492543.72 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-04-15
Work Began 12-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 90
Percent Time Used 90
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0276-05-026
PRIMATE CONSTRUCTION, INC. (0.30%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.47%)
COWBELL TRAFFIC SERVICES, INC. (0.48%)
FLASHER EQUIPMENT COMPANY(3.27%)
ENVIRONMENTAL SAFETY SERVICES, INC.(6.15%)
Contract # 06153026
Totals 6314120.64 0.00 7492543.72 99.9

CountyMAVERICK
Highway US 277 ETC
From @ NORTH ST
To .
CSJ 0299-04-070
Proj ID STP 2016(066)HES
Work Type IMPROVE TRAFFIC SIGNALS
 
1.000 315267.29 0.00 68151.00 21.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-22-15
Work Began 04-25-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 112
Addl Days Granted 0
Working Days Charged 74
Percent Time Used 66
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0299-04-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09153021
Totals 315267.29 0.00 68151.00 21.6

CountyMAVERICK
Highway US 277 ETC
From SL 480
To 11.960 MI W OF DIMMIT COUNTY LINE
CSJ 0300-01-091
Proj ID STP 1602(174)HESG
Work Type TEXTURIZE SHOULDERS CENTERLINE TEXT
 
50.697 307234.04 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0300-01-091
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163024
Totals 307234.04 0.00 0.00 0.0

CountyDIMMIT
Highway US 277
From FM 393
To SL 517
CSJ 0300-03-066
Proj ID NH 2016(478)
Work Type PLANING, ACP, OVERLAY PAV MRK
 
30.560 9546333.92 0.00 2294270.81 24.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-29-16
Work Began 06-27-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 205
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 10
Contractor(s)
H. L. ZUMWALT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0300-03-066
CHEROKEE SERVICES(0.34%)
FLASHER EQUIPMENT COMPANY(1.83%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.00%)
Contract # 01163217
Totals 9546333.92 0.00 2294270.81 24.0

CountyDIMMIT
Highway SH 85
From US 83
To 1.20 MI WEST OF FM 1867
CSJ 0301-01-075
Proj ID STP 2015(741)
Work Type ACP OVERLAY, PAV MRK
 
29.826 9781744.13 36533.50 9912528.70 99.9
Work Order 04-28-15
Work Began 06-08-15
Work Completed  
Time Computed 05-29-15
Contract Working Days 142
Addl Days Granted 0
Working Days Charged 140
Percent Time Used 98
Contractor(s)
H. L. ZUMWALT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0301-01-075
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.74%)
FLASHER EQUIPMENT COMPANY(3.92%)
BEAVER CONTRACTORS, LLC(2.54%)
SAN GERONIMO CONTRACTORS (0.40%)
Contract # 03153201
Totals 9781744.13 36533.50 9912528.70 99.9

CountyLASALLE
Highway SH 97
From FRIO RIVER BRIDGE
To .
CSJ 0328-08-022
Proj ID BR 1502(514)
Work Type REPLACEMENT OF EXISTING BRIDGE
 
0.160 8315541.28 0.00 1697069.74 20.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-30-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 373
Addl Days Granted 70
Working Days Charged 17
Percent Time Used 5
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0328-08-022
FLASHER EQUIPMENT COMPANY(1.14%)
D&S TEXAS ICON CONSTRUCTION(1.52%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.59%)
AARON CONCRETE CONTRACTORS, L.P. (1.78%)
PRIMATE CONSTRUCTION, INC. (0.32%)
VOGES DRILLING CO. (4.79%)
CUATRO T CONSTRUCTION, INC.(0.67%)
Contract # 08153038
Totals 8315541.28 0.00 1697069.74 20.4

CountyLASALLE
Highway SH 97
From 0.038 MI W OF BU 35
To 0.095 MI E OF BU 35
CSJ 0483-01-046
Proj ID STP 1302(033)
Work Type CONCRETE INTERSECTION
 
