Monthly State Let Construction Report For Waco District As Of May 11, 2015 Page 3 Of 4

Last Update: Monday, May 11, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyMCLENNAN
Highway VA
From AT VARIOUS LOCATIONS IN BELL,
To MCLENNAN COUNTIES
CSJ 0909-00-043
Proj ID STP 2014(780)
Work Type CSTR / RECNSTR ADA RMPS
 
0.001 1649141.20 23316.96 1931405.46 99.9
Work Order 10-02-14
Work Began 11-03-14
Work Completed  
Time Computed 10-18-14
Contract Working Days 179
Addl Days Granted 0
Working Days Charged 112
Percent Time Used 62
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0909-00-043
FLASHER EQUIPMENT COMPANY(2.11%)
GEORGE MEEKS LANDPRO, INC. (2.82%)
LEIJA TRACTOR(0.80%)
Contract # 06143225
Totals 1649141.20 23316.96 1931405.46 99.9

CountyMCLENNAN
Highway CR
From CR 747 @ TEHUACANA CRK TRIB
To (MAP #286) (MAEHR RD)
CSJ 0909-22-162
Proj ID BR 2013(958)
Work Type REPL BR & APPRS
 
0.100 434551.93 85332.20 148182.12 34.0
Work Order 09-30-14
Work Began 03-23-15
Work Completed  
Time Computed 03-29-15
Contract Working Days 128
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 19
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0909-22-162
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.63%)
FLASHER EQUIPMENT COMPANY(0.64%)
SAN-ANN-CO., INC.(1.86%)
ROADWAY SPECIALTIES, INC.(2.39%)
FORTSON CONTRACTING, INC.(2.31%)
Contract # 08143040
Totals 434551.93 85332.20 148182.12 34.0

CountyBELL
Highway CS
From LAMPASAS RV ON TOLL BRDG RD
To (MAP #48-BELTON)
CSJ 0909-36-136
Proj ID BR 2013(959)
Work Type REPL BR & APPRS
 
0.156 924031.22 153096.25 294191.32 31.8
Work Order 09-11-14
Work Began 03-23-15
Work Completed  
Time Computed 03-10-15
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 20
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0909-36-136
M & D FOUNDATION DRILLING INDUSTRIES, INC. (9.62%)
D. I. J. CONSTRUCTION, INC.(0.55%)
FORTSON CONTRACTING, INC.(0.90%)
ROADWAY SPECIALTIES, INC.(1.01%)
SAN-ANN-CO., INC.(0.40%)
MESA ROD BUSTERS, INC. (0.29%)
Contract # 07143010
Totals 924031.22 153096.25 294191.32 31.8

CountyHILL
Highway PW
From LAKE WHITNEY STATE PARK
To .
CSJ 0909-37-050
Proj ID C 909-37-50
Work Type RESURF
 
1.775 354883.90 1498.60 361084.40 100.0
CountyHILL
Highway PR 47
From LAKE WHITNEY STATE PARK
To (ACCESS RD)
CSJ 2309-02-004
Proj ID C 2309-2-4
Work Type RESURF ACCESS RD
 
1.775 170800.05 0.00 174133.65 100.0
Work Order 01-17-14
Work Began 06-17-14
Work Completed 02-27-15
Time Computed 03-18-14
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 64
Percent Time Used 100
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0909-37-050
FLASHER EQUIPMENT COMPANY(3.19%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.93%)
TEXAS ALTERNATIVE GRASSER, INC.(2.37%)
Contract # 10133013
Totals 525683.95 1498.60 535218.05 100.0

CountyHILL
Highway CR
From CR 305 @ BYNUM CREEK
To (MAP #81)
CSJ 0909-37-054
Proj ID BR 2012(393)
Work Type REPL BR & APPRS
 
0.100 297405.80 19265.00 288463.50 96.9
CountyHILL
Highway CR
From ON CR 116 @ NO NAME
To CREEK (MAP#161)
CSJ 0909-37-055
Proj ID BR 2012(392)
Work Type REPL BR & APPRS
 
