Monthly State Let Construction Report For Waco District As Of Feb 11, 2016 Page 3 Of 4

Last Update: Thursday, February 11, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyFALLS
Highway BS 7-B
From @ GOODWIN BRANCH
To (STR #006)
CSJ 0513-03-018
Proj ID BR 2014(779)
Work Type REPL BR & APPRS
 
0.099 350557.61 0.00 347360.59 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-11-14
Work Began 12-01-14
Work Completed 10-05-15
Time Computed 11-10-14
Contract Working Days 85
Addl Days Granted 5
Working Days Charged 90
Percent Time Used 100
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0513-03-018
FORTSON CONTRACTING, INC.(6.37%)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(0.98%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.33%)
STRIPING TECHNOLOGY, L.P.(1.88%)
TEXAS ALTERNATIVE GRASSER, INC.(1.40%)
B.E.S.T. (0.54%)
BEAR CREEK CONSTRUCTION, LLC ( 36.44%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
Contract # 06143214
Totals 350557.61 0.00 347360.59 100.0

CountyCORYELL
Highway FM 107 ETC
From FM 1996
To MCLENNAN CO LINE
CSJ 0567-01-025
Proj ID STP 2015(230)
Work Type SEAL COAT
 
173.125 8024181.54 14400.00 7808557.64 100.0
Work Order 11-10-14
Work Began 07-06-15
Work Completed 12-01-15
Time Computed 06-10-15
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 143
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0567-01-025
BATTERSON,LLP( 14.60%)
COWBELL TRAFFIC SERVICE, INC.(0.28%)
Contract # 10143221
Totals 8024181.54 14400.00 7808557.64 100.0

CountyLIMESTONE
Highway FM 39
From SH 164
To LEON CO LINE
CSJ 0643-02-025
Proj ID STP 1502(415)
Work Type WDN, GR, BS, SURF & ADD SHLDRS
 
8.651 6211432.54 0.00 0.00 0.0
CountyLIMESTONE
Highway FM 39
From SH 164
To FM 80
CSJ 0643-02-026
Proj ID STP 1502(414)HES
Work Type SFTY TR FX OBJS
 
7.210 1328780.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0643-02-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153009
Totals 7540212.54 0.00 0.00 0.0

CountyCORYELL
Highway FM 116
From US 84
To CACTUS LANE
CSJ 0724-01-044
Proj ID STP 1502(343)
Work Type ADD PASS LNS / SHLDRS
 
18.891 17587091.47 1878549.07 3536540.28 20.1
Work Order 08-20-15
Work Began 11-11-15
Work Completed  
Time Computed 12-19-15
Contract Working Days 510
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 10
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0724-01-044
ABC EROSION CONTROL, INC.(2.03%)
SAN-ANN-CO., INC.(0.30%)
W. W. FOUNDATION DRILLING, LTD.(0.67%)
GK CONSTRUCTION, LLC (0.11%)
PRIMATE CONSTRUCTION, INC. (0.13%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.26%)
COWBELL TRAFFIC SERVICES, INC. (0.13%)
DS TEXAS ICON CONSTRUCTION (0.61%)
ROADWAY SPECIALTIES, INC.(0.85%)
JOY LATTIMER, LLC. (4.01%)
D. I. J. CONSTRUCTION, INC.(1.47%)
FORTSON CONTRACTING, INC.(1.05%)
MCL CONTRACTING, LLC (0.00%)
NIXON ENGINEERING(0.00%)
Contract # 06153203
Totals 17587091.47 1878549.07 3536540.28 20.1

CountyCORYELL
Highway FM 116
From ANDERSON AVE
To AVENUE B
CSJ 0724-01-049
Proj ID STP 2013(586)
Work Type WDN, GR & STR
 
0.704 4531202.35 0.00 0.00 0.0
CountyCORYELL
Highway FM 116
From ANDERSON AVE
To AVENUE B
CSJ 0724-01-052
Proj ID ROW 724-1-52
Work Type ROW ACQUISITION
 
