Monthly State Let Construction Report For Waco District As Of Aug 10, 2015 Page 3 Of 4

Last Update: Monday, August 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyFALLS
Highway FM 147
From SH 6
To LIMESTONE CO LINE
CSJ 0752-05-027
Proj ID STP 2014(233)
Work Type WDN, GR, BS, SURF, ADD SHLDRS
 
11.563 4379271.22 582605.82 3741547.64 86.4
Work Order 03-10-14
Work Began 05-21-14
Work Completed  
Time Computed 05-09-14
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 301
Percent Time Used 118
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0752-05-027
BEAR CREEK CONSTRUCTION, LLC ( 22.91%)
D. I. J. CONSTRUCTION, INC.(1.00%)
GJ SEEDING, LLC(0.43%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.54%)
ROADWAY SPECIALTIES, INC.(4.79%)
TEXAS ALTERNATIVE GRASSER, INC.(0.30%)
TEX OP CONSTRUCTION, LP(0.25%)
BROCK CONSTRUCTION, LLC(0.39%)
RUTHERFORD TREE SERVICES (0.39%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
Contract # 11133209
Totals 4379271.22 582605.82 3741547.64 86.4

CountyFALLS
Highway FM 413
From @ LITTLE BRAZOS RIVER
To (STR #007)
CSJ 0808-02-013
Proj ID BR 2013(685)
Work Type REPL BR & APPRS
 
0.180 565266.22 0.00 391409.11 84.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-16-13
Work Began 09-23-13
Work Completed  
Time Computed 09-14-13
Contract Working Days 84
Addl Days Granted 0
Working Days Charged 155
Percent Time Used 184
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0808-02-013
DALLAS LITE AND BARRICADE INC. (1.06%)
BEAIRD DRILLING(4.53%)
D. I. J. CONSTRUCTION, INC.(1.29%)
FORTSON CONTRACTING, INC.(2.70%)
LINDAMOOD DEMOLITION, INC. (4.16%)
SHALLOW FORD CONSTRUCTION CO., INC.(0.53%)
LONE STAR PAVING COMPANY (3.94%)
REED HYDROMULCHING, INC. (0.84%)
HOUSTON SAWING & DRILLING(0.30%)
ALTUS TRAFFIC MANAGEMENT LLC (2.37%)
LONE STAR PAVING COMPANY (INACTIVE)( 20.44%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.92%)
TERO ENTERPRISES, LLC. (0.80%)
Contract # 05133012
Totals 565266.22 0.00 391409.11 84.0

CountyMCLENNAN
Highway FM 1637
From FM 3051
To 0.65 MI W OF FM 2490
CSJ 0833-03-035
Proj ID HP 1502(059)
Work Type WDN GR, STRS & SURF
 
4.337 27836847.99 95625.00 95625.00 0.3
Work Order 06-30-15
Work Began 00-00-00
Work Completed  
Time Computed 12-28-15
Contract Working Days 574
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0833-03-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153257
Totals 27836847.99 95625.00 95625.00 0.3

CountyBELL
Highway SH 195
From @ KILLEEN SOUTH CITY LIMITS
To .
CSJ 0836-02-069
Proj ID C 836-2-69
Work Type LANDSCAPE ENHANCE
 
0.051 292247.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-30-15
Work Began 00-00-00
Work Completed  
Time Computed 08-15-15
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0836-02-069
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153210
Totals 292247.00 0.00 0.00 0.0

CountyCORYELL
Highway FM 183
From 0.15 MI E OF FS 183
To US 84
CSJ 0867-03-026
Proj ID STP 2014(012)HES
Work Type PROV ADD'TL PV SURF WIDTH
 
9.769 4552211.28 442526.31 4410448.45 97.0
Work Order 12-10-13
Work Began 02-13-14
Work Completed  
Time Computed 02-10-14
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 264
Percent Time Used 103
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0867-03-026
BEAIRD DRILLING(0.60%)
JOY LATTIMER, LLC. (2.30%)
TEXAS ALTERNATIVE GRASSER, INC.(0.68%)
ROADWAY SPECIALTIES, INC.(3.81%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.51%)
D. I. J. CONSTRUCTION, INC.(1.81%)
K & S BACKHOE SERVICES INC.( 13.51%)
P E K INC DBA SERVICELINE TRANSPORT(0.46%)
BRYDL CONTRACTING, INC.(0.07%)
Contract # 09133218
Totals 4552211.28 442526.31 4410448.45 97.0

CountyHILL
Highway FM 934
From @ BRANCH OF HACKBERRY CRK
To (STR #007)
CSJ 0888-01-017
Proj ID BR 2014(083)
Work Type REPL BR & APPRS
 
