Monthly State Let Construction Report For Waco District As Of Jul 12, 2016 Page 2 Of 3

Last Update: Tuesday, July 12, 2016
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHAMILTON
Highway US 281
From SOUTH HAMILTON C/L
To US 84 IN EVANT
CSJ 0251-02-047
Proj ID STP 2014(011)
Work Type REHAB RDWY & ADD PASS LNS
 
14.545 9687836.94 0.00 9947046.93 99.9
Work Order 12-03-13
Work Began 12-16-13
Work Completed  
Time Computed 12-16-13
Contract Working Days 426
Addl Days Granted 18
Working Days Charged 444
Percent Time Used 100
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0251-02-047
D. I. J. CONSTRUCTION, INC.(0.99%)
DUSTROL, INC.(0.11%)
SAN-ANN-CO., INC.(0.45%)
TEXAS ALTERNATIVE GRASSER, INC.(0.80%)
ROADWAY SPECIALTIES, INC.(2.91%)
PRIMATE CONSTRUCTION, INC. (0.26%)
J & M CONTRACTING, COMPANY ( 10.61%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.09%)
NIXON ENGINEERING(0.00%)
BRYDL CONTRACTING, INC.(0.07%)
BROCK CONSTRUCTION, LLC(0.22%)
Contract # 09133019
Totals 9687836.94 0.00 9947046.93 99.9

CountyBOSQUE
Highway SH 6
From HAMILTON CO LINE
To CR 2139
CSJ 0258-04-034
Proj ID NH 2016(745)
Work Type UNDERSEAL / LEVELUP / OVERLAY
 
19.839 5936805.87 1380452.86 4127317.61 69.5
Work Order 03-29-16
Work Began 04-11-16
Work Completed  
Time Computed 07-15-16
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 44
Percent Time Used 73
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0258-04-034
FLASHER EQUIPMENT COMPANY(0.16%)
ODUM SERVICES, L.P.(3.13%)
SCR CONSTRUCTION CO., INC. (0.40%)
D. I. J. CONSTRUCTION, INC.(1.84%)
WOLFE CONSTRUCTION GROUP, INC. (0.14%)
NIXON ENGINEERING(0.00%)
Contract # 02163008
Totals 5936805.87 1380452.86 4127317.61 69.5

CountyMCLENNAN
Highway SH 6
From BUFFALO COUNTRY RD IN VALLEY MILLS
To LADY BIRD RD
CSJ 0258-08-032
Proj ID STP 2013(587)
Work Type REHAB RDWY, ADD PASS LNS
 
9.669 4687935.11 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 234
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0258-08-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163015
Totals 4687935.11 0.00 0.00 0.0

CountyMCLENNAN
Highway SH 6
From LADY BIRD RD
To 0.5 MI N OF SP 412
CSJ 0258-08-033
Proj ID NH 2013(945)
Work Type ADD LFT TRN LN & SHLDRS
 
1.100 1946235.87 3575.00 1918619.24 99.1
Work Order 09-30-14
Work Began 06-26-15
Work Completed  
Time Computed 12-29-14
Contract Working Days 107
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 114
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0258-08-033
FORTSON CONTRACTING, INC.(1.78%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(8.86%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.51%)
TEXAS ALTERNATIVE GRASSER, INC.(0.51%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.58%)
JOY LATTIMER, LLC. (1.54%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.57%)
PIPE WHOLESALERS OF TEXAS, INC.(2.19%)
Contract # 07143029
Totals 1946235.87 3575.00 1918619.24 99.1

CountyMCLENNAN
Highway SH 6
From SP 412
To 0.5 MI N OF SP 412
CSJ 0258-08-034
Proj ID NH 2016(830)
Work Type MILL / SEAL / INLAY
 
0.549 288197.40 0.00 0.00 0.0
CountyMCLENNAN
Highway SH 6
From FM 3476
To SP 412
CSJ 0258-09-139
Proj ID NH 2016(830)
Work Type MILL / SEAL / INLAY
 
9.226 5380793.71 0.00 0.00 0.0
CountyMCLENNAN
Highway SH 6
From @ LAKE WACO (NB MAINLANE)
To (STR #067)
CSJ 0258-09-140
Proj ID BR 1602(037)
Work Type REHAB BR & APPRS
 
0.743 4331178.40 0.00 0.00 0.0
CountyMCLENNAN
Highway SH 6
From @ LAKE WACO (SB MAINLANE)
To (STR #068)
CSJ 0258-09-141
Proj ID BR 1602(037)
Work Type REHAB BR & APPRS
 