0.704 1012118.22 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-13-15
Work Began 00-00-00
Work Completed  
Time Computed 03-12-16
Contract Working Days 340
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0724-01-049
SAN-ANN-CO., INC.(0.78%)
ROADWAY SPECIALTIES, INC.(1.24%)
TEX OP CONSTRUCTION, LP(0.25%)
R K STEPHENS CONSTRUCTION, LLC (7.97%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.36%)
TRP CONSTRUCTION GROUP, LLC(0.97%)
MCLEAN CONSTRUCTION, INC.( 39.03%)
Contract # 09153013
Totals 5543320.57 0.00 0.00 0.0

CountyFALLS
Highway FM 147
From SH 6
To LIMESTONE CO LINE
CSJ 0752-05-027
Proj ID STP 2014(233)
Work Type WDN, GR, BS, SURF, ADD SHLDRS
 
11.563 4379271.22 61374.14 4548200.71 100.0
Work Order 03-10-14
Work Began 05-21-14
Work Completed 01-28-16
Time Computed 05-09-14
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 303
Percent Time Used 118
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0752-05-027
BEAR CREEK CONSTRUCTION, LLC ( 22.91%)
D. I. J. CONSTRUCTION, INC.(1.00%)
GJ SEEDING, LLC(0.43%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.54%)
ROADWAY SPECIALTIES, INC.(4.79%)
TEXAS ALTERNATIVE GRASSER, INC.(0.30%)
TEX OP CONSTRUCTION, LP(0.25%)
BROCK CONSTRUCTION, LLC(0.39%)
RUTHERFORD TREE SERVICES (0.39%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
NEW IMAGE SEALING(0.13%)
Contract # 11133209
Totals 4379271.22 61374.14 4548200.71 100.0

CountyLIMESTONE
Highway FM 147
From SH 14
To FALLS CO LINE
CSJ 0752-06-022
Proj ID STP 2016(103)
Work Type WDN, GR, BS, SURF, ADD SHLDRS
 
10.055 4469649.32 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-16-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 234
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0752-06-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09153221
Totals 4469649.32 0.00 0.00 0.0

CountyFALLS
Highway FM 413
From @ LITTLE BRAZOS RIVER
To (STR #007)
CSJ 0808-02-013
Proj ID BR 2013(685)
Work Type REPL BR & APPRS
 
0.180 565266.22 0.00 402775.40 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-16-13
Work Began 09-23-13
Work Completed 09-25-15
Time Computed 09-14-13
Contract Working Days 84
Addl Days Granted 150
Working Days Charged 409
Percent Time Used 174
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0808-02-013
DALLAS LITE AND BARRICADE INC. (1.06%)
BEAIRD DRILLING(4.53%)
D. I. J. CONSTRUCTION, INC.(1.29%)
FORTSON CONTRACTING, INC.(2.70%)
LINDAMOOD DEMOLITION, INC. (4.16%)
SHALLOW FORD CONSTRUCTION CO., INC.(0.53%)
LONE STAR PAVING COMPANY (3.94%)
REED HYDROMULCHING, INC. (0.84%)
HOUSTON SAWING & DRILLING(0.30%)
ALTUS TRAFFIC MANAGEMENT LLC (2.37%)
LONE STAR PAVING COMPANY (INACTIVE)( 20.44%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.92%)
TERO ENTERPRISES, LLC. (0.80%)
Contract # 05133012
Totals 565266.22 0.00 402775.40 100.0

CountyMCLENNAN
Highway FM 1637
From FM 3051
To 0.65 MI W OF FM 2490
CSJ 0833-03-035
Proj ID HP 1502(059)
Work Type WDN GR, STRS & SURF
 
4.337 27836847.99 0.00 95625.00 0.3
Work Order 06-30-15
Work Began 00-00-00
Work Completed  
Time Computed 12-28-15
Contract Working Days 574
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0833-03-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153257
Totals 27836847.99 0.00 95625.00 0.3

CountyBELL
Highway SH 195
From @ KILLEEN SOUTH CITY LIMITS
To .
CSJ 0836-02-069
Proj ID C 836-2-69
Work Type LANDSCAPE ENHANCE
 
