Monthly State Let Construction Report For Pharr District As Of Feb 09, 2018 Page 3 Of 3

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCAMERON
HighwayCS
FromLOS FRESNOS WEST SCHOOL CONNECTION
ToW OF OLEANDER ST TO W OF LONG HORN
CSJ0921-06-286
Proj IDSTP 1602(198)TP
Work TypeCONSTRUCT SIDEWALKS
 
0.100265005.00182995.8569.0
CountyCAMERON
HighwayCS
FromLOS FRESNOS SOUTH RES CONNECTION
ToFROM ALVAREZ COURT TO SH 100
CSJ0921-06-287
Proj IDSTP 1602(198)TP
Work TypeCONSTRUCT SIDEWALKS
 
0.100147710.00180700.8099.9
Work Order01-13-17
Work Began02-21-17
Work Completed
Time Computed02-13-17
Contract Working Days93
Addl Days Granted0
Working Days Charged71
Percent Time Used76
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-06-286
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11163024
Totals412715.001500.00363696.6588.1

CountyWILLACY
HighwayCR
FromCR 156 STR AA01-64-002
ToOLD WEST MAIN DRAIN
CSJ0921-27-035
Proj IDBR 2011(283)
Work TypeREPLACE BRIDGE & RECONST APPROACHES
 
0.064440467.05376103.4585.3
CountyWILLACY
HighwayCR
From#AA01-74-001 @ WEST MAIN DRAIN
To.05 MI W OF BUS 77
CSJ0921-27-036
Proj IDBR 2011(282)
Work TypeREPLACE BRIDGE & RECONST APPROACHES
 
0.057385584.40375380.8297.3
Work Order06-23-14
Work Began11-24-14
Work Completed
Time Computed07-09-14
Contract Working Days184
Addl Days Granted0
Working Days Charged157
Percent Time Used85
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-27-035
RIO GRANDE REBAR PLACING, LTD. (0.51)
LAREDO STRIPING INC. (2.58)
SOIL-TECH, INC. (1.92)
PAVEMENT MARKINGS INC. (0.59)
Contract #04143227
Totals826051.4510665.54751484.2790.9

CountySTARR
HighwayFM 755
FromFM 755 REALIGNMENT, US 83 N.
ToFM 755
CSJ1103-04-027
Proj IDCBI 2014(896)
Work TypeREALIGN/W PARTIAL WIDENING TO 4 LNS
 
2.40010733925.489049211.6988.4
Work Order10-28-14
Work Began01-27-15
Work Completed
Time Computed11-13-14
Contract Working Days380
Addl Days Granted13
Working Days Charged741
Percent Time Used188
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1103-04-027
HIGHWAY BARRICADES AND SERVICES, LLC (1.09)
J & P TRUCKING AND HAULING (5.17)
D S TEXAS ICON CONSTRUCTION, LLC (0.73)
CERTIFIED PLACERS LLC (0.98)
W. W. FOUNDATION DRILLING, LTD. (4.64)
DUSTROL, INC. (0.20)
LAREDO STRIPING INC. (0.84)
AARON CONCRETE CONTRACTORS, L.P. (1.28)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.82)
HUDSON, INC. (0.18)
SOIL-TECH, INC. (0.68)
TREV-CORT TRUCKING, INC. (1.19)
Contract #09143042
Totals10733925.48458277.399049211.6988.4

CountyCAMERON
HighwayFM 803
FromIH-69E @ RANCHO VIEJO AVENUE
To0.077 MI N OF SH 100
CSJ1138-02-015
Proj IDSTP 2014(897)MM
Work TypeREALIGN & WIDEN TO 4 LANES
 
2.76310494854.4811626207.1399.9
Work Order12-17-14
Work Began02-09-15
Work Completed
Time Computed01-02-15
Contract Working Days560
Addl Days Granted70
Working Days Charged630
Percent Time Used100
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1138-02-015
SOIL-TECH, INC. (2.09)
RHYNER CONSTRUCTION SERVICES, INC. (0.49)
LAREDO STRIPING INC. (0.68)
HIGHWAY BARRICADES AND SERVICES, LLC (1.76)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION (OLD PRIME) (1.96)
RIO GRANDE REBAR PLACING, LTD. (0.21)
Contract #09143237
Totals10494854.4841547.5511626207.1399.9

CountyHIDALGO
HighwayFM 907
FromNOLANA LOOP
ToIH-2
CSJ1586-01-069
Proj IDSTP 1702(649)
Work TypeWIDEN TO 4 LN DIV - CURB & GUTTER
 
2.31710446130.301274853.8712.2
Work Order09-18-17
Work Began00-00-00
Work Completed
Time Computed10-18-17
Contract Working Days500
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS CORDIA CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1586-01-069
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173007
Totals10446130.3058764.121274853.8712.2

CountyHIDALGO
HighwayFM 1925
FromFM 681
ToFM 2220
CSJ1803-01-037
Proj IDSTP 2016(127)
Work TypeREHABILITATE ROADWAY
 
5.5238117383.108479106.2899.9
Work Order11-24-15
Work Began02-02-16
Work Completed
Time Computed12-24-15
Contract Working Days420
Addl Days Granted0
Working Days Charged285
Percent Time Used67
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1803-01-037
AUSTIN TRAFFIC SIGNAL CONSTRUCTION (OLD PRIME) (0.78)
GO UNDERGROUND, LIMITED LIABILITY COMPANY (7.11)
HIGHWAY BARRICADES AND SERVICES, LLC (2.18)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (2.74)
D&S TEXAS ICON CONSTRUCTION (2.53)
Contract #10153209
Totals8117383.1019325.008479106.2899.9

CountyCAMERON
HighwayFM 106
FromFM 1847 ON GEN BRANT RD, E & S
ToFM 510
CSJ2243-01-009
Proj IDC 2243-1-9
Work TypeGR, STRS & SURF
 
11.44015555190.8912003661.1777.9
Work Order10-28-14
Work Began11-09-15
Work Completed
Time Computed11-09-15
Contract Working Days420
Addl Days Granted39
Working Days Charged551
Percent Time Used120
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2243-01-009
ALTUS TRAFFIC MANAGEMENT LLC (0.39)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.29)
HIGHWAY BARRICADES AND SERVICES, LLC (0.46)
HURFCO INDUSTRIES, INC. DBA HURRICANE FENCE COMPANY (3.11)
J & P TRUCKING AND HAULING (17.32)
LAREDO STRIPING INC. (0.37)
GULF COAST CONTRACTORS, INC. (1.91)
EZ FENCE (0.39)
Contract #09143004
Totals15555190.89443862.9912003661.1777.9

CountyHIDALGO
HighwaySH 364
FromSH 495 N
ToFM 1924
CSJ2966-01-009
Proj IDC 2966-1-9
Work TypeGRADING, STRUCTURES & SURFACING
 
2.0006848709.564837302.1370.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-21-15
Work Began02-16-16
Work Completed
Time Computed00-00-00
Contract Working Days400
Addl Days Granted33
Working Days Charged283
Percent Time Used65
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 2966-01-009
GULF COAST CONTRACTORS, INC. (0.92)
HIGHWAY BARRICADES AND SERVICES, LLC (1.25)
MUSTANG COLT SERVICES, INC. (4.14)
CERTIFIED PLACERS LLC (0.09)
Contract #11153214
Totals6848709.56146050.194837302.1370.6

page 1 | page 2 | page 3