0.100 153781.60 360.00 148082.00 96.2
Work Order 07-08-14
Work Began 11-20-14
Work Completed  
Time Computed 01-04-15
Contract Working Days 170
Addl Days Granted 0
Working Days Charged 100
Percent Time Used 58
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0909-37-054
ABC EROSION CONTROL, INC.(2.38%)
FORTSON CONTRACTING, INC.(3.67%)
FRAIRE"S REBAR, INC(5.09%)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(1.15%)
WYLIE DRILLING & DRAINAGE, INC.(6.91%)
Contract # 05143016
Totals 451187.40 19625.00 436545.50 96.7

CountyHILL
Highway CR
From CR 850 @ BR OF AQUILLA CRK
To (MAP #38)
CSJ 0909-37-056
Proj ID BR 2013(960)
Work Type REPL BR & APPRS
 
0.047 191321.10 0.00 184764.80 96.5
CountyHILL
Highway CR
From ON CR 560_@ AQUILLA CREEK
To (MAP #209)
CSJ 0909-37-058
Proj ID BR 2014(196)
Work Type REPL BR & APPRS
 
0.069 265118.95 2728.00 252777.30 95.3
CountyHILL
Highway CR
From CR 893 @ COBB CRK
To (MAP #218) (HCR 3102)
CSJ 0909-37-059
Proj ID BR 2014(197)
Work Type REPL BR & APPRS
 
0.089 229899.15 350.00 214084.00 93.1
Work Order 08-07-14
Work Began 11-19-14
Work Completed  
Time Computed 02-03-15
Contract Working Days 264
Addl Days Granted 0
Working Days Charged 105
Percent Time Used 39
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0909-37-056
ABC EROSION CONTROL, INC.(3.48%)
FORTSON CONTRACTING, INC.(3.61%)
FRAIRE"S REBAR, INC(4.95%)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(5.65%)
WYLIE DRILLING & DRAINAGE, INC.(8.37%)
Contract # 04143027
Totals 686339.20 3078.00 651626.10 94.9

CountyFALLS
Highway CR
From ON CR 198 @ KEECHI
To CRK (MAP #90)
CSJ 0909-38-054
Proj ID BR 1102(567)
Work Type REPL BR & APPRS
 
0.287 1024493.05 0.00 958753.30 93.5
Work Order 04-10-13
Work Began 07-29-13
Work Completed  
Time Computed 06-09-13
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 252
Percent Time Used 78
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0909-38-054
DUSTIN ALLEN, INC. (4.35%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.19%)
TEXAS ALTERNATIVE GRASSER, INC.(1.26%)
Contract # 02133014
Totals 1024493.05 0.00 958753.30 93.5

CountyFALLS
Highway CR
From ON CR 105 @ SOUTH
To COW BAYOU (MAP #2016)
CSJ 0909-38-055
Proj ID BR 1102(565)
Work Type REPL BR & APPRS
 
0.301 899572.80 6090.00 868389.19 100.0
Work Order 05-14-13
Work Began 07-18-13
Work Completed 04-24-15
Time Computed 07-13-13
Contract Working Days 352
Addl Days Granted 0
Working Days Charged 272
Percent Time Used 77
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0909-38-055
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.69%)
SAN-ANN-CO., INC.(1.68%)
ROADWAY SPECIALTIES, INC.(5.54%)
NORTH TEXAS REBAR, LLC (0.26%)
Contract # 03133007
Totals 899572.80 6090.00 868389.19 100.0

CountyFALLS
Highway CR
From CR 221 @ BIG SANDY CRK BR
To (MAP #40)
CSJ 0909-38-072
Proj ID BR 1402(049)
Work Type REPL BR & APPRS
 
0.345 1169676.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 489
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0909-38-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153253
Totals 1169676.10 0.00 0.00 0.0

CountyCORYELL
Highway PW
From @ MOTHER NEFF STATE PARK
To .
CSJ 0909-39-123
Proj ID C 909-39-123
Work Type CONSTR / RECONSTR PARK RD / ACCESS RDS
 