0.531 2157787.20 0.00 647522.15 30.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-22-15
Work Began 05-31-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 141
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 29
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0483-01-046
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. ( 10.41%)
D&S TEXAS ICON CONSTRUCTION(1.38%)
FLASHER EQUIPMENT COMPANY(1.95%)
FUQUAY, INC. (0.78%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.91%)
PATRICIA ANN SANCHEZ (DBA) P.A.G. CONCRETE CO. (2.27%)
Contract # 07153063
Totals 2157787.20 0.00 647522.15 30.0

CountyLASALLE
Highway SH 97 ETC
From FM 469
To 2.918 MI W OF LASALLE/MCMULLEN C/L
CSJ 0483-01-051
Proj ID STP 2016(401)
Work Type SURF TREATMENT, PAV MRK
 
73.069 2781568.60 0.00 2784902.42 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 04-04-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 148
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 41
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0483-01-051
FLASHER EQUIPMENT COMPANY(1.50%)
VIZCAINO, L.P. ( 14.98%)
CHEROKEE SERVICES(1.28%)
Contract # 12153019
Totals 2781568.60 0.00 2784902.42 99.9

CountyWEBB
Highway US 59 ETC
From CASA DEL SOL
To IH 35
CSJ 0542-01-083
Proj ID STP 1602(512)HES
Work Type IMPROVE TRAFFIC SIGNALS
 
16.169 1680643.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 145
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0542-01-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163225
Totals 1680643.30 0.00 0.00 0.0

CountyDUVAL
Highway US 59
From 5.3 MI N OF SH 44
To MCMULLEN COUNTY LINE
CSJ 0542-04-031
Proj ID NH 1502(452)
Work Type GRADE, MBGF, ACP OVERLAY, PAV MKS
 
12.904 8814670.68 0.00 8527040.10 96.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-06-15
Work Began 01-09-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 100
Percent Time Used 100
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0542-04-031
ALTUS TRAFFIC MANAGEMENT LLC (0.11%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.54%)
D&S TEXAS ICON CONSTRUCTION(0.38%)
RPV CONSTRUCTION (2.84%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.20%)
Contract # 07153219
Totals 8814670.68 0.00 8527040.10 96.7

CountyWEBB
Highway VA
From DISTRICTWIDE
To .
CSJ 0922-00-056
Proj ID STP 1602(137)
Work Type UPGRADE RAIL
 
1.396 1498321.43 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-08-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 281
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0922-00-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163214
Totals 1498321.43 0.00 0.00 0.0

CountyWEBB
Highway VA
From DISTRICTWIDE
To .
CSJ 0922-00-057
Proj ID STP 1402(073)
Work Type UPGRADE BRIDGE RAIL AND MBGF
 
0.100 912820.00 0.00 807115.18 91.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-23-14
Work Began 12-03-14
Work Completed  
Time Computed 10-09-14
Contract Working Days 178
Addl Days Granted 20
Working Days Charged 244
Percent Time Used 123
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0922-00-057
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143245
Totals 912820.00 0.00 807115.18 91.4

CountyLASALLE
Highway VA
From REPAIR BRIDGE RAIL ALONG IH 35
To .
CSJ 0922-20-017
Proj ID BR 1502(453)
Work Type UPGRADE BRIDGE RAIL
 
0.200 2001775.85 0.00 1816233.03 90.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-09-15
Work Began 12-14-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 164
Percent Time Used 91
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0922-20-017
FLASHER EQUIPMENT COMPANY(1.58%)
RPV CONSTRUCTION ( 30.18%)
D & S TEXAS ICON CONSTRUCTION, LLC.(4.25%)
Contract # 07153242
Totals 2001775.85 0.00 1816233.03 90.7

CountyWEBB
Highway CR
From ON LINCOLN RD AT BECERRA CREEK
To 17.60 MI N OF US 59
CSJ 0922-33-113
Proj ID BR 1502(352)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.527 855593.80 0.00 552518.63 64.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-12-15
Work Began 01-13-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 129
Addl Days Granted 0
Working Days Charged 71
Percent Time Used 55
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0922-33-113
ALTUS TRAFFIC MANAGEMENT LLC (1.06%)
BEAVER CONTRACTORS, LLC( 19.87%)
FUQUAY, INC. (4.03%)
IZAGUIRRE CONSTRUCTION (3.76%)
Contract # 08153251
Totals 855593.80 0.00 552518.63 64.5

