Monthly Local Let Maintenance Report For Laredo District As Of Feb 11, 2015 Page 3 Of 4

Last Update: Wednesday, February 11, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWEBB
Highway IH0035
From IH 35
To US 59, ETC.
CSJ 6266-21-001
Proj ID SUP - 626621001
Work Type PICNIC AREA MAINTENANCE
 
0.001 36251.24 0.00 32062.47 100.0
Work Order 10-15-13
Work Began 10-15-13
Work Completed 01-13-15
Time Computed 10-15-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10132231
Totals 36251.24 0.00 32062.47 100.0

CountyDUVAL
Highway US0059
From US 59
To SH 44, ETC.
CSJ 6266-23-001
Proj ID SUP - 626623001
Work Type PICNIC AREA MAINTENANCE
 
0.001 38349.48 0.00 36407.63 100.0
Work Order 10-15-13
Work Began 10-15-13
Work Completed 01-13-15
Time Computed 10-15-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10132232
Totals 38349.48 0.00 36407.63 100.0

CountyLASALLE
Highway IH0035
From IH 35
To VARIOUS
CSJ 6268-15-001
Proj ID RMC - 626815001
Work Type CLEANING AND SWEEPING OF HIGHWAYS / LITTER
 
19.800 56805.48 2701.08 22326.00 39.3
Work Order 05-16-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 243
Percent Time Used 66
Contractor(s)
RK POWER DRIVE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6268-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04142202
Totals 56805.48 2701.08 22326.00 39.3

CountyWEBB
Highway IH0035
From IH 35
To VARIOUS
CSJ 6268-16-001
Proj ID SUP - 626816001
Work Type GUARDRAIL REPAIR
 
0.001 560700.00 49123.75 228018.14 40.6
Work Order 09-12-14
Work Began 09-15-14
Work Completed  
Time Computed 09-15-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 139
Percent Time Used 38
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6268-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07142231
Totals 560700.00 49123.75 228018.14 40.6

CountyWEBB
Highway IH0035
From IH 35
To VARIOUS
CSJ 6268-64-001
Proj ID RMC - 626864001
Work Type MOWING OF HIGHWAYS RIGHT - OF - WAY
 
292.620 196095.60 0.00 122023.80 62.2
Work Order 10-10-14
Work Began 10-16-14
Work Completed  
Time Computed 10-16-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 105
Percent Time Used 28
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6268-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09142201
Totals 196095.60 0.00 122023.80 62.2

CountyVAL VERDE
Highway US0277
From VARIOUS
To VARIOUS
CSJ 6268-89-001
Proj ID RMC - 626889001
Work Type INSTALL PAVEMENT MRKGS AND PAVEMENT MRKS
 
0.001 268816.61 0.00 357004.96 99.9
Work Order 07-23-14
Work Began 07-23-14
Work Completed  
Time Computed 07-23-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 183
Percent Time Used 50
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6268-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04142203
Totals 268816.61 0.00 357004.96 99.9

CountyWEBB
Highway IH0035
From VARIOUS
To VARIOUS
CSJ 6269-73-001
Proj ID RMC - 626973001
Work Type INSTALL PAVEMENT MRKGS AND PAVEMENT MRKR
 
0.001 261912.51 2755.00 364681.06 99.9
Work Order 07-22-14
Work Began 07-22-14
Work Completed  
Time Computed 07-22-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 193
Percent Time Used 52
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04142204
Totals 261912.51 2755.00 364681.06 99.9

CountyWEBB
Highway IH0035
From VARIOUS
To .
CSJ 6269-76-001
Proj ID SUP - 626976001
Work Type JANITORIAL AND GROUNDS MAINTENANCE
 
0.001 80486.56 0.00 77762.16 96.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-01-14
Work Began 02-01-14
Work Completed  
Time Computed 02-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6269-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01142231
Totals 80486.56 0.00 77762.16 96.6

CountyLASALLE
Highway IH0035
From IH 35
To VARIOUS
CSJ 6269-77-001
Proj ID RMC - 626977001
Work Type MOWING OF HIGHWAYS RIGHT - OF - WAY
 
192.400 235474.53 36837.59 108223.03 45.9
Work Order 06-26-14
Work Began 07-14-14
Work Completed  
Time Computed 07-14-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 201
Percent Time Used 27
Contractor(s)
COASTAL MAINTENANCE
SUBCONTRACTOR(S) FOR CCSJ: 6269-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05142204
Totals 235474.53 36837.59 108223.03 45.9

CountyMAVERICK
Highway US0277
From US 277
To VARIOUS
CSJ 6270-30-001
Proj ID RMC - 627030001
Work Type CLEANING, SWEEPING AND LITTER PICKUP
 
66.480 164236.00 17661.35 46406.80 28.2
Work Order 07-18-14
Work Began 07-21-14
Work Completed  
Time Computed 07-21-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 215
Percent Time Used 58
Contractor(s)
M & M STRIPING & POWER WASHING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6270-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06142203
Totals 164236.00 17661.35 46406.80 28.2

