Monthly Local Let Maintenance Report For Laredo District As Of Jun 10, 2015 Page 3 Of 4

Last Update: Wednesday, June 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLASALLE
Highway IH0035
From IH 35
To VARIOUS
CSJ 6269-77-001
Proj ID RMC - 626977001
Work Type MOWING OF HIGHWAYS RIGHT - OF - WAY
 
192.400 235474.53 0.00 108223.03 45.9
Work Order 06-26-14
Work Began 07-14-14
Work Completed  
Time Computed 07-14-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 322
Percent Time Used 44
Contractor(s)
COASTAL MAINTENANCE
SUBCONTRACTOR(S) FOR CCSJ: 6269-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05142204
Totals 235474.53 0.00 108223.03 45.9

CountyKINNEY
Highway US0090
From 1.0 MI E OF SH 131
To 0.008 MI E
CSJ 6270-21-001
Proj ID BPM - 627021001
Work Type REHABILITATION OF A BRIDGE FACILITY
 
0.008 310951.29 167232.41 167232.41 53.7
Work Order 05-04-15
Work Began 05-13-15
Work Completed  
Time Computed 05-13-15
Contract Working Days 37
Addl Days Granted 0
Working Days Charged 13
Percent Time Used 35
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6270-21-001
DUSTROL, INC.(2.51%)
FLASHER EQUIPMENT COMPANY(8.11%)
Contract # 02152202
Totals 310951.29 167232.41 167232.41 53.7

CountyMAVERICK
Highway US0277
From US 277
To VARIOUS
CSJ 6270-30-001
Proj ID RMC - 627030001
Work Type CLEANING, SWEEPING AND LITTER PICKUP
 
66.480 164236.00 3161.55 67567.20 41.1
Work Order 07-18-14
Work Began 07-21-14
Work Completed  
Time Computed 07-21-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 335
Percent Time Used 91
Contractor(s)
M & M STRIPING & POWER WASHING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6270-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06142203
Totals 164236.00 3161.55 67567.20 41.1

CountyWEBB
Highway IH0035
From VARIOUS
To VARIOUS
CSJ 6270-92-001
Proj ID RMC - 627092001
Work Type INSTALL RAISED MEDIAN, SIGNING & STRIPIN
 
0.001 298482.30 0.00 45694.55 15.3
Work Order 02-05-15
Work Began 02-09-15
Work Completed  
Time Computed 02-09-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 112
Percent Time Used 30
Contractor(s)
GILMAR CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6270-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05142201
Totals 298482.30 0.00 45694.55 15.3

CountyVAL VERDE
Highway US0090
From VARIOUS
To .
CSJ 6271-94-001
Proj ID SUP - 627194001
Work Type JANITORIAL, GROUNDS, LANDSCAPING
 
0.001 23990.40 0.00 24774.40 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-01-14
Work Began 00-00-00
Work Completed  
Time Computed 04-01-14
Contract Working Days 153
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 79
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6271-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03142231
Totals 23990.40 0.00 24774.40 99.9

CountyWEBB
Highway IH0035
From VARIOUS
To VARIOUS
CSJ 6272-30-001
Proj ID SUP - 627230001
Work Type LITTER PICKUP MAINTENANCE - WEBB / DIMMIT
 
0.001 241170.36 15053.45 255997.24 99.9
Work Order 03-31-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 365
Addl Days Granted 61
Working Days Charged 426
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03142232
Totals 241170.36 15053.45 255997.24 99.9

CountyWEBB
Highway IH0035
From IH 35
To VARIOUS
CSJ 6272-63-001
Proj ID RMC - 627263001
Work Type TIRE RUBBER DEBRIS REMOVAL ON ROADWAYS
 
150.000 245263.68 17457.84 150574.32 61.3
Work Order 07-18-14
Work Began 08-01-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 304
Percent Time Used 83
Contractor(s)
M & M STRIPING & POWER WASHING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6272-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05142206
Totals 245263.68 17457.84 150574.32 61.3

CountyDUVAL
Highway US0059
From US 59
To VARIOUS
CSJ 6272-72-001
Proj ID RMC - 627272001
Work Type MOWING OF HIGHWAYS RIGHT - OF - WAY
 
331.190 313224.53 18375.44 118415.16 37.8
Work Order 07-21-14
Work Began 08-11-14
Work Completed  
Time Computed 08-11-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 288
Percent Time Used 39
Contractor(s)
COASTAL MAINTENANCE
SUBCONTRACTOR(S) FOR CCSJ: 6272-72-001
K-BAR SERVICES, INC. ( 26.77%)
Contract # 06142202
Totals 313224.53 18375.44 118415.16 37.8

CountyZAVALA
Highway US0083
From VARIOUS
To VARIOUS
CSJ 6273-48-001
Proj ID RMC - 627348001
Work Type MOWING OF HIGHWAYS RIGHT - OF - WAY
 
264.000 255398.00 0.00 58531.46 22.9
Work Order 12-04-14
Work Began 12-04-14
Work Completed  
Time Computed 12-04-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 179
Percent Time Used 24
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6273-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07142201
Totals 255398.00 0.00 58531.46 22.9

CountyVAL VERDE
Highway US0277
From VARIOUS
To VARIOUS
CSJ 6274-64-001
Proj ID RMC - 627464001
Work Type GUARDRAIL REPAIR
 
