Monthly Local Let Maintenance Report For Laredo District As Of Jul 14, 2017 Page 2 Of 3

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWEBB
HighwayIH0035
FromVARIOUS
ToVARIOUS
CSJ6295-31-001
Proj IDSUP - 629531001
Work TypePICNIC AREA MAINTENANCE
 
0.00177768.0858666.2775.4
Work Order10-08-15
Work Began10-15-15
Work Completed
Time Computed10-15-15
Contract Working Days731
Addl Days Granted0
Working Days Charged623
Percent Time Used85
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10152231
Totals77768.083404.7258666.2775.4

CountyVAL VERDE
HighwayUS0277
FromUS 277
ToVARIOUS
CSJ6296-98-001
Proj IDRMC - 629698001
Work TypeINSTALL PVT. MARKINGS AND PVT. MARKERS
 
0.001267451.12100301.6437.5
Work Order07-11-16
Work Began07-11-16
Work Completed
Time Computed07-11-16
Contract Working Days365
Addl Days Granted128
Working Days Charged355
Percent Time Used72
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162201
Totals267451.120.00100301.6437.5

CountyWEBB
HighwayIH0035
FromIH 35
ToUS 83, ETC.
CSJ6297-22-001
Proj IDRMC - 629722001
Work TypeLANDSCAPE MAINTENANCE
 
7.000214488.00109540.0051.0
Work Order04-27-16
Work Began04-28-16
Work Completed
Time Computed04-28-16
Contract Working Days730
Addl Days Granted0
Working Days Charged427
Percent Time Used58
Contractor(s)
RK POWER DRIVE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01162204
Totals214488.000.00109540.0051.0

CountyWEBB
HighwaySL0020
FromSL 20
ToVARIOUS
CSJ6297-39-001
Proj IDRMC - 629739001
Work TypeLANDSCAPE MAINTENANCE
 
2.000228036.50249095.3099.9
Work Order04-27-16
Work Began04-28-16
Work Completed
Time Computed04-28-16
Contract Working Days365
Addl Days Granted365
Working Days Charged427
Percent Time Used58
Contractor(s)
RK POWER DRIVE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01162206
Totals228036.5019630.95249095.3099.9

CountyWEBB
HighwayUS0083
FromUS 83
ToVARIOUS
CSJ6299-31-001
Proj IDRMC - 629931001
Work TypeCLEANING AND SWEEPING OF HIGHWAYS
 
66.010187777.7430163.6516.0
Work Order04-28-17
Work Began05-01-17
Work Completed
Time Computed05-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged59
Percent Time Used16
Contractor(s)
CTX SPECIAL SERVICES CO LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02172201
Totals187777.7415332.2630163.6516.0

CountyWEBB
HighwayIH0035
FromIH 35
ToVARIOUS
CSJ6299-42-001
Proj IDRMC - 629942001
Work TypeCLEANING AND SWEEPING OF HIGHWAYS
 
85.880299280.0060324.0020.1
Work Order04-01-17
Work Began04-03-17
Work Completed
Time Computed04-03-17
Contract Working Days365
Addl Days Granted0
Working Days Charged89
Percent Time Used24
Contractor(s)
RK POWER DRIVE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02172202
Totals299280.0020108.0060324.0020.1

CountyWEBB
HighwayIH0035
FromIH 35
ToVARIOUS
CSJ6300-77-001
Proj IDRMC - 630077001
Work TypeMAINTENANCE OF ILLUMINATION SYSTEMS ALON
 
0.001120800.0050000.0041.3
Work Order07-29-16
Work Began08-01-16
Work Completed
Time Computed08-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged332
Percent Time Used45
Contractor(s)
TRIPLE H FIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6300-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07162201
Totals120800.005000.0050000.0041.3

CountyVAL VERDE
HighwayUS0090
FromUS 277
ToVARIOUS
CSJ6301-03-001
Proj IDRMC - 630103001
Work TypeUPGRADE OF EXISTING MBGF, DOWNSTREAM ANC
 
0.001312383.64247113.7279.1
Work Order08-08-16
Work Began08-15-16
Work Completed
Time Computed08-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
ELITE CASTLE RESOURCES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6301-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05162203
Totals312383.6434155.76247113.7279.1

CountyWEBB
HighwayIH0035
FromIH 35
ToVARIOUS
CSJ6301-09-001
Proj IDRMC - 630109001
Work TypeINSTALL PVT. MARKINGS AND PVT. MARKERS
 
0.001262806.47389408.08100.0
Work Order04-11-17
Work Began04-11-17
Work Completed07-13-17
Time Computed04-11-17
Contract Working Days365
Addl Days Granted0
Working Days Charged81
Percent Time Used22
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162202
Totals262806.470.00389408.08100.0

CountyVAL VERDE
HighwaySS0239
FromDEL RIO TXDOT COMPLEX
ToDEL RIO TXDOT COMPLEX
CSJ6301-67-001
Proj IDRMC - 630167001
Work TypeLANDSCAPE MAINTENANCE
 
0.00111200.004700.0041.9
Work Order12-01-16
Work Began12-15-16
Work Completed
Time Computed12-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged198
Percent Time Used54
Contractor(s)
DELGADO'S CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6301-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11162201
Totals11200.000.004700.0041.9