0.743 4481138.90 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-12-16
Work Began 00-00-00
Work Completed  
Time Computed 07-11-16
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0258-09-139
N-LINE TRAFFIC MAINTENANCE, L.P. (0.37%)
APAC-TEXAS, INC. ( 22.26%)
ROADWAY SPECIALTIES, INC.(0.06%)
GK CONSTRUCTION, LLC (1.01%)
A. H. BECK FOUNDATION CO., INC.( 20.45%)
ODUM SERVICES, L.P.(0.08%)
FLASHER EQUIPMENT COMPANY(2.19%)
A BROTHERS MILLING, LLC(0.97%)
WEST TEXAS RUMBLE STRIP(0.10%)
CHEROKEE SERVICES(1.91%)
C-HOP CONSTRUCTION (0.60%)
POTTER TRUCKING(0.89%)
Contract # 03163002
Totals 14481308.41 0.00 0.00 0.0

CountyMCLENNAN
Highway SH 6
From IH 35
To US 77
CSJ 0258-09-111
Proj ID C 258-9-111
Work Type CONSTR OP / RAMPS; EXTEND FRTG RDS
 
1.949 22387388.26 587723.00 4327002.37 19.3
Work Order 02-10-16
Work Began 03-07-16
Work Completed  
Time Computed 03-07-16
Contract Working Days 701
Addl Days Granted 0
Working Days Charged 84
Percent Time Used 11
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0258-09-111
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(3.62%)
FLASHER EQUIPMENT COMPANY(0.55%)
BRICK PAVING PLUS, INC.(0.56%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.65%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.37%)
JUST GROOVING, LTD.(0.04%)
ROADWAY SPECIALTIES, INC.(0.49%)
FORTSON CONTRACTING, INC.(0.38%)
WEST TEXAS RUMBLE STRIP(0.02%)
ABC EROSION CONTROL, INC.(0.36%)
Contract # 12153203
Totals 22387388.26 587723.00 4327002.37 19.3

CountyMCLENNAN
Highway SH 6
From BRAZOS RIVER
To SP 484 / SH 6
CSJ 0258-09-124
Proj ID NH 1602(305)
Work Type WDN TO 4 LN FRWY
 
1.365 14733502.65 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 617
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0258-09-124
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163205
Totals 14733502.65 0.00 0.00 0.0

CountyBELL
Highway SH 95
From FM 2268 IN HOLLAND
To WILLIAMSON CO LINE
CSJ 0320-02-033
Proj ID STP 2015(477)
Work Type WDN, GR, BS, SURF & ADD SHLDRS
 
5.337 6989387.63 47469.68 3093599.67 44.2
CountyBELL
Highway SH 95
From @ INDIAN CREEK
To (STR #054)
CSJ 0320-02-037
Proj ID BR 2015(476)
Work Type REPL BR & APPRS
 
0.114 1361222.86 145300.00 1358604.39 99.8
Work Order 03-31-15
Work Began 07-06-15
Work Completed  
Time Computed 09-27-15
Contract Working Days 319
Addl Days Granted 31
Working Days Charged 243
Percent Time Used 69
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0320-02-033
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.11%)
AUSTIN LAND SERVICE(0.52%)
BEAR CREEK CONSTRUCTION, LLC ( 14.81%)
D. I. J. CONSTRUCTION, INC.(0.89%)
ELLIS-MCGINNIS CONSTRUCTION CO.( 13.81%)
ROADWAY SPECIALTIES, INC.(2.20%)
SAN-ANN-CO., INC.(0.69%)
W. W. FOUNDATION DRILLING, LTD.(0.81%)
MCL CONTRACTING, LLC (0.20%)
JUST GROOVING, LTD.(0.06%)
1 PRIORITY ENVIRONMENTAL SERVICES, INC.(0.23%)
Contract # 02153225
Totals 8350610.49 192769.68 4452204.06 53.3

CountyBELL
Highway SH 317
From 0.2 MI S OF FM 2305
To 0.4 MI N OF FM 439
CSJ 0398-04-059
Proj ID C 398-4-59
Work Type WDN, GR, STRS & SURF
 
2.149 16887376.62 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 532
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0398-04-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163006
Totals 16887376.62 0.00 0.00 0.0

CountyBELL
Highway SH 317
From SH 36
To FM 2305
CSJ 0398-04-073
Proj ID STP 1502(565)HES
Work Type INST CONT LFT TRN LN
 