4.800 1385145.26 8680.00 1519374.19 100.0
Work Order 07-17-13
Work Began 01-15-14
Work Completed 04-28-15
Time Computed 01-13-14
Contract Working Days 107
Addl Days Granted 39
Working Days Charged 146
Percent Time Used 100
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0909-39-123
N-LINE TRAFFIC MAINTENANCE, L.P. (1.05%)
D. I. J. CONSTRUCTION, INC.(1.51%)
ABC EROSION CONTROL, INC.(1.46%)
TEXAS ALTERNATIVE GRASSER, INC.(0.31%)
AUSTIN WOOD RECYCLING(1.68%)
JOY LATTIMER, LLC. (1.89%)
Contract # 05133230
Totals 1385145.26 8680.00 1519374.19 100.0

CountyLIMESTONE
Highway CR
From CR 408 @ STEELE CRK RELIEF
To (MAP #117)
CSJ 0909-40-068
Proj ID BR 2014(376)
Work Type REPL BR & APPRS
 
0.100 241319.00 1945.60 240719.00 99.7
CountyLIMESTONE
Highway CR
From CR 408 @ MILLS CREEK
To (MAP #115)
CSJ 0909-40-069
Proj ID BR 2014(378)
Work Type REPL BR & APPRS
 
0.100 504196.60 23837.80 490223.00 97.2
Work Order 09-15-14
Work Began 11-03-14
Work Completed  
Time Computed 11-14-14
Contract Working Days 192
Addl Days Granted 0
Working Days Charged 109
Percent Time Used 56
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0909-40-068
FORTSON CONTRACTING, INC.(2.22%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.81%)
MESA ROD BUSTERS, INC. (0.28%)
SAN-ANN-CO., INC.(0.67%)
Contract # 07143230
Totals 745515.60 25783.40 730942.00 98.0

CountyHILL
Highway FM 933
From FM 1713
To FM 1244 IN WHITNEY
CSJ 1190-01-041
Proj ID STP 2013(688)
Work Type ROW ACQ.; RELOC. ASSIST.
 
2.894 318318.15 0.00 0.00 0.0
CountyHILL
Highway FM 933
From FM 1713
To FM 1244 IN WHITNEY
CSJ 1190-01-043
Proj ID HP 2013(358)
Work Type WDN, GR, STRS & SURF
 
3.002 9598789.16 3500.00 3500.00 0.0
Work Order 02-13-15
Work Began 04-20-15
Work Completed  
Time Computed 04-15-15
Contract Working Days 574
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 1190-01-043
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(1.80%)
ROADWAY SPECIALTIES, INC.(0.98%)
SAN-ANN-CO., INC.(0.38%)
STRIPING TECHNOLOGY, L.P.(0.73%)
TEXOP CONSTRUCTION (0.11%)
Contract # 12143218
Totals 9917107.31 3500.00 3500.00 0.0

CountyLIMESTONE
Highway FM 937
From @ MONTGOMERY CREEK
To (STR #013)
CSJ 1191-04-022
Proj ID BR 2015(077)
Work Type REHAB BR & APPRS
 
1.127 1049361.10 124041.31 491817.03 46.8
Work Order 11-14-14
Work Began 01-15-15
Work Completed  
Time Computed 01-13-15
Contract Working Days 192
Addl Days Granted 0
Working Days Charged 78
Percent Time Used 40
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1191-04-022
DRILL TECH DRILLING & SHORING, INC.(5.41%)
JUST GROOVING, LTD.(0.25%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.28%)
MESA ROD BUSTERS, INC. (0.36%)
RICE ENVIRONMENTAL SERVICES(3.47%)
SAN-ANN-CO., INC.(0.71%)
STRIPING TECHNOLOGY, L.P.(2.00%)
Contract # 09143030
Totals 1049361.10 124041.31 491817.03 46.8

CountyMCLENNAN
Highway FM 185
From SH 317
To SH 6
CSJ 1969-01-017
Proj ID STP 2014(939)
Work Type WDN, GR, BS, SURF, ADD SHLDRS
 