0.051 292247.00 13.50 258578.00 88.4
Work Order 07-30-15
Work Began 08-29-15
Work Completed  
Time Computed 08-31-15
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 98
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0836-02-069
FLASHER EQUIPMENT COMPANY(0.87%)
Contract # 06153210
Totals 292247.00 13.50 258578.00 88.4

CountyBELL
Highway SH 195
From US 190
To FM 3470
CSJ 0836-02-070
Proj ID NH 2015(873)
Work Type MILL / INLAY
 
2.216 1516922.75 0.00 0.00 0.0
Work Order 10-22-15
Work Began 00-00-00
Work Completed  
Time Computed 11-15-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0836-02-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09153008
Totals 1516922.75 0.00 0.00 0.0

CountyCORYELL
Highway FM 183
From 0.15 MI E OF FS 183
To US 84
CSJ 0867-03-026
Proj ID STP 2014(012)HES
Work Type PROV ADD'TL PV SURF WIDTH
 
9.769 4552211.28 798.70 4474477.33 100.0
Work Order 12-10-13
Work Began 02-13-14
Work Completed 09-25-15
Time Computed 02-10-14
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 264
Percent Time Used 103
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0867-03-026
BEAIRD DRILLING(0.60%)
JOY LATTIMER, LLC. (2.30%)
TEXAS ALTERNATIVE GRASSER, INC.(0.68%)
ROADWAY SPECIALTIES, INC.(3.81%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.51%)
D. I. J. CONSTRUCTION, INC.(1.81%)
K & S BACKHOE SERVICES INC.( 13.51%)
P E K INC DBA SERVICELINE TRANSPORT(0.46%)
BRYDL CONTRACTING, INC.(0.07%)
Contract # 09133218
Totals 4552211.28 798.70 4474477.33 100.0

CountyHILL
Highway FM 934
From @ BRANCH OF HACKBERRY CRK
To (STR #007)
CSJ 0888-01-017
Proj ID BR 2014(083)
Work Type REPL BR & APPRS
 
0.089 374507.10 0.00 366085.00 100.0
CountyHILL
Highway FM 934
From @ COTTONWOOD CREEK
To (STR #004)
CSJ 0888-01-018
Proj ID BR 2014(083)
Work Type REPL BR & APPRS
 
0.092 424277.54 0.00 413785.43 100.0
CountyHILL
Highway FM 934
From SH 171
To SH 81
CSJ 0888-01-020
Proj ID STP 2014(082)
Work Type WDN, GR, BS, SURF, SHLDRS
 
4.860 1936383.89 0.00 2092183.12 100.0
CountyHILL
Highway FM 934
From FM 66 (EAST ST IN ITASCA)
To IH 35W
CSJ 1661-03-012
Proj ID STP 2014(082)
Work Type WDN, GR, BS, SURF, SHLDRS
 
1.484 658471.52 0.00 712377.92 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-17-14
Work Began 03-18-14
Work Completed 07-27-15
Time Computed 03-18-14
Contract Working Days 276
Addl Days Granted 0
Working Days Charged 218
Percent Time Used 78
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0888-01-020
BEAIRD DRILLING(1.20%)
JUST GROOVING, LTD.(0.08%)
ROADWAY SPECIALTIES, INC.(4.96%)
STRIPING TECHNOLOGY, L.P.(1.52%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.89%)
BEAR CREEK CONSTRUCTION, LLC ( 17.95%)
Contract # 10133215
Totals 3393640.05 0.00 3584431.47 100.0

CountyMCLENNAN
Highway VA
From AT VARIOUS LOCATIONS IN BELL,
To MCLENNAN COUNTIES
CSJ 0909-00-043
Proj ID STP 2014(780)
Work Type CSTR / RECNSTR ADA RMPS
 
0.001 1649141.20 -3140.00 1943800.46 99.9
Work Order 10-02-14
Work Began 11-03-14
Work Completed  
Time Computed 10-18-14
Contract Working Days 179
Addl Days Granted 0
Working Days Charged 196
Percent Time Used 109
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0909-00-043
FLASHER EQUIPMENT COMPANY(2.11%)
GEORGE MEEKS LANDPRO, INC. (2.82%)
LEIJA TRACTOR(0.80%)
JE CASEY, LLC(0.65%)
Contract # 06143225
Totals 1649141.20 3140.00 1943800.46 99.9