CountyKINNEY
HighwayUS0090
FromUS 90
ToVARIOUS
CSJ6302-58-001
Proj IDRMC - 630258001
Work TypeUPGRADE OF EXISTING BRIDGE RAIL
 
0.001194084.00113628.3658.5
Work Order01-23-17
Work Began01-23-17
Work Completed
Time Computed01-23-17
Contract Working Days60
Addl Days Granted0
Working Days Charged31
Percent Time Used51
Contractor(s)
DELGADO'S CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6302-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11162202
Totals194084.0032310.00113628.3658.5

CountyWEBB
HighwayIH0035
FromIH 35
ToVARIOUS
CSJ6305-19-001
Proj IDSUP - 630519001
Work TypeLITTER PICKUP MAINTENANCE
 
0.001276022.22264512.5795.8
Work Order06-28-16
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted62
Working Days Charged365
Percent Time Used85
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162231
Totals276022.2226869.08264512.5795.8

CountyMAVERICK
HighwayUS0277
FromUS 277
ToVARIOUS
CSJ6305-28-001
Proj IDSUP - 630528001
Work TypePICNIC AREA MAINTENANCE
 
0.00160934.8030467.4050.0
Work Order06-28-16
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged365
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162232
Totals60934.802652.4030467.4050.0

CountyDIMMIT
HighwayUS0083
FromUS 83
ToVARIOUS
CSJ6305-70-001
Proj IDRMC - 630570001
Work TypeMOWING OF HIGHWAYS RIGHT-OF-WAY
 
246.200271941.57118622.3443.6
Work Order10-18-16
Work Began10-24-16
Work Completed
Time Computed10-24-16
Contract Working Days365
Addl Days Granted0
Working Days Charged250
Percent Time Used68
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6305-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162202
Totals271941.570.00118622.3443.6

CountyVAL VERDE
HighwayUS0277
FromUS 277
ToVARIOUS
CSJ6307-52-001
Proj IDRMC - 630752001
Work TypeINSTALL TRAFFIC SIG., FLASH BEACONS PVT
 
0.001168873.2541383.5524.5
Work Order11-22-16
Work Began11-22-16
Work Completed
Time Computed11-22-16
Contract Working Days365
Addl Days Granted0
Working Days Charged221
Percent Time Used60
Contractor(s)
TRIPLE H FIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6307-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162204
Totals168873.250.0041383.5524.5

CountyVAL VERDE
HighwaySL0025
FromVARIOUS
To.
CSJ6308-23-001
Proj IDSUP - 630823001
Work TypeJANITORIAL AND GROUNDS
 
0.001140119.2023158.5916.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-25-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days720
Addl Days Granted0
Working Days Charged122
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162203
Totals140119.200.0023158.5916.5

CountyZAVALA
HighwayUS0083
FromUS 83
ToVARIOUS
CSJ6309-73-001
Proj IDRMC - 630973001
Work TypeMOWING OF HIGHWAYS RIGHT-OF-WAY
 
0.001345279.80172757.6250.0
Work Order12-21-16
Work Began12-21-16
Work Completed
Time Computed12-21-16
Contract Working Days730
Addl Days Granted0
Working Days Charged212
Percent Time Used29
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6309-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11162203
Totals345279.8015559.15172757.6250.0

CountyVAL VERDE
HighwaySS0239
FromDEL RIO AREA/MAINTENANCE COMPLEX
ToDEL RIO AREA/MAINTENANCE COMPLEX
CSJ6310-71-001
Proj IDSUP - 631071001
Work TypeJANITORIAL MAINTENANCE @ DEL RIO COMPLEX
 
0.00137664.528976.6923.8
Work Order12-01-16
Work Began12-01-16
Work Completed
Time Computed12-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged212
Percent Time Used29
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11162231
Totals37664.521429.198976.6923.8

CountyDIMMIT
HighwayUS0083
FromUS 83
ToVARIOUS
CSJ6310-77-001
Proj IDRMC - 631077001
Work TypeCLEAN/SWEEP OF HIGHWAYS AND LITTER PICKU
 
57.000120951.5657014.0747.1
Work Order01-23-17
Work Began01-23-17
Work Completed
Time Computed01-23-17
Contract Working Days365
Addl Days Granted0
Working Days Charged159
Percent Time Used43
Contractor(s)
CTX SPECIAL SERVICES CO LLC
SUBCONTRACTOR(S) FOR CCSJ: 6310-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11162204
Totals120951.5617002.5157014.0747.1

CountyMAVERICK
HighwayUS0277
FromUS 277
ToVARIOUS
CSJ6311-22-001
Proj IDRMC - 631122001
Work TypeCLEANING/SWEEPING OF HIGHWAYS AND LITTER
 
0.001269060.5454013.5420.0
Work Order04-27-17
Work Began05-01-17
Work Completed
Time Computed05-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
CROSBY RD CONSTRUCTION INC
SUBCONTRACTOR(S) FOR CCSJ: 6311-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172201
Totals269060.5427800.1454013.5420.0