0.089 374507.10 1070.62 366004.60 100.0
CountyHILL
Highway FM 934
From @ COTTONWOOD CREEK
To (STR #004)
CSJ 0888-01-018
Proj ID BR 2014(083)
Work Type REPL BR & APPRS
 
0.092 424277.54 720.62 413691.63 100.0
CountyHILL
Highway FM 934
From SH 171
To SH 81
CSJ 0888-01-020
Proj ID STP 2014(082)
Work Type WDN, GR, BS, SURF, SHLDRS
 
4.860 1936383.89 77422.81 2070114.34 100.0
CountyHILL
Highway FM 934
From FM 66 (EAST ST IN ITASCA)
To IH 35W
CSJ 1661-03-012
Proj ID STP 2014(082)
Work Type WDN, GR, BS, SURF, SHLDRS
 
1.484 658471.52 67740.70 695047.92 100.0
Work Order 01-17-14
Work Began 03-18-14
Work Completed 07-27-15
Time Computed 03-18-14
Contract Working Days 276
Addl Days Granted 0
Working Days Charged 218
Percent Time Used 78
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0888-01-020
BEAIRD DRILLING(1.20%)
JUST GROOVING, LTD.(0.08%)
ROADWAY SPECIALTIES, INC.(4.96%)
STRIPING TECHNOLOGY, L.P.(1.52%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.89%)
BEAR CREEK CONSTRUCTION, LLC ( 17.95%)
Contract # 10133215
Totals 3393640.05 146954.75 3544858.49 100.0

CountyMCLENNAN
Highway VA
From AT VARIOUS LOCATIONS IN BELL,
To MCLENNAN COUNTIES
CSJ 0909-00-043
Proj ID STP 2014(780)
Work Type CSTR / RECNSTR ADA RMPS
 
0.001 1649141.20 1500.00 1935905.46 99.9
Work Order 10-02-14
Work Began 11-03-14
Work Completed  
Time Computed 10-18-14
Contract Working Days 179
Addl Days Granted 0
Working Days Charged 167
Percent Time Used 93
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0909-00-043
FLASHER EQUIPMENT COMPANY(2.11%)
GEORGE MEEKS LANDPRO, INC. (2.82%)
LEIJA TRACTOR(0.80%)
JE CASEY, LLC(0.65%)
Contract # 06143225
Totals 1649141.20 1500.00 1935905.46 99.9

CountyMCLENNAN
Highway CR
From CR 747 @ TEHUACANA CRK TRIB
To (MAP #286) (MAEHR RD)
CSJ 0909-22-162
Proj ID BR 2013(958)
Work Type REPL BR & APPRS
 
0.100 434551.93 49065.00 198247.12 45.6
Work Order 09-30-14
Work Began 03-23-15
Work Completed  
Time Computed 03-29-15
Contract Working Days 128
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 25
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0909-22-162
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.63%)
FLASHER EQUIPMENT COMPANY(0.64%)
SAN-ANN-CO., INC.(1.86%)
ROADWAY SPECIALTIES, INC.(2.39%)
FORTSON CONTRACTING, INC.(2.31%)
Contract # 08143040
Totals 434551.93 49065.00 198247.12 45.6

CountyBELL
Highway CS
From LAMPASAS RV ON TOLL BRDG RD
To (MAP #48-BELTON)
CSJ 0909-36-136
Proj ID BR 2013(959)
Work Type REPL BR & APPRS
 
0.156 924031.22 500.00 459675.72 49.7
Work Order 09-11-14
Work Began 03-23-15
Work Completed  
Time Computed 03-10-15
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 94
Percent Time Used 63
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0909-36-136
M & D FOUNDATION DRILLING INDUSTRIES, INC. (9.62%)
D. I. J. CONSTRUCTION, INC.(0.55%)
FORTSON CONTRACTING, INC.(0.90%)
ROADWAY SPECIALTIES, INC.(1.01%)
SAN-ANN-CO., INC.(0.40%)
MESA ROD BUSTERS, INC. (0.29%)
Contract # 07143010
Totals 924031.22 500.00 459675.72 49.7

CountyHILL
Highway PW
From LAKE WHITNEY STATE PARK
To .
CSJ 0909-37-050
Proj ID C 909-37-50
Work Type RESURF
 
1.775 354883.90 0.00 361084.40 100.0
CountyHILL
Highway PR 47
From LAKE WHITNEY STATE PARK
To (ACCESS RD)
CSJ 2309-02-004
Proj ID C 2309-2-4
Work Type RESURF ACCESS RD
 