9.119 4636733.87 485028.80 1581245.79 34.1
Work Order 10-02-14
Work Began 11-10-14
Work Completed  
Time Computed 12-01-14
Contract Working Days 255
Addl Days Granted 40
Working Days Charged 123
Percent Time Used 57
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1969-01-017
ALPHA EROSION PRODUCTS, LLC(0.35%)
ROADWAY SPECIALTIES, INC.(3.11%)
COLD CREEK CONSTRUCTION, LTD (0.58%)
FORTSON CONTRACTING, INC.(2.72%)
JOY LATTIMER, LLC. (1.55%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.76%)
TEXAS ALTERNATIVE GRASSER, INC.(1.37%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.95%)
SAN-ANN-CO., INC.(0.99%)
PAVETEX ENGINEERING & TESTING, INC.(0.14%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.10%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.86%)
Contract # 07143234
Totals 4636733.87 485028.80 1581245.79 34.1

CountyMCLENNAN
Highway FM 2311
From FM 2114
To FM 308
CSJ 2174-01-016
Proj ID STP 2015(479)
Work Type WDN, GR, BS, SURF, ADD SHLDRS
 
7.060 3380323.06 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-24-15
Work Began 00-00-00
Work Completed  
Time Computed 08-23-15
Contract Working Days 213
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2174-01-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153019
Totals 3380323.06 0.00 0.00 0.0

CountyBELL
Highway FM 2410
From 822 FT W OF HIGHLAND OAKS
To 686 FT E OF HIGHLAND OAKS
CSJ 2304-02-039
Proj ID STP 2014(781)MM
Work Type ADD TRN LNS
 
0.286 571433.33 137113.94 257457.57 45.0
Work Order 08-13-14
Work Began 02-09-15
Work Completed  
Time Computed 02-09-15
Contract Working Days 192
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 28
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 2304-02-039
FLASHER EQUIPMENT COMPANY(3.00%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.06%)
ROADWAY SPECIALTIES, INC.(3.87%)
Contract # 06143008
Totals 571433.33 137113.94 257457.57 45.0

CountyMCLENNAN
Highway FM 3051
From @ INTERS OF MLK/LAKE BRAZOS PKWY
To .
CSJ 2311-01-037
Proj ID NH 2015(400)
Work Type LANDSCAPE ENHANCE
 
0.200 897015.06 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 107
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2311-01-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153229
Totals 897015.06 0.00 0.00 0.0

CountyBOSQUE
Highway FM 1713
From @ LAKE WHITNEY
To .
CSJ 3228-02-013
Proj ID BR 2015(874)
Work Type REPAINT BRIDGE
 
0.589 2623030.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 213
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MONOKO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 3228-02-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153206
Totals 2623030.00 0.00 0.00 0.0

CountyBELL
Highway FM 3481
From 0.16 MI N OF FM 2410
To 0.50 MI S OF FM 2410
CSJ 3409-01-004
Proj ID STP 2015(481)
Work Type CNSTR LFT TRN LN
 
0.627 1666290.93 0.00 0.00 0.0
CountyBELL
Highway FM 3481
From @ PROSPECTOR TRAIL
To .
CSJ 3409-01-005
Proj ID CC 3409-1-5
Work Type INSTL TRAF SIG
 
0.002 124152.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-24-15
Work Began 00-00-00
Work Completed  
Time Computed 08-23-15
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3409-01-004
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153023
Totals 1790442.93 0.00 0.00 0.0

CountyMCLENNAN
Highway FM 2837
From IH 35
To 0.2 MI W OF IH 35
CSJ 3521-01-016
Proj ID STP 2014(782)
Work Type INTERS IMPRVMT
 
0.360 1787727.68 2500.00 289833.06 16.2
Work Order 08-20-14
Work Began 09-15-14
Work Completed  
Time Computed 09-15-14
Contract Working Days 127
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 15
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3521-01-016
N-LINE TRAFFIC MAINTENANCE, L.P. (0.49%)
STRIPING TECHNOLOGY, L.P.(1.95%)
SAN-ANN-CO., INC.(0.53%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (6.21%)
Contract # 06143027
Totals 1787727.68 2500.00 289833.06 16.2