CountyWEBB
Highway CR
From ON MINES ROAD AT ESPADA CREEK
To AT 22.6 MI N OF SH 255
CSJ 0922-33-157
Proj ID BR 2016(736)
Work Type REPLACE STRUCTURES AND APPROACHES
 
0.027 597832.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0922-33-157
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163026
Totals 597832.00 0.00 0.00 0.0

CountyDIMMIT
Highway FM 1019
From FM 468
To END OF PAVEMENT
CSJ 1270-01-026
Proj ID STP 1502(455)HES
Work Type WIDEN, BASE, GRADE, ACP, STR, MBGF, PMK
 
6.314 3036840.45 0.00 2898240.38 95.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-05-15
Work Began 12-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 119
Addl Days Granted 0
Working Days Charged 112
Percent Time Used 94
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1270-01-026
MURRAY CONSTRUCTION(0.74%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.77%)
FLASHER EQUIPMENT COMPANY(1.99%)
MV HENKE COMPANY, LLC(3.33%)
RELMCO, INC. (4.34%)
Contract # 07153028
Totals 3036840.45 0.00 2898240.38 95.4

CountyZAVALA
Highway FM 1025
From US 83
To FM 117
CSJ 1279-01-036
Proj ID STP 1302(036)
Work Type GRADE, WIDEN, STR, SURF TREAT, PAV MRKS
 
19.855 7134438.21 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-03-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 322
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1279-01-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163208
Totals 7134438.21 0.00 0.00 0.0

CountyDIMMIT
Highway FM 468
From FM 1019 INTERSECTION
To LA SALLE COUNTY LINE
CSJ 1545-01-015
Proj ID STP 2014(567)
Work Type BASE REPAIR, ACP OV, SIGNS & PV MRKS
 
7.468 5795930.18 0.00 5634494.87 97.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-09-14
Work Began 01-05-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 168
Addl Days Granted 0
Working Days Charged 168
Percent Time Used 100
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1545-01-015
ALTUS TRAFFIC MANAGEMENT LLC (0.28%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.28%)
PENHALL COMPANY(0.20%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.71%)
D S TEXAS ICON CONSTRUCTION, LLC (1.54%)
Contract # 06143055
Totals 5795930.18 0.00 5634494.87 97.2

CountyLASALLE
Highway FM 468
From FM 469
To DIMMIT COUNTY LINE
CSJ 1545-02-021
Proj ID STP 1502(456)
Work Type GRADING, BASE, SURFACING & PAV MRKS
 
27.923 9571743.10 0.00 7321001.33 76.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-11-15
Work Began 11-02-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 223
Addl Days Granted 0
Working Days Charged 183
Percent Time Used 82
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1545-02-021
ALTUS TRAFFIC MANAGEMENT LLC (0.46%)
CHEROKEE SERVICES(0.10%)
FLASHER EQUIPMENT COMPANY(1.90%)
ROADWAY SPECIALTIES, INC.(1.96%)
CLARK CONSTRUCTION OF TEXAS, INC.(6.47%)
Contract # 07153046
Totals 9571743.10 0.00 7321001.33 76.4

CountyZAVALA
Highway FM 2691
From FM 393
To END OF PAVEMENT
CSJ 1937-02-026
Proj ID STP 1502(458)HES
Work Type BASE, GRADE, ACP, STRT, MBGF, PAV MKS
 
8.476 3007204.02 0.00 2800119.38 93.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-06-15
Work Began 11-09-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 103
Addl Days Granted 46
Working Days Charged 102
Percent Time Used 68
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1937-02-026
TEXAS CUTTING & CORING, INC. (0.37%)
D & S TEXAS ICON CONSTRUCTION, LLC.(1.77%)
EGGEMEYER LAND CLEARING, LLC (2.65%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.60%)
FLASHER EQUIPMENT COMPANY(3.66%)
Contract # 07153060
Totals 3007204.02 0.00 2800119.38 93.1