CountyMCLENNAN
Highway CR
From CR 747 @ TEHUACANA CRK TRIB
To (MAP #286) (MAEHR RD)
CSJ 0909-22-162
Proj ID BR 2013(958)
Work Type REPL BR & APPRS
 
0.100 434551.93 3154.68 417785.08 96.1
Work Order 09-30-14
Work Began 03-23-15
Work Completed  
Time Computed 03-29-15
Contract Working Days 128
Addl Days Granted 0
Working Days Charged 128
Percent Time Used 100
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0909-22-162
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.63%)
FLASHER EQUIPMENT COMPANY(0.64%)
SAN-ANN-CO., INC.(1.86%)
ROADWAY SPECIALTIES, INC.(2.39%)
FORTSON CONTRACTING, INC.(2.31%)
Contract # 08143040
Totals 434551.93 3154.68 417785.08 96.1

CountyMCLENNAN
Highway CS
From ON CS 065 @ TONK CRK
To (MAP #1 - CRAWFORD)
CSJ 0909-22-166
Proj ID BR 2014(445)
Work Type REPL BR & APPRS
 
0.084 755454.92 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0909-22-166
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163023
Totals 755454.92 0.00 0.00 0.0

CountyBELL
Highway CS
From LAMPASAS RV ON TOLL BRDG RD
To (MAP #48-BELTON)
CSJ 0909-36-136
Proj ID BR 2013(959)
Work Type REPL BR & APPRS
 
0.156 924031.22 5588.00 915771.25 100.0
Work Order 09-11-14
Work Began 03-23-15
Work Completed 01-04-16
Time Computed 03-10-15
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 147
Percent Time Used 98
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0909-36-136
M & D FOUNDATION DRILLING INDUSTRIES, INC. (9.62%)
D. I. J. CONSTRUCTION, INC.(0.55%)
FORTSON CONTRACTING, INC.(0.90%)
ROADWAY SPECIALTIES, INC.(1.01%)
SAN-ANN-CO., INC.(0.40%)
MESA ROD BUSTERS, INC. (0.29%)
Contract # 07143010
Totals 924031.22 5588.00 915771.25 100.0

CountyBELL
Highway CR
From ON CR 493 @ SALADO
To CREEK (MAP#60)
CSJ 0909-36-137
Proj ID BR 2012(427)
Work Type REPL BR & APPRS
 
0.176 1202660.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 04-28-16
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0909-36-137
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10153004
Totals 1202660.75 0.00 0.00 0.0

CountyBELL
Highway CS
From ON ELMS RD FR CHISHOLM TRAIL
To KAYDENCE COURT
CSJ 0909-36-148
Proj ID STP 2015(782)HES
Work Type INSTL SFTY ITEMS & SDWLKS
 
0.187 237418.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 03-29-16
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0909-36-148
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09153206
Totals 237418.60 0.00 0.00 0.0

CountyHILL
Highway PW
From LAKE WHITNEY STATE PARK
To .
CSJ 0909-37-050
Proj ID C 909-37-50
Work Type RESURF
 
1.775 354883.90 0.00 361084.40 100.0
CountyHILL
Highway PR 47
From LAKE WHITNEY STATE PARK
To (ACCESS RD)
CSJ 2309-02-004
Proj ID C 2309-2-4
Work Type RESURF ACCESS RD
 
1.775 170800.05 0.00 174133.65 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-17-14
Work Began 06-17-14
Work Completed 02-27-15
Time Computed 03-18-14
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 64
Percent Time Used 100
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0909-37-050
FLASHER EQUIPMENT COMPANY(3.19%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.93%)
TEXAS ALTERNATIVE GRASSER, INC.(2.37%)
Contract # 10133013
Totals 525683.95 0.00 535218.05 100.0

page 1 | page 2 | page 3 | page 4