CountyWEBB
Highway IH0035
From VARIOUS
To VARIOUS
CSJ 6270-92-001
Proj ID RMC - 627092001
Work Type INSTALL RAISED MEDIAN, SIGNING & STRIPIN
 
0.001 298482.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-05-15
Work Began 02-09-15
Work Completed  
Time Computed 02-09-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GILMAR CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6270-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05142201
Totals 298482.30 0.00 0.00 0.0

CountyVAL VERDE
Highway US0090
From VARIOUS
To .
CSJ 6271-94-001
Proj ID SUP - 627194001
Work Type JANITORIAL, GROUNDS, LANDSCAPING
 
0.001 23990.40 0.00 24774.40 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-01-14
Work Began 00-00-00
Work Completed  
Time Computed 04-01-14
Contract Working Days 153
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 79
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6271-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03142231
Totals 23990.40 0.00 24774.40 99.9

CountyWEBB
Highway IH0035
From VARIOUS
To VARIOUS
CSJ 6272-30-001
Proj ID SUP - 627230001
Work Type LITTER PICKUP MAINTENANCE - WEBB / DIMMIT
 
0.001 241170.36 19214.89 188912.51 78.3
Work Order 03-31-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 303
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03142232
Totals 241170.36 19214.89 188912.51 78.3

CountyWEBB
Highway IH0035
From IH 35
To VARIOUS
CSJ 6272-63-001
Proj ID RMC - 627263001
Work Type TIRE RUBBER DEBRIS REMOVAL ON ROADWAYS
 
150.000 245263.68 14965.20 86083.92 35.0
Work Order 07-18-14
Work Began 08-01-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 184
Percent Time Used 50
Contractor(s)
M & M STRIPING & POWER WASHING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6272-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05142206
Totals 245263.68 14965.20 86083.92 35.0

CountyDUVAL
Highway US0059
From US 59
To VARIOUS
CSJ 6272-72-001
Proj ID RMC - 627272001
Work Type MOWING OF HIGHWAYS RIGHT - OF - WAY
 
331.190 313224.53 0.00 100039.72 31.9
Work Order 07-21-14
Work Began 08-11-14
Work Completed  
Time Computed 08-11-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 173
Percent Time Used 23
Contractor(s)
COASTAL MAINTENANCE
SUBCONTRACTOR(S) FOR CCSJ: 6272-72-001
K-BAR SERVICES, INC. ( 26.77%)
Contract # 06142202
Totals 313224.53 0.00 100039.72 31.9

CountyZAVALA
Highway US0083
From VARIOUS
To VARIOUS
CSJ 6273-48-001
Proj ID RMC - 627348001
Work Type MOWING OF HIGHWAYS RIGHT - OF - WAY
 
264.000 255398.00 18012.02 58531.46 22.9
Work Order 12-04-14
Work Began 12-04-14
Work Completed  
Time Computed 12-04-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 8
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6273-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07142201
Totals 255398.00 18012.02 58531.46 22.9

CountyWEBB
Highway IH0035
From VARIOUS
To VARIOUS
CSJ 6273-66-001
Proj ID RMC - 627366001
Work Type CLEANING AND CRACK SEALING OF HIGHWAYS
 
400.000 185400.00 27448.00 140168.00 100.0
Work Order 11-24-14
Work Began 12-01-14
Work Completed 01-22-15
Time Computed 12-01-14
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 34
Contractor(s)
FYL ENTERPRISES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6273-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08142201
Totals 185400.00 27448.00 140168.00 100.0

CountyMAVERICK
Highway US0277
From VARIOUS
To VARIOUS
CSJ 6273-94-001
Proj ID RMC - 627394001
Work Type CLEANING AND CRACK SEALING OF HIGHWAYS
 
400.000 177000.00 14328.90 165473.50 100.0
Work Order 11-24-14
Work Began 12-01-14
Work Completed 01-15-15
Time Computed 12-01-14
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 30
Contractor(s)
FYL ENTERPRISES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6273-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08142202
Totals 177000.00 14328.90 165473.50 100.0

CountyWEBB
Highway US0083
From VARIOUS
To VARIOUS
CSJ 6274-84-001
Proj ID RMC - 627484001
Work Type TRAFFIC SIGNALS, FLASH BEACONS, PVT MRKG
 
0.001 369118.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12142201
Totals 369118.40 0.00 0.00 0.0

CountyMAVERICK
Highway US0277
From US 277
To US 57, ETC.
CSJ 6275-06-001
Proj ID SUP - 627506001
Work Type PICNIC AREA MAINTENANCE
 
0.001 56309.20 2386.00 15429.40 27.4
Work Order 06-30-14
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 215
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06142231
Totals 56309.20 2386.00 15429.40 27.4