2.600 2346791.50 96539.51 792809.54 33.7
Work Order 10-30-15
Work Began 01-28-16
Work Completed  
Time Computed 01-15-16
Contract Working Days 128
Addl Days Granted 0
Working Days Charged 105
Percent Time Used 82
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0398-04-073
D. I. J. CONSTRUCTION, INC.(1.49%)
SAN-ANN-CO., INC.(2.12%)
DS TEXAS ICON CONSTRUCTION (0.76%)
R K STEPHENS CONSTRUCTION, LLC ( 10.91%)
TEXOP CONSTRUCTION (0.27%)
TEXAS ALTERNATIVE GRASSER, INC.(0.37%)
BMP SPECIALIST, LLC(0.89%)
Contract # 08153212
Totals 2346791.50 96539.51 792809.54 33.7

CountyLIMESTONE
Highway SH 171
From US 84
To CITY OF COOLIDGE
CSJ 0419-02-041
Proj ID STP 2016(746)
Work Type UNDERSEAL / OVLY
 
11.056 3653777.19 528279.58 684235.58 18.7
Work Order 03-14-16
Work Began 05-24-16
Work Completed  
Time Computed 05-16-16
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 55
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0419-02-041
ALTUS TRAFFIC MANAGEMENT LLC (0.30%)
BEAR CREEK CONSTRUCTION, LLC (0.74%)
COWBELL TRAFFIC SERVICES, INC. (0.34%)
D. I. J. CONSTRUCTION, INC.(1.85%)
FORTSON CONTRACTING, INC.(1.15%)
TEXOP CONSTRUCTION (1.12%)
Contract # 02163223
Totals 3653777.19 528279.58 684235.58 18.7

CountyCORYELL
Highway FM 1996
From US 84
To FM 107
CSJ 0567-01-027
Proj ID STP 1602(306)
Work Type REHAB RDWY
 
4.508 2775913.74 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 170
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0567-01-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163012
Totals 2775913.74 0.00 0.00 0.0

CountyLIMESTONE
Highway FM 39
From SH 164
To LEON CO LINE
CSJ 0643-02-025
Proj ID STP 1502(415)
Work Type WDN, GR, BS, SURF & ADD SHLDRS
 
8.651 6211432.54 704874.58 1680267.32 27.0
CountyLIMESTONE
Highway FM 39
From SH 164
To FM 80
CSJ 0643-02-026
Proj ID STP 1502(414)HES
Work Type SFTY TR FX OBJS
 
7.210 1328780.00 139430.00 140310.00 10.5
Work Order 02-29-16
Work Began 04-29-16
Work Completed  
Time Computed 04-29-16
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 17
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0643-02-025
BIG CREEK CONSTRUCTION, LTD. ( 23.44%)
D.I.J. CONSTRUCTION, INC (0.94%)
FLASHER EQUIPMENT COMPANY(0.23%)
J & M CONTRACTING, COMPANY (9.53%)
ROADWAY SPECIALTIES, INC.(8.50%)
WEST TEXAS RUMBLE STRIP(0.05%)
Contract # 12153009
Totals 7540212.54 844304.58 1820577.32 24.1

CountyCORYELL
Highway FM 116
From US 84
To CACTUS LANE
CSJ 0724-01-044
Proj ID STP 1502(343)
Work Type ADD PASS LNS / SHLDRS
 
18.891 17587091.47 595014.26 6441718.88 36.6
Work Order 08-20-15
Work Began 11-11-15
Work Completed  
Time Computed 12-19-15
Contract Working Days 510
Addl Days Granted 0
Working Days Charged 164
Percent Time Used 32
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0724-01-044
ABC EROSION CONTROL, INC.(2.03%)
SAN-ANN-CO., INC.(0.30%)
W. W. FOUNDATION DRILLING, LTD.(0.67%)
GK CONSTRUCTION, LLC (0.11%)
PRIMATE CONSTRUCTION, INC. (0.13%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.26%)
COWBELL TRAFFIC SERVICES, INC. (0.13%)
DS TEXAS ICON CONSTRUCTION (0.61%)
ROADWAY SPECIALTIES, INC.(0.85%)
JOY LATTIMER, LLC. (4.01%)
D. I. J. CONSTRUCTION, INC.(1.47%)
FORTSON CONTRACTING, INC.(1.05%)
MCL CONTRACTING, LLC (0.00%)
NIXON ENGINEERING(0.00%)
Contract # 06153203
Totals 17587091.47 595014.26 6441718.88 36.6

CountyCORYELL
Highway FM 116
From ANDERSON AVE
To AVENUE B
CSJ 0724-01-049
Proj ID STP 2013(586)
Work Type WDN, GR & STR
 