0.001 285889.50 0.00 0.00 0.0
Work Order 05-18-15
Work Began 05-18-15
Work Completed  
Time Computed 05-18-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 3
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6274-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03152201
Totals 285889.50 0.00 0.00 0.0

CountyWEBB
Highway US0083
From VARIOUS
To VARIOUS
CSJ 6274-84-001
Proj ID RMC - 627484001
Work Type TRAFFIC SIGNALS, FLASH BEACONS, PVT MRKG
 
0.001 369118.40 0.00 0.00 0.0
Work Order 04-29-15
Work Began 05-05-15
Work Completed  
Time Computed 05-05-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 7
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-84-001
GILMAR CONSTRUCTION, LTD.( 12.80%)
PAVEMENT MARKINGS INC. (9.85%)
GREEN LIGHT IN THE GROUND(0.78%)
Contract # 12142201
Totals 369118.40 0.00 0.00 0.0

CountyMAVERICK
Highway US0277
From US 277
To US 57, ETC.
CSJ 6275-06-001
Proj ID SUP - 627506001
Work Type PICNIC AREA MAINTENANCE
 
0.001 56309.20 2465.50 24655.20 43.7
Work Order 06-30-14
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 335
Percent Time Used 45
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06142231
Totals 56309.20 2465.50 24655.20 43.7

CountyVAL VERDE
Highway US0090
From VARIOUS
To .
CSJ 6276-51-001
Proj ID SUP - 627651001
Work Type JANITORIAL, GROUNDS, LANDSCAPING
 
0.001 128326.70 5449.49 47990.67 37.3
Work Order 09-01-14
Work Began 00-00-00
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 1
Working Days Charged 273
Percent Time Used 37
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6276-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08142231
Totals 128326.70 5449.49 47990.67 37.3

CountyWEBB
Highway IH0035
From VARIOUS
To VARIOUS
CSJ 6277-44-001
Proj ID RMC - 627744001
Work Type MAINTENANCE OF LARGE SIGNS
 
0.001 234525.00 20491.44 22341.44 9.5
Work Order 01-23-15
Work Began 01-23-15
Work Completed  
Time Computed 01-23-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 129
Percent Time Used 35
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10142201
Totals 234525.00 20491.44 22341.44 9.5

CountyWEBB
Highway IH0035
From VARIOUS
To VARIOUS
CSJ 6277-48-001
Proj ID RMC - 627748001
Work Type INSTALL PVT. MARKINGS AND PVT. MARKERS
 
0.001 292078.78 0.00 263620.91 90.2
Work Order 02-11-15
Work Began 02-11-15
Work Completed  
Time Computed 02-11-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 118
Percent Time Used 32
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12142202
Totals 292078.78 0.00 263620.91 90.2

CountyVAL VERDE
Highway US0277
From VARIOUS
To VARIOUS
CSJ 6277-50-001
Proj ID RMC - 627750001
Work Type INSTALL PVT. MARKINGS AND PVT. MARKERS
 
0.001 291850.95 0.00 74827.25 25.6
Work Order 02-05-15
Work Began 02-05-15
Work Completed  
Time Computed 02-05-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 116
Percent Time Used 31
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12142203
Totals 291850.95 0.00 74827.25 25.6

CountyWEBB
Highway IH0035
From VARIOUS
To .
CSJ 6277-51-001
Proj ID SUP - 627751001
Work Type JANITORIAL, GROUNDS, LANDSCAPING
 
0.001 273874.10 11630.27 102421.41 37.3
Work Order 09-01-14
Work Began 00-00-00
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 1
Working Days Charged 194
Percent Time Used 26
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6277-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08142232
Totals 273874.10 11630.27 102421.41 37.3

CountyDIMMIT
Highway US0083
From US 83
To VARIOUS
CSJ 6278-03-001
Proj ID RMC - 627803001
Work Type MOWING OF HIGHWAYS RIGHT - OF - WAY
 
247.200 181844.70 0.00 74682.30 41.0
Work Order 12-04-14
Work Began 12-04-14
Work Completed  
Time Computed 12-04-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 179
Percent Time Used 24
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6278-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11142201
Totals 181844.70 0.00 74682.30 41.0

CountyWEBB
Highway US0083
From US 83
To US 83
CSJ 6279-75-001
Proj ID SUP - 627975001
Work Type LANDSCAPE MAINTENANCE
 
0.001 4531.14 0.00 3020.76 66.6
Work Order 09-25-14
Work Began 10-01-14
Work Completed  
Time Computed 10-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 243
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6279-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09142231
Totals 4531.14 0.00 3020.76 66.6

CountyMAVERICK
Highway US0277
From 0.01 MI E. OF FM 1021 AT THE UPRR BRIDGE
To 0.215 MI E.
CSJ 6279-77-001
Proj ID EMC - 627977001
Work Type REHABILITATION OF A BRIDGE FACILITY
 
0.001 104700.00 3130.00 128047.59 100.0
Work Order 01-21-15
Work Began 01-27-15
Work Completed 03-11-15
Time Computed 01-27-15
Contract Working Days 8
Addl Days Granted 4
Working Days Charged 4
Percent Time Used 33
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6279-77-001
FLASHER EQUIPMENT COMPANY(8.82%)
Contract # 11142241
Totals 104700.00 3130.00 128047.59 100.0