1.775 170800.05 0.00 174133.65 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-17-14
Work Began 06-17-14
Work Completed 02-27-15
Time Computed 03-18-14
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 64
Percent Time Used 100
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0909-37-050
FLASHER EQUIPMENT COMPANY(3.19%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.93%)
TEXAS ALTERNATIVE GRASSER, INC.(2.37%)
Contract # 10133013
Totals 525683.95 0.00 535218.05 100.0

CountyHILL
Highway CR
From CR 305 @ BYNUM CREEK
To (MAP #81)
CSJ 0909-37-054
Proj ID BR 2012(393)
Work Type REPL BR & APPRS
 
0.100 297405.80 0.00 293359.50 98.6
CountyHILL
Highway CR
From ON CR 116 @ NO NAME
To CREEK (MAP#161)
CSJ 0909-37-055
Proj ID BR 2012(392)
Work Type REPL BR & APPRS
 
0.100 153781.60 0.00 151474.00 98.4
Work Order 07-08-14
Work Began 11-20-14
Work Completed  
Time Computed 01-04-15
Contract Working Days 170
Addl Days Granted 0
Working Days Charged 100
Percent Time Used 58
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0909-37-054
ABC EROSION CONTROL, INC.(2.38%)
FORTSON CONTRACTING, INC.(3.67%)
FRAIRE"S REBAR, INC(5.09%)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(1.15%)
WYLIE DRILLING & DRAINAGE, INC.(6.91%)
Contract # 05143016
Totals 451187.40 0.00 444833.50 98.5

CountyHILL
Highway CR
From CR 850 @ BR OF AQUILLA CRK
To (MAP #38)
CSJ 0909-37-056
Proj ID BR 2013(960)
Work Type REPL BR & APPRS
 
0.047 191321.10 0.00 185268.50 96.8
CountyHILL
Highway CR
From ON CR 560_@ AQUILLA CREEK
To (MAP #209)
CSJ 0909-37-058
Proj ID BR 2014(196)
Work Type REPL BR & APPRS
 
0.069 265118.95 350.00 254592.05 96.0
CountyHILL
Highway CR
From CR 893 @ COBB CRK
To (MAP #218) (HCR 3102)
CSJ 0909-37-059
Proj ID BR 2014(197)
Work Type REPL BR & APPRS
 
0.089 229899.15 0.00 216658.85 94.2
Work Order 08-07-14
Work Began 11-19-14
Work Completed  
Time Computed 02-03-15
Contract Working Days 264
Addl Days Granted 0
Working Days Charged 105
Percent Time Used 39
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0909-37-056
ABC EROSION CONTROL, INC.(3.48%)
FORTSON CONTRACTING, INC.(3.61%)
FRAIRE"S REBAR, INC(4.95%)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(5.65%)
WYLIE DRILLING & DRAINAGE, INC.(8.37%)
Contract # 04143027
Totals 686339.20 350.00 656519.40 95.6

CountyHILL
Highway CR
From ON CR 267 @ WHITE ROCK CR
To (MAP #71)
CSJ 0909-37-060
Proj ID BR 2014(198)
Work Type REPL BR & APPRS
 
0.152 535344.65 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 107
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0909-37-060
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153038
Totals 535344.65 0.00 0.00 0.0

CountyFALLS
Highway CR
From ON CR 198 @ KEECHI
To CRK (MAP #90)
CSJ 0909-38-054
Proj ID BR 1102(567)
Work Type REPL BR & APPRS
 
0.287 1024493.05 4950.00 971460.30 100.0
Work Order 04-10-13
Work Began 07-29-13
Work Completed 06-30-15
Time Computed 06-10-13
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 252
Percent Time Used 78
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0909-38-054
DUSTIN ALLEN, INC. (4.35%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.19%)
TEXAS ALTERNATIVE GRASSER, INC.(1.26%)
Contract # 02133014
Totals 1024493.05 4950.00 971460.30 100.0

CountyFALLS
Highway CR
From ON CR 105 @ SOUTH
To COW BAYOU (MAP #2016)
CSJ 0909-38-055
Proj ID BR 1102(565)
Work Type REPL BR & APPRS
 
0.301 899572.80 0.00 872499.19 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-14-13
Work Began 07-18-13
Work Completed 04-24-15
Time Computed 07-13-13
Contract Working Days 352
Addl Days Granted 0
Working Days Charged 272
Percent Time Used 77
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0909-38-055
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.69%)
SAN-ANN-CO., INC.(1.68%)
ROADWAY SPECIALTIES, INC.(5.54%)
NORTH TEXAS REBAR, LLC (0.26%)
Contract # 03133007
Totals 899572.80 0.00 872499.19 100.0

CountyFALLS
Highway CR
From CR 221 @ BIG SANDY CRK BR
To (MAP #40)
CSJ 0909-38-072
Proj ID BR 1402(049)
Work Type REPL BR & APPRS
 