0.704 4531202.35 17000.00 92040.50 2.0
CountyCORYELL
Highway FM 116
From ANDERSON AVE
To AVENUE B
CSJ 0724-01-052
Proj ID ROW 724-1-52
Work Type ROW ACQUISITION
 
0.704 1012118.22 0.00 0.00 0.0
Work Order 11-13-15
Work Began 02-11-16
Work Completed  
Time Computed 02-11-16
Contract Working Days 340
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0724-01-049
SAN-ANN-CO., INC.(0.78%)
ROADWAY SPECIALTIES, INC.(1.24%)
TEX OP CONSTRUCTION, LP(0.25%)
R K STEPHENS CONSTRUCTION, LLC (7.97%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.36%)
TRP CONSTRUCTION GROUP, LLC(0.97%)
MCLEAN CONSTRUCTION, INC.( 39.03%)
Contract # 09153013
Totals 5543320.57 17000.00 92040.50 1.6

CountyLIMESTONE
Highway FM 147
From SH 14
To FALLS CO LINE
CSJ 0752-06-022
Proj ID STP 2016(103)
Work Type WDN, GR, BS, SURF, ADD SHLDRS
 
10.055 4469649.32 125692.46 808304.85 18.0
Work Order 11-16-15
Work Began 02-29-16
Work Completed  
Time Computed 02-15-16
Contract Working Days 234
Addl Days Granted 0
Working Days Charged 84
Percent Time Used 35
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0752-06-022
BEAR CREEK CONSTRUCTION, LLC ( 15.29%)
D.I.J. CONSTRUCTION, INC (1.51%)
FORTSON CONTRACTING, INC.(0.81%)
ROADWAY SPECIALTIES, INC.(4.43%)
SAN-ANN-CO., INC.(1.81%)
TEXAS ALTERNATIVE GRASSER, INC.(1.15%)
WEST TEXAS RUMBLE STRIP(0.10%)
Contract # 09153221
Totals 4469649.32 125692.46 808304.85 18.0

CountyMCLENNAN
Highway FM 1637
From FM 3051
To 0.65 MI W OF FM 2490
CSJ 0833-03-035
Proj ID HP 1502(059)
Work Type WDN GR, STRS & SURF
 
4.337 27836847.99 1413140.03 1770844.72 6.3
Work Order 06-30-15
Work Began 04-04-16
Work Completed  
Time Computed 12-28-15
Contract Working Days 574
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 4
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0833-03-035
RAMBO CONTRACTING, INC.(2.78%)
APEX LANDSCAPE & IRRIGATION, LLC (0.62%)
BRICK PAVING PLUS, INC.(2.72%)
DUSTROL, INC.(0.52%)
ROADWAY SPECIALTIES, INC.(1.35%)
FLASHER EQUIPMENT COMPANY(0.56%)
SAN-ANN-CO., INC.(0.27%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(2.19%)
LONE STAR HIGHWAY PRODUCTS, INC. (4.07%)
Contract # 04153257
Totals 27836847.99 1413140.03 1770844.72 6.3

CountyBELL
Highway SH 195
From @ KILLEEN SOUTH CITY LIMITS
To .
CSJ 0836-02-069
Proj ID C 836-2-69
Work Type LANDSCAPE ENHANCE
 
0.051 292247.00 1570.00 274266.50 93.8
Work Order 07-30-15
Work Began 08-29-15
Work Completed  
Time Computed 08-31-15
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 98
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0836-02-069
FLASHER EQUIPMENT COMPANY(0.87%)
Contract # 06153210
Totals 292247.00 1570.00 274266.50 93.8

CountyBELL
Highway SH 195
From US 190
To FM 3470
CSJ 0836-02-070
Proj ID NH 2015(873)
Work Type MILL / INLAY
 
2.216 1516922.75 46609.64 371464.45 24.4
Work Order 10-22-15
Work Began 04-22-16
Work Completed  
Time Computed 11-23-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 61
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0836-02-070
DUSTROL, INC.(3.84%)
CHEROKEE SERVICES(0.73%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.15%)
TRP CONSTRUCTION GROUP, LLC(4.88%)
Contract # 09153008
Totals 1516922.75 46609.64 371464.45 24.4

CountyMCLENNAN
Highway CS
From ON CS 065 @ TONK CRK
To (MAP #1 - CRAWFORD)
CSJ 0909-22-166
Proj ID BR 2014(445)
Work Type REPL BR & APPRS
 
0.084 755454.92 0.00 0.00 0.0
Work Order 04-20-16
Work Began 00-00-00
Work Completed  
Time Computed 06-20-16
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0909-22-166
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163023
Totals 755454.92 0.00 0.00 0.0