0.345 1169676.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-07-15
Work Began 00-00-00
Work Completed  
Time Computed 09-06-15
Contract Working Days 489
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0909-38-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153253
Totals 1169676.10 0.00 0.00 0.0

CountyCORYELL
Highway PW
From @ MOTHER NEFF STATE PARK
To .
CSJ 0909-39-123
Proj ID C 909-39-123
Work Type CONSTR / RECONSTR PARK RD / ACCESS RDS
 
4.800 1385145.26 0.00 1523094.19 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-17-13
Work Began 01-15-14
Work Completed 04-28-15
Time Computed 01-13-14
Contract Working Days 107
Addl Days Granted 39
Working Days Charged 146
Percent Time Used 100
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0909-39-123
N-LINE TRAFFIC MAINTENANCE, L.P. (1.05%)
D. I. J. CONSTRUCTION, INC.(1.51%)
ABC EROSION CONTROL, INC.(1.46%)
TEXAS ALTERNATIVE GRASSER, INC.(0.31%)
AUSTIN WOOD RECYCLING(1.68%)
JOY LATTIMER, LLC. (1.89%)
Contract # 05133230
Totals 1385145.26 0.00 1523094.19 100.0

CountyLIMESTONE
Highway CR
From CR 408 @ STEELE CRK RELIEF
To (MAP #117)
CSJ 0909-40-068
Proj ID BR 2014(376)
Work Type REPL BR & APPRS
 
0.100 241319.00 5600.00 248559.00 100.0
CountyLIMESTONE
Highway CR
From CR 408 @ MILLS CREEK
To (MAP #115)
CSJ 0909-40-069
Proj ID BR 2014(378)
Work Type REPL BR & APPRS
 
0.100 504196.60 0.00 492503.00 100.0
Work Order 09-15-14
Work Began 11-03-14
Work Completed 07-30-15
Time Computed 11-14-14
Contract Working Days 192
Addl Days Granted 0
Working Days Charged 109
Percent Time Used 56
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0909-40-068
FORTSON CONTRACTING, INC.(2.22%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.81%)
MESA ROD BUSTERS, INC. (0.28%)
SAN-ANN-CO., INC.(0.67%)
S&S BRIDGE PAINTING(0.67%)
Contract # 07143230
Totals 745515.60 5600.00 741062.00 100.0

CountyHILL
Highway FM 933
From FM 1713
To FM 1244 IN WHITNEY
CSJ 1190-01-041
Proj ID STP 2013(688)
Work Type ROW ACQ.; RELOC. ASSIST.
 
2.894 318318.15 0.00 17806.55 5.5
CountyHILL
Highway FM 933
From FM 1713
To FM 1244 IN WHITNEY
CSJ 1190-01-043
Proj ID HP 2013(358)
Work Type WDN, GR, STRS & SURF
 
3.002 9598789.16 601111.38 1245145.00 12.9
Work Order 02-13-15
Work Began 04-20-15
Work Completed  
Time Computed 04-15-15
Contract Working Days 574
Addl Days Granted 0
Working Days Charged 69
Percent Time Used 12
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 1190-01-043
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(1.80%)
ROADWAY SPECIALTIES, INC.(0.98%)
SAN-ANN-CO., INC.(0.38%)
STRIPING TECHNOLOGY, L.P.(0.73%)
TEXOP CONSTRUCTION (0.11%)
JMJ CONTRACTOR ( 36.58%)
K & S BACKHOE SERVICES INC.( 36.58%)
N LINE TRAFFIC CONTROL (0.13%)
Contract # 12143218
Totals 9917107.31 601111.38 1262951.55 12.7

CountyLIMESTONE
Highway FM 937
From @ MONTGOMERY CREEK
To (STR #013)
CSJ 1191-04-022
Proj ID BR 2015(077)
Work Type REHAB BR & APPRS
 
1.127 1049361.10 125528.17 801684.74 76.3
Work Order 11-14-14
Work Began 01-15-15
Work Completed  
Time Computed 01-13-15
Contract Working Days 192
Addl Days Granted 0
Working Days Charged 143
Percent Time Used 74
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1191-04-022
DRILL TECH DRILLING & SHORING, INC.(5.41%)
JUST GROOVING, LTD.(0.25%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.28%)
MESA ROD BUSTERS, INC. (0.36%)
RICE ENVIRONMENTAL SERVICES(3.47%)
SAN-ANN-CO., INC.(0.71%)
STRIPING TECHNOLOGY, L.P.(2.00%)
Contract # 09143030
Totals 1049361.10 125528.17 801684.74 76.3